This is a Statement of Work for the Excess Non-Accelerator Facilities Demolition Phase 1 project at Fermi National Accelerator Laboratory, managed by Fermi Forward Discovery Group, LLC for the U.S. Department of Energy Office of Science. The project (ISD Project Number 13-1-69) requires demolition of two residential structures—the Site 50 house and Site 55 house—located throughout the Fermilab site in DuPage County, Illinois. The subcontractor must furnish all required supervision, labor, materials, tools, equipment, and services to complete the work in accordance with drawing set "13-1-69_Demo GPP_Final Design" dated September 23, 2025, and associated project manual specifications. Work scope includes demolition of both structures, proper termination or rerouting of existing utilities, and backfill with suitable soil material upon completion of building removal. All costs for transportation, overhead, bonding, insurance, safety oversight, quality control, and supervision are included in the subcontractor's proposal.
The project is scheduled for completion within 154 calendar days from Notice to Proceed, with Milestone 0 marking the start of construction work and Milestone 1 at calendar day 154 requiring project completion and submittal of approved closeout documents. All personnel working at Fermilab must provide Real ID and obtain badging from the Fermilab Badging Office. All construction traffic must enter and exit the Fermilab site via the Wilson Street entrance. The subcontractor is responsible for all quality control activities and compliance with Subcontract documents, with a Fermilab Construction Coordinator assigned to oversee the project in accordance with Specification section 010010 (General Requirements) and section 014100 (Quality Requirements).
View the file
Other files
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1 1
STATEMENT OF WORK
Excess Non-Accelerator Facilities Demolition
Phase 1
- Demolition of Sites 50 and 55 ISD Project Number: 13-1-69
Version History
11/10/2025 Initial Release
Fermi National Accelerator Laboratory 2
STATEMENT OF WORK
Excess Non-Accelerator Facilities Demolition Phase 1
- Demolition of Sites 50 and 55
13-1-69
Introduction and Background:
Following through with the Lab’s strategic plan and major initiatives requires investment in demolitions to reduce the Lab’s excess facility operation burdens and to concentrate personnel and equipment for more efficient teamwork. This Program aligns with the FNAL Campus Master Plan by making progress towards campus objectives to consolidate, centralize, and modernize site infrastructure.
Scope of Work:
Provide all work as shown on drawing set “13-1-69_Demo GPP_Final Design”, dated September 23, 2025, with associated project manual specifications.
The subcontractor shall furnish all required supervision, labor, materials, tools, plant, and appurtenances necessary to perform diligently and fully all work as described in the drawings and technical specifications. All work includes transportation, overhead, bonding costs, insurance, safety oversight, quality control oversight, and supervision as required to construct the project described in the drawings and technical specifications.
The Subcontractor’s scope of work is not limited to the general work outline described below. The Subcontractor shall perform all work required to complete the construction work in accordance with the drawings and/or specifications. The description listed below are general in nature and are only intended to describe the range and complexity of this scope of work. The description provided below are not to be used as the basis for establishing a cost proposal. Specific quantities and definitions of the scope of work for providing a proposal shall be based solely on estimates developed by the Offer from the drawings, specifications, and the information obtained from examining of the project site.
1. Base Proposal Work for excess non-accelerator facilities demolition phase 1 will include:
a. Demolition work, including:
i. Demolition of Site 50 house and Site 55 house.
ii. Properly terminate/reroute existing utilities.
iii. Backfill with suitable soil material upon completion of building removal.
Deliverables:
The Subcontractor shall perform all work required to complete the construction work in accordance with the drawings and/or specifications.
Quality Assurance:
A Fermilab Construction Coordinator will be assigned to this project. See Specification section 010010, GENERAL REQUIREMENTS.
The Subcontractor is responsible for all activities necessary to manage, control, and document that work complies with the Subcontract documents. The Subcontractor’s responsibility includes ensuring adequate Quality Control services are provided for work accomplished on- and off-site by his/her organization, suppliers, Fermi National Accelerator Laboratory 3 sub-tier contractors, technical laboratories, and consultants. See Specification section 01 41 00 QUALITY
REQUIREMENTS.
Security:
All personnel working at Fermilab are required to provide Real ID and obtain badging from the Fermilab Badging Office.
Place of Performance:
The demolitions are located throughout the Fermilab site in DuPage County. All construction traffic shall enter and exit the Fermilab site via the Wilson Street entrance. Refer to the drawings for the specific location.
Schedule/Period of Performance:
1. Milestone 0 - Calendar Day 0 – NTP, this milestone marks the point where construction work may begin;
2. Milestone 1 – Calendar Day 154 – Project Complete, submittal & approval of all closeout documents