This document is an attachment to a state and local contract opportunity that outlines the requirements for starting up and demonstrating the operation and maintenance of various systems and equipment for the Ellington AFB (EF) project. The attachment includes details on coordinating the start-up schedule, verifying equipment and system conditions, executing start-up under manufacturer supervision, providing written reports, demonstrating operation and maintenance to the Owner's personnel, and hiring an independent firm to perform testing, adjusting, and balancing. The document specifies that the General Contractor is responsible for paying for the independent testing, adjusting, and balancing services, and that the reports from this work will be submitted to the Project Manager.
The document does not provide any information about pricing terms, set asides, incumbents, funding requirements and sources, or other salient commercial details. It focuses solely on the technical requirements for starting up, demonstrating, and testing the various systems and equipment for the Ellington AFB project.
View the file
Other files
Show 40 more
Latest 50 of 76 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT G.O - ELLINGTON AFB (EF) STARTING OF SYSTEMS
PART 1 – GENERAL
1. SUMMARY
A. This Section includes:
a. Starting systems.
b. Demonstration and instructions.
c. Testing, adjusting, and balancing.
d. Third party testing, adjusting, and balancing.
2. RELATED SECTIONS
A. Solicitation Section C Statement of Work.
B. Attachment G.G - Ellington AFB (EF) Quality Control.
C. Attachment G.P - Ellington AFB (EF) Contract Closeout.
3. STARTING OF SYSTEMS
A. Coordinate schedule for start-up of various equipment and systems.
B. Notify the Project Manager in writing seven days prior to start-up of each item.
C. Verify that each piece of equipment or system has been checked for proper lubrication, drive rotation, belt tension, control sequence, or for other conditions which may cause damage.
D. Verify that tests, meter readings, and specified electrical characteristics agree with those re- quired by the equipment or system manufacturer.
E. Verify wiring and support components for equipment are complete and tested.
F. Execute start-up under supervision of applicable Contractors' personnel in accordance with manufacturers' instructions.
G. When specified in individual specification Sections, require manufacturer to provide authorized representative to be present at site to inspect, check, and approve equipment or system installation prior to start-up, and to supervise placing equipment or system in operation.
H. Submit a written report in accordance with Section 01400 that equipment or system has been properly installed and is functioning correctly.
4. DEMONSTRATION AND INSTRUCTIONS
A. Demonstrate operation and maintenance of Products to Owner's personnel prior to final payment.
B. For equipment or systems requiring seasonal operation, perform demonstration for other sea- son within six months.
C. Utilize operation and maintenance manuals as basis for instruction. Review contents of manual with Owners' personnel in detail to explain all aspects of operation and maintenance.
D. Demonstrate start-up, operation, control, adjustment, troubleshooting, servicing, maintenance, and shutdown of each item of equipment at scheduled time at designated location.
E. Prepare and insert additional data in operations and maintenance manuals when need for additional data becomes apparent during instruction.
ELLINGTON FIELD, HOUSTON, TX 21 May 2024
F. The amount of time required for instruction on each item of equipment and system is that specified in individual sections.
5. TESTING, ADJUSTING, AND BALANCING
A. General Contractor shall pay for (Hire) for services of an independent firm to perform testing, adjusting, and balancing. The independent firm shall work with the Project
Manager in conducting operations of the performance.
B. Reports will be submitted by the independent firm to the Project Manager indicating observations and results of tests and indicating compliance or non-compliance with the requirements of the Contract Documents.