This Statement of Work (SOW) details the MI-65 transfer piping project for Fermi National Accelerator Laboratory, managed by FermiForward for the U.S. Department of Energy Office of Science. The project involves demolishing and rebuilding piping connecting two tanks within the MI-65 service building, replacing existing double-wall PVC piping with welded stainless steel piping and flanged valves, constructed to ASME B31.3 and FESHM 5031.1 requirements.
The subcontractor's scope includes demolition of existing piping, submission of welder qualification records, performing coupon welds, welding the new piping system (with 10% of welds examined by FermiForward), and hydrostatic system testing. The project timeline spans 105 calendar days, with key milestones including Notice to Proceed (0 days), material submittals (14 days), piping installation and testing (90 days), and project completion (105 days). This is a small business set-aside solicitation under NAICS code 332996 with a size standard of $45.0 Million, and a pre-proposal meeting is scheduled for May 01, 2025.
View the file
Other files
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MI-65 Transfer Piping Statement of Work (SOW)
Revision 1 January 31, 2025
Statement of Work: New Task Release for Final Design of CUB Upgrades ISD Engineering
Fermi National Accelerator Laboratory 2
1. SCOPE OF SERVICES
1.1 Description
The MI-65 transfer piping project shall demolish and rebuild piping that connects two tanks within the MI-65 service building. The existing piping system consists of double wall PVC piping, bulk head fittings, valves, and fittings. The new replacement piping system consists of welded stainless steel piping and flanged valves, constructed to the requirements of ASME B31.3 and
FESHM 5031.1.
1.2 Scope
The subcontractor shall perform the following scope of work to provide FermiForward with a fully functioning piping system at MI-65.
1.2.1 CONSTRUCTION WORK
The subcontractor shall perform the following work:
1. Demolition of existing double wall PVC Piping connecting the two tanks within MI-65 in accordance with FermiForward disposal of materials. FermiForward shall inspect demolished piping prior to disposal.
2. Submission of Welder Qualification Record complying with specification section SS-9-
002, or alternate qualification record meeting or exceeding specification section SS-9-
002.
3. Welding a coupon weld in the presence of FermiForward’s authorized representative.
4. Welding the new piping system with at least 10% of the welds examined by
FermiForward’s authorized representative.
5. Hydrostatically testing the system upon completion of assembly.
1.3 Activities and Timeline
1.3.1 TIMELINE
The subcontractor shall comply with the following timeline:
1. Milestone 0 – 0 Calendar Days – Notice to Proceed (NTP). This milestone marks the point where construction work may begin;
2. Milestone 1 – 14 Calendar Days – All material submittals;
3. Milestone 2 – 90 Calendar Days – Complete with punch-list items remaining, piping installed and tested and placed into operations.
4. Milestone 3 – 105 Calendar Days - Project Complete
1.4 Fee Breakdown
FermiForward requests that the subcontractor submit the proposed fee broken out in the following way:
• Total cost