ESBD_374441_1724691507659_ATTACHMENT G.F.2 - Ellington AFB (EF) Contractor Hazardous Material Identification Form Close-Out Procedures.pdf
PDF 51 KB Posted
- Attached to
- Hush House Transformer Replacement
- Solicitation number
- TMD24-ANG-WJ-24150007
- Issued by
- Harris County, Texas
About this file
This document is an attachment titled "ATTACHMENT G.F.2 - ELLINGTON AFB (EF) CONTRACTOR HAZARDOUS MATERIAL IDENTIFICATION FORM CLOSE-OUT PROCEDURES" related to a state and local contract opportunity. The attachment outlines the close-out procedures for the Ellington AFB (EF) Contractor Hazardous Material Identification Form. It requires the contractor to accompany the Project Manager's Representative and the Environmental Manager on the close-out inspection to ensure all used and unused hazardous materials have been removed from the installation. The close-out inspection must be approved with signatures from the Contractor, Project Manager/Representative, and the CEV (Environmental Manager).
The document does not provide details on the overall contract, such as the products or services requested, project overviews, item quantities, response dates, due dates, site visits, bidder's meetings and conferences, award dates, or the term of the contract including any renewal options. It also does not mention pricing terms, set asides, incumbents, current environment, funding requirements and sources, amounts, or any other salient information.
View the file
Other files
Show 40 more
Latest 50 of 76 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT G.F.2 - ELLINGTON AFB (EF) CONTRACTOR HAZARDOUS
MATERIAL IDENTIFICATION FORM CLOSE-OUT PROCEDURES
Part II
Attach this part to Part I
Contractor shall accompany the Project Manager’s Representative and the
Environmental Manager on the close-out inspection to ensure all used and unused HM has been removed from the installation.
Close-out Approval Signatures:
Contractor
Signature Date
Project Manager
/Representative CEV
(Environmental Manager)