This document contains site maps and detailed pad specifications for Base Camp Victory, located at approximately 37°53'25.1"N 81°06'40.2"W. The facility comprises seven designated pads (PAD 1 through PAD 7) requiring various ground preparation and site development work.
The pads range in size from approximately 0.4 acres to 2 acres and have the following specific requirements: PAD 1 (~2 acres) requires grading of all gravel in the inner area; PAD 2 (~1.5 acres) requires spreading and compaction of all gravel; PAD 3 (~0.4 acres) requires compaction of all gravel; PAD 4 (~0.4 acres) requires movement of rip-rap and grading plus compaction of all gravel; PAD 5 (~0.6 acres) requires compaction of all gravel; PAD 6 (~0.4 acres) requires grading and compaction of all gravel; and PAD 7 acreage is not specified but is shown on the site map. Additionally, a pedestrian walkway (marked in yellow) connecting PADs 2, 3, and 4 requires development. The document provides aerial imagery with color-coded overlays identifying the specific areas within each pad requiring work, enabling contractors to assess scope and develop accurate cost estimates for site preparation activities.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| BID OPENING ABSTRACT.pdf | ||
| Questions and Answers for Solicitation 10 june 2026.docx | DOCX document | |
| SITE VISIT SIGN IN.pdf | ||
| Questions and Answers for Solicitation 9 june 2026.pdf | ||
| Site Visit -VBSA EXCAVATION AND GRAVEL WORK FINAL.pptx | PPTX presentation | |
| WD WV20260102 REV 1 DTD 18 MAY 2026.pdf | ||
| Statment of Work Excavation and Gravel Work FINAL.docx | DOCX document | |
| DAVIS BACON WAGES WV102 MAY 2026.pdf | ||
| Solicitation - W912L826BA001.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Locations of Interest:
• Base Camp Victory
Base Camp Victory
Base Camp Victory
Approximate Location:
37°53'25.1"N 81°06'40.2"W
PAD 1
PAD 2
PAD 3
PAD 4
PAD 5
PAD 6
PAD 7
PAD 1
~2 acres
PAD 1
Requires grading of all gravel in (Yellow) inner area
PAD 2
~1.5 acres
PAD 3
PAD 4
~0.4 acres
~0.4 acres
PAD 5
~0.6 acres PAD 2
PAD 3
PAD 5
PAD 4
Pedestrian Walkway (yellow) connecting pads 2, 3, and 4
Requires spreading and compaction of all gravel in
(Red) inner area
Requires compaction of all gravel in (Green) inner area
Requires movement of rip-rap and grading + compaction of all gravel in (Purple) inner area
PAD 7
PAD 6
~0.4 acres
PAD 6
Requires grading + compaction of all gravel in
(Gold) inner area