ESBD_374441_1724692143764_ATTACHMENT G.P - Ellington Field (EF) Contract Closeout.pdf

PDF 147 KB Posted

Attached to
Hush House Transformer Replacement
Solicitation number
TMD24-ANG-WJ-24150007
Issued by
Harris County, Texas

About this file

This document is the Attachment G.P - Ellington AFB (EF) Contract Closeout for a state and local contract opportunity. The attachment outlines the procedures for the final acceptance and closeout of the Ellington Field project, including pre-final inspections, training and instruction, final inspections, closeout procedures, final cleaning, project record documentation, operation and maintenance data, warranties, and the provision of spare parts and maintenance materials. The attachment details the responsibilities of the Construction Contractor and the Project Manager throughout the closeout process, as well as the potential consequences of excessive deficiencies found during inspections.

The document specifies the required content and format for the project record documents, operation and maintenance data, and warranties to be provided by the Construction Contractor. It also outlines the adjustments and final cleaning required prior to the project's completion and final acceptance.

View the file

Other files

File Type Posted
ESBD_374441_1724693925873_ATTACHMENT G.3 TMD Standard Terms and Conditions.pdf PDF
ESBD_374441_1724690404606_ATTACHMENT G.B - Ellington Field (EF) Coordination And Meetings.pdf PDF
ESBD_374441_1724691507659_ATTACHMENT G.F.2 - Ellington AFB (EF) Contractor Hazardous Material Identification Form Close-Out Procedures.pdf PDF
ESBD_374441_1724692432692_ATTACHMENT G.W - Ellington AFB (EF) AF103_REV.pdf PDF
ESBD_374441_1724690583036_ATTACHMENT G.F.1 - Ellington AFB (EF) Contractor Hazardous Material Usage Data.pdf PDF
ESBD_374441_1724691790419_ATTACHMENT G.J - Ellington Field (EF) Operation And Maintenance Data.pdf PDF
ESBD_374441_1724692312038_ATTACHMENT G.T - Ellington Field (EF) Post Award Submittals.pdf PDF
ESBD_374441_1724692020055_ATTACHMENT G.M - Ellington AFB (EF) Material Equipment.pdf PDF
ESBD_374441_1724692121362_ATTACHMENT G.O - Ellington Field (EF) Starting Of Systems.pdf PDF
ESBD_374441_1724690507683_ATTACHMENT G.D - Ellington AFB (EF) Field Engineering.pdf PDF
ESBD_374441_1724690315307_ATTACHMENT G.1 Direct Deposit Authorization Form.pdf PDF
ESBD_374441_1724692161504_ATTACHMENT G.Q - Ellington AFB (EF) Cutting And Patching.pdf PDF
ESBD_374441_1724691956363_ATTACHMENT G.K - Ellington AFB (EF) Construction Facilities And Temporary Controls.pdf PDF
ESBD_374441_1724691815157_ATTACHMENT G.J.1 - Ellington AFB (EF) Maintenance Summary Form.pdf PDF
ESBD_374441_1724692399005_ATTACHMENT G.V - Ellington Field (EF) Houston Texas Standard Operating Procedure (Sop) For Inadvertent Discovery Of Unmarked Burials.pdf PDF
ESBD_374441_1724692037243_ATTACHMENT G.N - Ellington Field (EF) Manufacturers’ Services.pdf PDF
ESBD_374441_1724690553865_ATTACHMENT G.F - Ellington Field (EF) EMS Hazardous Material Procedures.pdf PDF
ESBD_374441_1724690355671_ATTACHMENT G.4 Pricing Schedule.pdf PDF
ESBD_374441_1725392781473_ESBD Addendum 2 - TMD24-ANG-WJ-24150007.pdf PDF
ESBD_374441_1724691712762_ATTACHMENT G.I - Ellington Field (EF) Houston Texas Standard Operating Procedure (Sop) For Inadvertent Discovery Of Cultural Materials.pdf PDF
ESBD_374441_1724694211190_ESBD Addendum 1 - TMD24-ANG-WJ-24150007.pdf PDF
ESBD_374441_1724692143764_ATTACHMENT G.P - Ellington Field (EF) Contract Closeout.pdf PDF
ESBD_374441_1724690368368_ATTACHMENT G.5 Photo of Hush House Transformer and new ALAMO Transformer.pdf PDF
ESBD_374441_1724692447571_ATTACHMENT G.X - Ellington AFB (EF) AF3000.pdf PDF
ESBD_374441_1724690540926_ATTACHMENT G.E - Ellington Field (EF) Safety Policies And Procedures.pdf PDF
ESBD_374441_1724692509041_ATTACHMENT G.Y - ELLINGTON AFB (EF) Form 17 - VISITOR CONTRACTOR PASS REQUEST (01OCT23).pdf PDF
ESBD_374441_1724692099667_ATTACHMENT G.N.1 - Ellington Field (EF) Manufacturer’s Certificate Of Proper Installation.pdf PDF
ESBD_374441_1724691998089_ATTACHMENT G.L - Ellington Field JRB Final Asbestos Abatement Report Template.pdf PDF
ESBD_374441_1724690490077_ATTACHMENT G.C - Ellington AFB (EF) Project Coordination.pdf PDF
ESBD_374441_1724691612581_ATTACHMENT G.H - Ellington Field (EF) EMS Environmental Protection.pdf PDF
ESBD_374441_1724692341515_ATTACHMENT G.U - Ellington Field (EF) Sustainable Design Requirements.pdf PDF
ESBD_374441_1724692242063_ATTACHMENT G.S - Ellington AFB (EF) Substitutions Request Form.pdf PDF
ESBD_374441_1724691585489_ATTACHMENT G.G - Ellington AFB (EF) Quality Control.pdf PDF
ESBD_374441_1724690331895_ATTACHMENT G.2 Application for Texas Identification Number.pdf PDF
ESBD_374441_1726259554868_Addendum 3 - TMD24-ANG-WJ-24150007.pdf PDF
ESBD_374441_1724692217506_ATTACHMENT G.R - Ellington Field (EF) EMS Construction Waste Management And Disposal Part 1 - General.pdf PDF
ESBD_374441_1724690388476_ATTACHMENT G.A - Ellington Field (EF) General Requirements.pdf PDF
ESBD_374441_1725392736305_TMD24-ANG-WJ-24150007 Hush House Transformer Replacement.pdf PDF
ESBD_374441_1724691585489_ATTACHMENT G.G - Ellington AFB (EF) Quality Control.pdf PDF
ESBD_374441_1726259554868_Addendum 3 - TMD24-ANG-WJ-24150007.pdf PDF
ESBD_374441_1725392736305_TMD24-ANG-WJ-24150007 Hush House Transformer Replacement.pdf PDF
ESBD_374441_1724692020055_ATTACHMENT G.M - Ellington AFB (EF) Material Equipment.pdf PDF
ESBD_374441_1724692447571_ATTACHMENT G.X - Ellington AFB (EF) AF3000.pdf PDF
ESBD_374441_1724690315307_ATTACHMENT G.1 Direct Deposit Authorization Form.pdf PDF
ESBD_374441_1724692161504_ATTACHMENT G.Q - Ellington AFB (EF) Cutting And Patching.pdf PDF
ESBD_374441_1724691790419_ATTACHMENT G.J - Ellington Field (EF) Operation And Maintenance Data.pdf PDF
ESBD_374441_1724692242063_ATTACHMENT G.S - Ellington AFB (EF) Substitutions Request Form.pdf PDF
ESBD_374441_1725392781473_ESBD Addendum 2 - TMD24-ANG-WJ-24150007.pdf PDF
ESBD_374441_1724692121362_ATTACHMENT G.O - Ellington Field (EF) Starting Of Systems.pdf PDF
ESBD_374441_1724694211190_ESBD Addendum 1 - TMD24-ANG-WJ-24150007.pdf PDF
Show 40 more

Latest 50 of 76 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT G.P - ELLINGTON AFB (EF) CONTRACT CLOSEOUT

PART 1 – GENERAL

1. SUMMARY

A. This Section includes:

a. Procedures for final acceptance of the Project.

b. Closeout procedures.

c. Final cleaning.

d. Adjusting.

e. Project record documents.

f. Operation and maintenance data.

g. Warranties.

h. Spare parts and maintenance materials.

2. RELATED SECTIONS

A. Attachment G.O - Ellington AFB (EF) Starting Of Systems: Progress cleaning.

B. Attachment G.O - Ellington AFB (EF) Starting Of Systems: System start-up, testing, adjusting, and balancing.

3. PROCEDURES FOR FINAL ACCEPTANCE OF THE PROJECT

A. Pre-final inspection:

a. When the Construction Contractor has completed all work and is satisfied the project is fully in compliance with the contract documents; he will notify the

Project Manager, in writing, that the project is complete and ready for inspection. The Project Manager will arrange for and conduct an inspection of the project by the Project Manager, the Project Manager 's Representatives, and the Construction Contractor. The Project Manager will be provided a reasonable time to arrange for and conduct an inspection.

b. The Project Manager will document any deficiencies on a written punch list and will arrange a meeting with the Construction Contractor to review the punch list and explain all deficient items. The Construction Contractor shall correct the deficiencies and notify the Project Manager in writing when the project is ready for inspection of the deficient items. The Project Manager will arrange and conduit a re-inspection of the project to review the corrected items.

c. The formal list of deficiencies found shall not be considered a final list of all deficient items. The contractor must correct any deficiencies that are found at any point prior to or after final acceptance of the project.

d. NOTE: LIQUIDATED DAMAGES ON PROJECTS THAT EXTEND

BEYOND THE CONTRACT COMPLETION DATE WILL CONTINUE TO

RUN UNTIL ALL CLOSE-OUT DOCUMENTATION IS SUBMITTED

AND ACCEPTED AND ALL “PUNCH-LIST” WORK IS COMPLETE.

B. Training, Instruction and Demonstration:

a. When the Project Manager has determined that the project is sufficiently complete to allow instruction of the Government’s Representative, the Project

Manager will request, in writing, that the Construction Contractor provide

ELLINGTON FIELD, HOUSTON, TX 21 May 2024 training, instruction and demonstration of the work. This training, instruction and demonstration will not be scheduled until all required operations and maintenance data has been submitted and approved.

b. Upon formal notice from the Project Manager, the Construction Contractor shall then arrange for instruction of the Government’s staff in the operation of the constructed systems. This includes submission of all outstanding record documents, including operating and maintenance manuals (required prior to scheduling instruction meeting), equipment cuts, guarantees, warranties, maintenance contracts, and any additional instructions necessary for the operation of the systems. The Construction Contractor shall acquaint the

Government's staff with acceptance tests, guarantees, warranties, and maintenance manuals. The Construction Contractor and the Project Manager will determine the transfer of responsibility for heat, utilities, security, and insurance. The Construction Contractor shall also obtain a Certificate of

Occupancy (where applicable) or similar releases required to permit the

Owner's occupancy of the project.

c. Should the instruction period find deficiencies, the Project Manager will notify the Construction Contractor in writing of deficient items.

C. Final inspection:

a. Upon completion of the remaining deficiencies the Construction Contractor shall notify the Project Manager in writing, that the project is complete and ready for a final inspection. The Project Manager shall arrange for and conduct a final inspection of the project.

D. Additional inspection:

a. Should the project require inspections beyond inspections noted above, from pre- final through final inspection, the Project Manager will reduce from the

Construction Contractor's final payment those monies necessary to provide for the cost of the additional inspections. The reduction shall not be considered as a part of any "Liquidated Damages" for failure to complete within the specified contract time. The reduction shall not be considered as a penalty to the Construction Contractor; but shall be for the actual cost of monies required for the reimbursement of fees for Architect, Owner Representatives, and other specialist necessary for acceptance of the project.

E. Excessive deficiencies found during inspections:

a. During any inspection of project completion, if it is determined by the Project

Manager, that the Construction Contractor has not sufficiently completed the work in compliance to the contract documents, the owner may declare that the project is not sufficiently complete to continue inspection of the work. Within three (3) working days, of the declaration, the Project Manager will issue in writing, a list of deficiencies found. The deficiency listed shall be understood as only a partial list and that the partial list may or may not represent deficiencies in areas that were not inspected.

4. CLOSEOUT PROCEDURES

A. Submit written certification that Contract Documents have been reviewed, Work has been inspected, and that Work is complete in accordance with Contract Documents and ready for the Project Manager’s review.

B. Provide submittals to the Project Manager that are required by governing or other authorities.

C. Submit final Application for Payment identifying total adjusted Contract Sum, previous payments, and sum remaining due.

D. Submit with the final Application for Payment a complete certified list of subcontractors and material suppliers. Accompanying the list shall be a lien waiver signed by each subcontractor and material supplier as documentation verifying that payment has been made for services and materials required for completion of this

Contract. Lien waiver forms are available from the Project Manager.

5. FINAL CLEANING

A. Execute final cleaning prior to final project assessment.

B. Clean interior and exterior glass, surfaces exposed to view; remove temporary labels, stains, and foreign substances, polish transparent and glossy surfaces, vacuum carpeted and soft surfaces.

C. Clean equipment and fixtures to a sanitary condition with cleaning materials appropriate to the surface and material being cleaned.

D. Replace filters of operating equipment.

E. Clean debris from roofs, gutters, downspouts, and drainage systems.

F. Clean site, only areas that were used for staging and adjacent areas that may need cleaning due to windblown construction debris; sweep paved areas, rake clean landscaped surfaces.

G. Remove waste and surplus materials, rubbish, and construction facilities from the site.

6. ADJUSTING

A. Adjust operating Products and equipment to ensure smooth and unhindered operation.

7. PROJECT RECORD DOCUMENTS

A. Maintain on site, one set of the following record documents; record actual revisions to the Work:

a. Drawings.

b. Specifications.

c. Addenda.

d. Change Orders and other modifications to the Contract.

e. Reviewed Shop Drawings, Product Data, and Samples.

f. Manufacturer's instruction for assembly, installation, and adjusting.

B. Ensure entries are complete and accurate, enabling future reference by the

Government.

C. Store record documents separate from documents used for construction.

D. Record information concurrent with construction progress.

E. Specifications: Legibly mark and record at each Product section description of actual

Products installed, including the following:

a. Manufacturer's name and product model and number.

b. Product substitutions or alternates utilized.

c. Changes made by Addenda and modifications.

F. Record Documents and Shop Drawings: Legibly mark each item to record actual construction including:

a. Measured depths of foundations in relation to finish first floor datum.

b. Measured horizontal and vertical locations of underground utilities and appurtenances, referenced to permanent surface improvements.

c. Measured locations of internal utilities and appurtenances concealed in construction, referenced to visible and accessible features of the Work.

d. Field changes of dimension and detail.

e. Details not on original Contract drawings.

G. Remove Architect title block and seal from all documents.

H. General Contractor shall provide red-lined as-built drawings to the A-E and BCE at the completion of the project. The A-E shall provide as-built drawings in the form of

CAD and pdf versions, upon substantial completion of the project in a format compatible with the geobase system.

8. OPERATION AND MAINTENANCE DATA

A. Submit data bound in 8-1/2 x 11-inch (216 x 279 mm) text pages, three D side ring binders with durable plastic covers.

B. Prepare binder cover with printed title "OPERATION AND MAINTENANCE

INSTRUCTIONS", title of project, and subject matter of binder when multiple binders are required.

C. Internally subdivide the binder contents with permanent page dividers, logically organized as described below; with tab titling clearly printed under reinforced laminated plastic tabs.

D. Contents: Prepare a Table of Contents for each volume, with each Product or system description identified, typed on 24-pound white paper, in three parts as follows:

a. Part 1: Directory, listing names, addresses, and telephone numbers of

Architect, Contractor, Subcontractors, and major equipment suppliers.

b. Part 2: Operation and maintenance instructions, arranged by system and subdivided by specification section. For each category, identify names, addresses, and telephone numbers of Subcontractors and suppliers. Identify the following:

i. Significant design criteria.

ii. List of equipment.

iii. Parts list for each component.

iv. Operating instructions.

v. Maintenance instructions for equipment and systems.

vi. Maintenance instructions for special finishes, including recommended cleaning methods and materials, and special precautions identifying detrimental agents.

c. Part 3: Project documents and certificates, including the following:

i. Shop drawings and product data.

ii. Air and water balance reports.

iii. Certificates.

iv. Photocopies of warranties and bonds.

E. Submit 1 draft copy of completed volumes 15 days prior to final inspection. This copy will be reviewed and returned after final inspection, with the Project Manager’s comments. Revise content of all documents sets as required prior to final submission.

F. Submit three sets of revised final volumes, within 10 days after final inspection.

9. WARRANTIES

A. Provide duplicate notarized copies.

B. Execute and assemble transferable warranty documents from Subcontractors, suppliers, and manufacturers.

C. Provide Table of Contents and assemble in three D side ring binder with durable plastic cover.

D. Prepare binder cover with printed title "WARRANTIES", and title of project.

E. Submit prior to final Application for Payment.

F. For items of Work delayed beyond date of Substantial Completion, provide updated submittal within 10 days after acceptance, listing date of acceptance as start of warranty period.

10. SPARE PARTS AND MAINTENANCE MATERIALS

A. Provide products, spare parts, maintenance and extra materials in quantities specified in individual specification sections.

B. Deliver to Project site and place in location as directed by the Project Manager; obtain receipt prior to final payment.

File details come from the government source that posted it. Updated .