This is a Performance Work Statement (Section 024200) for site demolition, removal, and recycling work as part of the Excess Non-Accelerator Facilities Demolition Phase 1 project at Fermilab, dated October 2024.
The work scope encompasses complete demolition and removal of existing buildings, structures, hardstands, paved areas, vaults, sheds, fences, steps, foundations, and retaining walls to a depth of eighteen inches below grade. The subcontractor must identify and document all existing underground utilities (both active and abandoned) in coordination with Fermilab's GIS personnel, verify disconnection and proper sealing of utility connections, and is prohibited from using blasting methods. Prior to demolition, Fermilab will perform testing and abatement for contaminants such as lead-based paint and asbestos, though the subcontractor must notify the Construction Coordinator of any suspect materials encountered during work. The subcontractor must coordinate with Fermilab for removal of specific items including light fixture ballasts and lamps, fire extinguishers, smoke detectors, fire alarm panels, telephone handsets, and lockset cylinders. A certified EPA-registered refrigerant recovery service is required, with all recovered refrigerant turned over to Fermilab. The subcontractor must recycle or salvage at least fifty percent of non-hazardous construction and demolition materials and provide documentation of recycling quantities. Additional requirements include maintaining erosion control measures throughout the project, protecting existing people and property with temporary bracing and barricades, filling sites to original grade with suitable material, maintaining existing drainage patterns, preventing debris from leaving the construction site with daily roadway cleaning, and seeding disturbed areas with IDOT Class 2 Roadside grass mixture at 200 lbs/acre upon completion.
View the file
Other files
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Excess Non-Accelerator Facilities Demolition Phase 1 October 2024
SITE DEMOLITION, REMOVAL, 024200-1
AND RECYLING
SECTION 024200 – SITE DEMOLITION, REMOVAL, AND RECYCLING
PART 1 GENERAL
1.01 SCOPE OF WORK: This section includes the general requirements for the demolition of existing infrastructure; including protection of existing trees, monuments, benchmarks, and natural features of the site to remain, identification and documentation of existing underground utilities, removal and recycling of material, and site cleanup and restoration.
1.02 RELATED WORK: The following sections include items of related work. Coordinate work prescribed by this section with work prescribed by these sections:
A. Section 010010 – General Requirements
B. Section 013100 – Environment, Safety, and Health Requirements
C. Section 013300 – Submittals
D. Section 014100 – Quality Requirements
1.03 APPLICABLE STANDARDS: The publications listed below form part of this section. Each publication shall be the latest revision and addendum in effect on the date of the subcontract award, unless noted otherwise. Except as specifically modified by the requirements specified herein or the details on the drawings, the work included under this section shall conform to the provisions of these publications:
A. The Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA)
B. Resource Conservation and Recovery Act (RCRA)
C. Illinois Department of Transportation (IDOT) – Standard Specifications for Road and Bridge Construction, Adopted January 1, 2007.
1.04 SUBMITTALS: Submittal documentation shall be in accordance with Section 013300 - Submittals.
1.05 QUALITY ASSURANCE AND CONTROL
A. Subcontractor shall be responsible for quality control and construction inspection in accordance with the requirements of Section 010010 – General Requirements, Article 3.3.
B. All work is subject to Final Acceptance by Fermilab. Strict conformance to the drawings and specifications shall be required.
SITE DEMOLITION, REMOVAL, 024200-2
AND RECYLING
PART 2 PRODUCTS
NOT USED
PART 3 EXECUTION
3.01 SITE CONTAMINATION AND ASSESSMENT
A. Perform a physical or visual examination of the site, including examination of existing structures for structural integrity and other potential hazards, prior to commencing demolition activities.
B. Fermilab will test for the presence of various contaminants such as lead-based paint and asbestos, and perform abatement work as necessary.
However, the Subcontractor shall notify the Fermilab Construction Coordinator if any suspect materials are encountered during demolition, that may have been missed during the initial assessment.
3.02 EROSION CONTROL
A. All soil erosion and sediment control measures shall be properly installed and functioning prior to, and during, demolition activities.
B. The Subcontractor shall provide and maintain all temporary erosion control measures during the entire period of demolition. The Subcontractor shall remove all measures upon completion of the Work unless specifically noted otherwise.
C. The Subcontractor shall take necessary precautions to prevent debris from leaving the construction site and shall clean adjacent roadways of tracked debris on a daily basis.
3.03 IDENTIFICATION OF EXISTING UNDERGROUND UTILITIES
A. Prior to starting demolition, the Subcontractor shall verify the locations of all existing underground active and abandoned utilities.
B. The Subcontractor shall ensure that all existing utility connections to the structure to be removed have been disconnected and properly sealed and secured.
3.04 DOCUMENTATION OF EXISTING UNDERGROUND UTILITIES
A. The Subcontractor shall coordinate with Fermilab’s GIS personnel to document the locations of any existing underground utilities or structures encountered outside of the known locations.
B. The Subcontractor shall also coordinate with Fermilab’s GIS personnel to document locations of all abandoned utility lines.
3.05 DEMOLITION OF EXISTING ABOVE GROUND ITEMS
SITE DEMOLITION, REMOVAL, 024200-3
AND RECYLING
A. The Subcontractor shall demolish and remove completely all buildings, structures, hardstands, paved areas adjacent thereto, vaults, sheds, fences, steps, foundations, and retaining walls to a depth of eighteen (18”) inches below grade.
B. The Subcontractor is prohibited from using blasting methods to demolish existing structures.
C. The Subcontractor shall coordinate with the Fermilab Construction Coordinator, prior to demolition, for removal of the following items by Fermilab:
1. Light fixture ballasts and lamps (magnetic core ballasts shall be salvaged and reused by Fermilab);
2. Fire extinguishers and smoke detectors;
3. Fire alarm panels;
4. Telephone handsets; and,
5. Lockset cylinders.
D. The Subcontractor shall provide a certified refrigerant recovery service. All refrigerant to remain onsite. The Subcontractor shall provide proof of EPA Refrigerant Recovery Certification, shall recover refrigerant, and turn over to Fermilab. Tanks for the refrigerant shall be provided by Fermilab. The Subcontractor shall also be responsible for completing the Refrigerant Service Order Form.
3.06 RECYCLING OF EXISTING MATERIALS
A. The Subcontractor shall recycle or salvage at least fifty percent (50%) of the non-hazardous construction, demolition, and land clearing materials, excluding soil, for compliance with DOE Guiding Principles.
B. The Subcontractor shall make reasonable efforts to salvage the demolished material and provide backup documentation of either a sale or donation of the material.
C. If it is not reasonable to salvage the material, the Subcontractor shall use a vendor that monitors and documents the quantities of material recycled as a percentage of the total material removed from the demolition site. The Subcontractor is responsible for submitting this documentation to the Fermilab Construction Coordinator.
3.07 PROTECTION OF EXISTING PEOPLE AND PROPERTY
The Subcontractor shall erect and maintain temporary bracing, shoring, lights, barricades, baffles, curtains, signs, and other measures as necessary to protect Fermilab employees, workers, and adjacent structures from damage from demolition work.
3.08 HARDSTAND AND FILL MATERIALS
SITE DEMOLITION, REMOVAL, 024200-4
AND RECYLING
The Subcontractor shall fill the existing site up to the original grade with suitable fill material. If suitable fill is not available in the immediate area, it may be available from a remote Fermilab stockpile.
3.09 SITE DRAINAGE
The Subcontractor shall maintain existing overland flow drainage routes throughout the demolition project and shall not prohibit the flow of storm water from retaining these flow patterns.
3.10 VEGETATION
Once the demolition work has been completed and the site has been backfilled and finish graded, the Subcontractor shall seed the disturbed area with IDOT Class 2 Roadside grass mixture, applied at 200 lbs. / acre.
3.11 SITE CLEANUP
A. The Subcontractor shall remove all debris and equipment and dispose of all materials from the site of work, and leave the ground clear of all materials, rubbish or debris, and in a clean and neat condition, as demolition of each structure is completed.
B. The Subcontractor shall take necessary precautions to prevent debris from leaving the construction site and shall clean adjacent roadways of tracked debris on a daily basis.
END OF SECTION 024200