Exhibit_1_-_Time_&_Materials_(T&M)_Work_Authorization_Form.pdf
PDF 173 KB Posted
- Solicitation number
- 012-3044004-EB
- Issued by
- Orange County, San Francisco City, California
About this file
This is a Time & Materials (T&M) Work Authorization Form for the Mile Square Northeast Area Smart Irrigation Controller Upgrade project administered by the County of Orange, California. The form documents authorized work tasks including re-wiring with dedicated low-voltage wire runs and trenching for new wire paths, with a critical requirement that each valve must have a dedicated wire run and wire splitting is prohibited. The form provides structured tracking for valve/station numbers, trenching footage, wiring footage, materials used, and total material costs, with blank rows for data entry and totals summation. The contractor must certify that no wiring was split or shared between valves and that each valve serviced has a dedicated lead to the controller with WeatherTRAK site map updates. County Project Manager approval is required to verify that performed work and listed materials/measurements meet project specifications.
The form functions as a billing and verification document within the larger smart irrigation controller installation contract that includes firm fixed-fee components for equipment and labor, with T&M work items available for field wiring repairs. This authorization mechanism allows for documented tracking of additional work beyond the base contract scope while maintaining strict compliance with project specifications regarding dedicated wiring architecture. The dual signature requirement—contractor certification and County Project Manager approval—establishes accountability for both work performed and material costs, ensuring alignment with the overall project requirements for the WeatherTRAK OptiFlow XR smart irrigation controller system installation at Mile Square Regional Park.
View the file
Other files
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Exhibit 1: Time & Materials (T&M) Work Authorization Form
Project: Mile Square Northeast Area Smart Irrigation Controller Upgrade
Work Order #: [Internal Number] | Date: [Date of Work]
1. Work Description
In accordance with the Project Scope, the following tasks are authorized for T&M compensation:
• Re-wiring: Installation of dedicated low-voltage wire runs (no splitting/doubling).
• Trenching: Excavation required for new wire paths.
2. Time & Material Tracking
Note: Each valve must have a dedicated wire run. Splitting wires is prohibited.
Valve / Station #
Trenching
(LF)
Wiring
(LF)
Materials Used (Valves, etc.)
Total Material Cost
Ex: Station 2
Controller C 45 $
Ex: Station 5
Controller H 55 $
Ex: Station 4 1 Valve $
Valve / Station #
Trenching
(LF)
Wiring
(LF)
Materials Used (Valves, etc.)
Total Material Cost
TOTALS [Sum] LF [Sum]
LF
$0.00
4. Contractor Certification & Field Verification
The Contractor certifies that no wiring was split or shared between valves. Each valve serviced above has a dedicated lead to the controller and has been updated on the WeatherTRAK site map.
Contractor Representative: _______________________ Date: __________
5. County Project Manager Approval
I have verified the work performed and the materials/measurements listed above meet the project specifications.
County Project Manager: _____________________________ Date: __________
Exhibit 1: Time & Materials (T&M) Work Authorization Form
File details come from the government source that posted it. Updated .