This is a Statement of Work for the procurement of precast concrete shield blocks for the PIP-II Project at Fermilab. The Fermi Forward Discovery Group (FFDG) is requesting proposals for fifty-eight (58) precast concrete blocks comprising seven different types: Type A (14 units), Type C (3 units), Type D (7 units), Type E (4 units), Type H (11 units), Type K (10 units), and Type L (9 units). The subcontractor must manufacture all blocks in accordance with ISD 13-2-40 Drawings and Specification 03410 and deliver them to Fermilab.

The subcontractor is responsible for all supervision, labor, materials, tools, plant, transportation, overhead, bonding costs, safety oversight, and quality control necessary to complete the work. The project timeline includes four milestones: Milestone 0 (Purchase Order Issued—work may begin); Milestone 1 (14 calendar days—submittals due); Milestone 2 (70 calendar days—complete and delivery); and Milestone 3 (84 calendar days—project complete including acceptance of as-built drawings). Manufacturing will occur at the subcontractor's production facility with coordination on delivery location to be arranged with Fermilab prior to delivery. All personnel working at Fermilab must provide Real ID and obtain badging from the Fermilab Badging Office. Proposals must include detailed pricing breakdown by block type. No materials or equipment will be furnished by FFDG.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Page | 1

STATEMENT OF WORK

13-2-40 PIP-II BTL SHIELD BLOCKS

Request for Proposal for procurement of precast concrete shield blocks for the PIP-II Project.

Introduction and Background

Fermi Forward Discovery Group (FFDG) is requesting a proposal for fifty-eight (58) precast concrete blocks. Proposal to include a breakdown detail of pricing per Block Type.

Scope of Work

Provide all work as shown on the ISD 13-2-40 Drawings and Specification 03410, “Precast Concrete Shield Blocks” to manufacture and deliver to Fermilab the following type and quantity of precast concrete shield blocks:

Block Type Quantity A 14 C 3 D 7 E 4 H 11 K 10 L 9

Refer to project drawings for specific details for each block type.

The Subcontractor shall furnish all required supervision, labor, materials, tools, plant and appurtenances necessary to perform diligently and fully all work as described in the drawings and technical specifications. All work includes transportation, overhead, bonding costs, safety oversight, quality control oversight, and supervision as required to deliver the project described in the drawings and technical specifications. Work to include transportation and delivery of the blocks to Fermilab.

Deliverables

The Subcontractor shall perform all work required to complete the work in accordance with the drawings and/or specifications.

Quality Assurance

The Subcontractor is responsible for all activities necessary to manage, control, and document that work complies with the Subcontract documents. The Subcontractor’s responsibility includes ensuring adequate Quality Control services are provided for work accomplished on- and off-site by his/her organization, suppliers, sub-tier contractors, technical laboratories, and consultants.

Government – Furnished Property

There will be no materials or equipment furnished by FFDG.

Page | 2

Security

All personnel entering and/or working at Fermilab are required to provide Real ID and obtain badging from the Fermilab Badging Office.

Place of Performance

The blocks will be manufactured at the Subcontractors production facility and delivered to Fermilab for offloading. On-site location to be coordinated with Fermilab prior to delivery.

Schedule/Period of Performance

This project includes the following milestones:

Milestone 0 – 0 Calendar Days - Purchase Order Issued, this milestone marks the point where work may begin;

Milestone 1 – 14 Calendar Days – Submittals;

Milestone 2 – 70 Calendar Days – Complete (delivery).

Milestone 3 – 84 Calendar Days - Project Complete

The executed purchase order represents the basis of the start of project duration. The Project Complete milestone marks the completion of the project including acceptance of as-built drawings and if required, submittals.

There will be no materials or equipment furnished by FFDG.
A. This project includes the following milestones:
1. Milestone 0 – 0 Calendar Days - Purchase Order Issued, this milestone marks the point where work may begin;
2. Milestone 1 – 14 Calendar Days – Submittals;
3. Milestone 2 – 70 Calendar Days – Complete (delivery).
4. Milestone 3 – 84 Calendar Days - Project Complete

B. The executed purchase order represents the basis of the start of project duration. The Project Complete milestone marks the completion of the project including acceptance of as-built drawings and if required, submittals.