ESBD_522306_1782823872379_Addendum 1 26CSP006.pdf
PDF 1 MB Posted
- Attached to
- CS3 CP2000534 26CSP006 Structural and Electrical Repairs State and local contract opportunity
- Solicitation number
- 26CSP006
- Issued by
- Travis County, Austin City, Austin City, Austin City, Austin City, Texas
About this file
This is Addendum No. 1 to a Request for Proposal issued by The University of Texas at Austin, Planning, Design and Construction division, for structural and electrical repairs at Central Chilling Station No. 3 (CS3), Contract 26CSP006, Project CP2000534. The addendum was issued on June 30, 2026, and becomes an integral part of the original RFP documents dated June 3, 2026, taking precedence over conflicting specifications and drawings. The addendum addresses a clarification question received after the pre-proposal conference regarding micropile steel casing specifications. Proposals for this project were due July 16, 2026. The project involves repairs to a continuously operational university facility and requires contractor experience with complex facilities maintaining operations during construction. A mandatory pre-proposal conference was held June 12, 2026, with a second site visit scheduled for June 17, 2026 at 10:00 a.m. Questions and addenda requests were due June 23, 2026 at noon.
The addendum clarifies that the intended steel casing pipe for micropiles is an 8-inch nominal Schedule 80 steel pipe with an inner diameter of 7 5/8 inches and a wall thickness of 0.5 inches. A mandatory VetHUB subcontracting plan demonstrating good-faith effort to recruit and utilize Texas-certified service-disabled veteran businesses is required, with responses lacking a completed plan rejected as material failures to comply. Contractors must divide work into reasonable lots and notify a minimum of two certified VetHUBs for each subcontracting opportunity in writing, allowing at least seven business days for response. Key personnel, including the project superintendent and project manager, must maintain current 30-hour OSHA certification and commit to the project for its duration unless an equally qualified substitute receives owner approval. Evaluation criteria assess contractor qualifications (maximum 65 of 100 points), experience with similarly complex facilities, OSHA safety records, project execution plans, quality control programs, and warranty support. The subcontracting plan becomes part of the awarded contract and may not be modified without prior written approval from UT Austin's Vendor Management Office.
View the file
Other files for this state and local contract opportunity
| File | Type | Posted |
|---|---|---|
| ESBD_522306_1780500483432_Link to RFP CS3 CP2000534 26CSP006.pdf | ||
| ESBD_522306_1781526236029_26CSP006 Preproposal Sign-in--.pdf | ||
| ESBD_522306_1780500658401_Section 8.docx | DOCX document | |
| ESBD_522306_1781787389238_26CSP006 2nd Site Visit--.pdf | ||
| ESBD_522306_1781623033178_26CSP006-CS-3-Pre-Proposal Slides_20260612.pptx | PPTX presentation | |
| ESBD_522306_1780500599833_Link to Drawings CS3 CP2000534 26CSP006.pdf | ||
| ESBD_522306_1780500766495_Exhibit H with SP and PAR (0526).pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
THE UNIVERSITY OF TEXAS AT AUSTIN
Planning, Design and Construction
1301 E. Dean Keeton Street, FC1 • Austin, Texas 78722 • H9610 • 512-471-3042 https://construction.utexas.edu/
CS3 CP2000534 06302026 ADD1-1
June 30, 2026
ADDENDUM:
To: All Specification Holders
Via: Trina Bickford, Assistant Director, Contracts
From: Logan Golla, Project Manager
Re: ADDENDUM NO. 1 to the Request for Proposal Documents for
Structural and Electrical Repairs Central Chilling Station No. 3 (CS3)
Contract 26CSP006 Project # CP2000534
This Addendum is a part of the Documents for the above-named project and shall become an integral part of the originally issued Request for Proposal Documents dated 6/3/2026. Wherein the items of Addenda differ from the original Specifications and/or Drawings, this Addendum shall take precedence. All other terms and conditions not specifically affected by this Addendum will remain unchanged. Revise the Specifications and Drawings referenced below as described. This Addendum contains sheets ADD1-1, Attachment: ‘Pile Casing Clarification’.
The Bidder shall acknowledge receipt of this Addendum by inserting its number in the Proposal Form.
I. CLARIFICATIONS
QUESTIONS/ANSWERS: The following question was received after the Pre-Proposal Conference. Answers are inserted.
Question # 1: Is steel casing pipe 7-5/8” diameter, ½” wall thickness grade 80 allowed for micropiles? (see attachment) Response: The intended steel casing pipe for the micropile is an 8” nominal schedule 80 steel pipe, with an inner diameter of 7 5/8” and wall thickness of 0.5”.
END OF ADDENDUM NO. 1
1. Question: Is steel casing pipe 7-5/8” diameter, ½” wall thickness grade 80 allowed for micropiles?
Response: The intended steel casing pipe for the micropile is an 8” nominal schedule 80 steel pipe, with an inner diameter of 7 5/8” and wall thickness of 0.5”.
Date : 06/25/26
Regarding : UTA CS3, Micropile steel casing size clarification
Job Number : 2025-0072
Bidder Question Response Inspire. Create. Deliver.