ESBD_374441_1724692161504_ATTACHMENT G.Q - Ellington AFB (EF) Cutting And Patching.pdf

PDF 134 KB Posted

Attached to
Hush House Transformer Replacement
Solicitation number
TMD24-ANG-WJ-24150007
Issued by
Harris County, Texas

About this file

This document is an attachment for the Ellington AFB (EF) Cutting and Patching contract opportunity. It includes procedural requirements for cutting and patching work. The scope of work involves removal of existing construction to permit installation or performance of other work, as well as fitting and repair work required to restore surfaces to original conditions after installation of other work. The contract requires submittals for cutting and patching proposals at least 10 days before the work is performed, including details on the extent of work, changes to existing construction, products to be used, schedule, utilities impacted, and structural reinforcement if applicable. The contract also specifies quality assurance requirements related to structural elements, operational elements, and a cutting and patching conference. Existing warranties for materials and surfaces must be maintained.

The contract requires the use of materials identical to existing materials, or materials that will match the visual and functional performance of existing materials if identical materials are unavailable. The execution requirements detail the examination, preparation, and performance of cutting and patching work, including temporary support, protection measures, and methods for cutting and patching to achieve matching finishes.

View the file

Other files

File Type Posted
ESBD_374441_1724693925873_ATTACHMENT G.3 TMD Standard Terms and Conditions.pdf PDF
ESBD_374441_1724690404606_ATTACHMENT G.B - Ellington Field (EF) Coordination And Meetings.pdf PDF
ESBD_374441_1724691507659_ATTACHMENT G.F.2 - Ellington AFB (EF) Contractor Hazardous Material Identification Form Close-Out Procedures.pdf PDF
ESBD_374441_1724692432692_ATTACHMENT G.W - Ellington AFB (EF) AF103_REV.pdf PDF
ESBD_374441_1724690583036_ATTACHMENT G.F.1 - Ellington AFB (EF) Contractor Hazardous Material Usage Data.pdf PDF
ESBD_374441_1724691790419_ATTACHMENT G.J - Ellington Field (EF) Operation And Maintenance Data.pdf PDF
ESBD_374441_1724692312038_ATTACHMENT G.T - Ellington Field (EF) Post Award Submittals.pdf PDF
ESBD_374441_1724692020055_ATTACHMENT G.M - Ellington AFB (EF) Material Equipment.pdf PDF
ESBD_374441_1724692121362_ATTACHMENT G.O - Ellington Field (EF) Starting Of Systems.pdf PDF
ESBD_374441_1724690507683_ATTACHMENT G.D - Ellington AFB (EF) Field Engineering.pdf PDF
ESBD_374441_1724690315307_ATTACHMENT G.1 Direct Deposit Authorization Form.pdf PDF
ESBD_374441_1724692161504_ATTACHMENT G.Q - Ellington AFB (EF) Cutting And Patching.pdf PDF
ESBD_374441_1724691956363_ATTACHMENT G.K - Ellington AFB (EF) Construction Facilities And Temporary Controls.pdf PDF
ESBD_374441_1724691815157_ATTACHMENT G.J.1 - Ellington AFB (EF) Maintenance Summary Form.pdf PDF
ESBD_374441_1724692399005_ATTACHMENT G.V - Ellington Field (EF) Houston Texas Standard Operating Procedure (Sop) For Inadvertent Discovery Of Unmarked Burials.pdf PDF
ESBD_374441_1724692037243_ATTACHMENT G.N - Ellington Field (EF) Manufacturers’ Services.pdf PDF
ESBD_374441_1724690553865_ATTACHMENT G.F - Ellington Field (EF) EMS Hazardous Material Procedures.pdf PDF
ESBD_374441_1724690355671_ATTACHMENT G.4 Pricing Schedule.pdf PDF
ESBD_374441_1725392781473_ESBD Addendum 2 - TMD24-ANG-WJ-24150007.pdf PDF
ESBD_374441_1724691712762_ATTACHMENT G.I - Ellington Field (EF) Houston Texas Standard Operating Procedure (Sop) For Inadvertent Discovery Of Cultural Materials.pdf PDF
ESBD_374441_1724694211190_ESBD Addendum 1 - TMD24-ANG-WJ-24150007.pdf PDF
ESBD_374441_1724692143764_ATTACHMENT G.P - Ellington Field (EF) Contract Closeout.pdf PDF
ESBD_374441_1724690368368_ATTACHMENT G.5 Photo of Hush House Transformer and new ALAMO Transformer.pdf PDF
ESBD_374441_1724692447571_ATTACHMENT G.X - Ellington AFB (EF) AF3000.pdf PDF
ESBD_374441_1724690540926_ATTACHMENT G.E - Ellington Field (EF) Safety Policies And Procedures.pdf PDF
ESBD_374441_1724692509041_ATTACHMENT G.Y - ELLINGTON AFB (EF) Form 17 - VISITOR CONTRACTOR PASS REQUEST (01OCT23).pdf PDF
ESBD_374441_1724692099667_ATTACHMENT G.N.1 - Ellington Field (EF) Manufacturer’s Certificate Of Proper Installation.pdf PDF
ESBD_374441_1724691998089_ATTACHMENT G.L - Ellington Field JRB Final Asbestos Abatement Report Template.pdf PDF
ESBD_374441_1724690490077_ATTACHMENT G.C - Ellington AFB (EF) Project Coordination.pdf PDF
ESBD_374441_1724691612581_ATTACHMENT G.H - Ellington Field (EF) EMS Environmental Protection.pdf PDF
ESBD_374441_1724692341515_ATTACHMENT G.U - Ellington Field (EF) Sustainable Design Requirements.pdf PDF
ESBD_374441_1724692242063_ATTACHMENT G.S - Ellington AFB (EF) Substitutions Request Form.pdf PDF
ESBD_374441_1724691585489_ATTACHMENT G.G - Ellington AFB (EF) Quality Control.pdf PDF
ESBD_374441_1724690331895_ATTACHMENT G.2 Application for Texas Identification Number.pdf PDF
ESBD_374441_1726259554868_Addendum 3 - TMD24-ANG-WJ-24150007.pdf PDF
ESBD_374441_1724692217506_ATTACHMENT G.R - Ellington Field (EF) EMS Construction Waste Management And Disposal Part 1 - General.pdf PDF
ESBD_374441_1724690388476_ATTACHMENT G.A - Ellington Field (EF) General Requirements.pdf PDF
ESBD_374441_1725392736305_TMD24-ANG-WJ-24150007 Hush House Transformer Replacement.pdf PDF
ESBD_374441_1724691585489_ATTACHMENT G.G - Ellington AFB (EF) Quality Control.pdf PDF
ESBD_374441_1726259554868_Addendum 3 - TMD24-ANG-WJ-24150007.pdf PDF
ESBD_374441_1725392736305_TMD24-ANG-WJ-24150007 Hush House Transformer Replacement.pdf PDF
ESBD_374441_1724692020055_ATTACHMENT G.M - Ellington AFB (EF) Material Equipment.pdf PDF
ESBD_374441_1724692447571_ATTACHMENT G.X - Ellington AFB (EF) AF3000.pdf PDF
ESBD_374441_1724690315307_ATTACHMENT G.1 Direct Deposit Authorization Form.pdf PDF
ESBD_374441_1724691790419_ATTACHMENT G.J - Ellington Field (EF) Operation And Maintenance Data.pdf PDF
ESBD_374441_1724692242063_ATTACHMENT G.S - Ellington AFB (EF) Substitutions Request Form.pdf PDF
ESBD_374441_1725392781473_ESBD Addendum 2 - TMD24-ANG-WJ-24150007.pdf PDF
ESBD_374441_1724692121362_ATTACHMENT G.O - Ellington Field (EF) Starting Of Systems.pdf PDF
ESBD_374441_1724694211190_ESBD Addendum 1 - TMD24-ANG-WJ-24150007.pdf PDF
ESBD_374441_1724692217506_ATTACHMENT G.R - Ellington Field (EF) EMS Construction Waste Management And Disposal Part 1 - General.pdf PDF
Show 40 more

Latest 50 of 76 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT G.Q - ELLINGTON AFB (EF) CUTTING AND

PATCHING

PART 1 – GENERAL

1. SUMMARY

This Section includes procedural requirements for cutting and patching.

2. DEFINITIONS

A. Cutting: Removal of existing construction necessary to permit installation or performance of other Work.

B. Patching: Fitting and repair work required to restore surfaces to original conditions after installation of other Work.

3. SUBMITTALS

A. Cutting and Patching Proposal: Submit a proposal describing procedures at least 10 days before the time cutting and patching will be performed, requesting approval to proceed. Include the following information:

a. Extent: Describe cutting and patching, show how they will be performed, and indicate why they cannot be avoided.

b. Changes to Existing Construction: Describe anticipated results. Include changes to structural elements and operating components as well as changes in building's appearance and other significant visual elements.

c. Products: List products to be used and firms or entities that will perform the

Work.

d. Dates: Indicate when cutting and patching will be performed.

e. Utilities: List utilities that cutting and patching procedures will disturb or affect. List utilities that will be relocated and those that will be temporarily out of service. Indicate how long service will be disrupted.

f. Structural Elements: Where cutting and patching involve adding reinforcement to structural elements, submit details and engineering calculations showing integration of reinforcement with original structure.

g. Contracting Officer’s Representative Approval: Obtain approval of cutting and patching proposal before cutting and patching. Approval does not waive right to later require removal and replacement of unsatisfactory work.

4. QUALITY ASSURANCE

A. Structural Elements: Do not cut and patch structural elements in a manner that could change their load-carrying capacity or load-deflection ratio.

B. Operational Elements: Do not cut and patch operating elements and related components in a manner that results in reducing their capacity to perform as intended or that results in increased maintenance or decreased operational life or safety, unless otherwise indicated.

a. Primary operational systems and equipment.

b. Air or smoke barriers.

c. Fire-protection systems.

d. Control systems.

ELLINGTON FIELD, HOUSTON, TX 21 May 2024

e. Communication systems.

f. Communications conduit shall have pull strings added in all applications

g. Conveying systems.

h. Electrical wiring systems.

i. Operating systems of special construction in Division 13 Sections.

C. Cutting and Patching Conference: Before proceeding, meet at Project site with parties involved in cutting and patching, including mechanical and electrical trades. Review areas of potential interference and conflict. Coordinate procedures and resolve potential conflicts before proceeding.

5. WARRANTY

A. Existing Warranties: Remove, replace, patch, and repair materials and surfaces cut or damaged during cutting and patching operations, by methods and with materials so as not to void existing warranties, where applicable.

PART 2 - PRODUCTS

1. MATERIALS

A. General: Comply with requirements specified in other Sections of these

Specifications.

B. Existing Materials: Use materials identical to existing materials. For exposed surfaces, use materials that visually fully match existing adjacent surfaces possible.

a. If identical materials are unavailable or cannot be used, use materials that, when installed, will match the visual and functional performance of existing materials.

PART 3 - EXECUTION

1. EXAMINATION

A. Examine surfaces to be cut and patched and conditions under which cutting, and patching are to be performed.

a. Compatibility: Before patching, verify compatibility with and suitability of substrates, including compatibility with existing finishes or primers.

b. Proceed with installation only after unsafe or unsatisfactory conditions have been corrected.

2. PREPARATION

A. Temporary Support: Provide temporary support of Work to be cut.

B. Protection: Protect existing construction during cutting and patching to prevent damage. Provide protection from adverse weather conditions for portions of Project that might be exposed during cutting and patching operations.

C. Adjoining Areas: Avoid interference with use of adjoining areas or interruption of free passage to adjoining areas.

D. Existing Services: Where existing services are required to be removed, relocated, or abandoned, bypass such services before cutting to minimize interruption of services to occupied areas.

3. PERFORMANCE

A. General: Employ skilled workers to perform cutting and patching. Proceed with cutting and patching at the earliest feasible time, and complete without delay.

a. Cut existing construction to provide for installation of other components or performance of other construction, and subsequently patch as required to restore surfaces to their original condition.

B. Cutting: Cut existing construction by sawing, drilling, breaking, chipping, grinding, and similar operations, including excavation, using methods least likely to damage elements retained or adjoining construction. If possible, review proposed procedures with original Installer; comply with original Installer's written recommendations.

a. In general, use hand or small power tools designed for sawing and grinding, not hammering, and chopping. Cut holes and slots as small as possible, neatly to size required, and with minimum disturbance of adjacent surfaces.

Temporarily cover openings when not in use.

b. Existing Finished Surfaces: Cut or drill from the exposed or finished side into concealed surfaces.

c. Concrete or Masonry: Cut using a cutting machine, such as an abrasive saw or a diamond-core drill.

d. Excavating and Backfilling: Comply with requirements in applicable Division

2 Sections where required by cutting and patching operations.

e. Mechanical and Electrical Services: Cut off pipe or conduit in walls or partitions to be removed. Cap, valve, or plug and seal remaining portion of pipe or conduit to prevent entrance of moisture or other foreign matter after cutting.

f. Proceed with patching after construction operations requiring cutting are complete.

C. Matching: Patch construction by filling, repairing, refinishing, closing, and similar operations following performance of other Work. Patch with durable seams that are as invisible as possible. Provide materials and comply with installation requirements specified in other Sections of these Specifications.

a. Inspection: Where feasible, test and inspect patched areas after completion to demonstrate integrity of installation.

b. Exposed Finishes: Restore exposed finishes of patched areas and extend finish restoration into retained adjoining construction in a manner that will eliminate evidence of patching and refinishing.

c. Floors and Walls: Where walls or partitions that are removed extend one finished area into another, patch and repair floor and wall surfaces in the new space. Provide an even surface of uniform finish, color, texture, and appearance. Remove existing floor and wall coverings and replace with new materials, if necessary, to achieve uniform color and appearance.

i. Where patching occurs in a painted surface, apply primer and intermediate paint coats over the patch and apply final paint coat over entire unbroken surface containing the patch. Provide additional coats until patch blends with adjacent surfaces.

d. Ceilings: Patch, repair, or re-hang existing ceilings as necessary to provide an even-plane surface of uniform appearance.

e. Exterior Building Enclosure: Patch components in a manner that restores enclosure to a weather tight condition.