ESBD_374441_1724690404606_ATTACHMENT G.B - Ellington Field (EF) Coordination And Meetings.pdf

PDF 56 KB Posted

Attached to
Hush House Transformer Replacement
Solicitation number
TMD24-ANG-WJ-24150007
Issued by
Harris County, Texas

About this file

This document is an attachment to a state and local contract opportunity detailing the coordination and meeting requirements for work at Ellington Field (EF) in Houston, Texas. The attachment outlines the contractor's responsibilities for coordinating the scheduling, submittals, and work of various sections to ensure an efficient and orderly sequence of installation. It also covers requirements for preconstruction meetings, progress meetings held monthly or every two weeks, and pre-installation meetings as needed. The attachment specifies the agenda, attendance requirements, and documentation for these meetings. Additionally, it details the contractor's responsibilities for examining existing site conditions and preparing the substrate prior to commencing work.

The attachment does not provide any details on pricing, set-asides, incumbents, funding, or other salient commercial information. This appears to be a technical specification document outlining the coordination and meeting requirements for the construction project at Ellington Field.

View the file

Other files

File Type Posted
ESBD_374441_1724693925873_ATTACHMENT G.3 TMD Standard Terms and Conditions.pdf PDF
ESBD_374441_1724690404606_ATTACHMENT G.B - Ellington Field (EF) Coordination And Meetings.pdf PDF
ESBD_374441_1724691507659_ATTACHMENT G.F.2 - Ellington AFB (EF) Contractor Hazardous Material Identification Form Close-Out Procedures.pdf PDF
ESBD_374441_1724692432692_ATTACHMENT G.W - Ellington AFB (EF) AF103_REV.pdf PDF
ESBD_374441_1724690583036_ATTACHMENT G.F.1 - Ellington AFB (EF) Contractor Hazardous Material Usage Data.pdf PDF
ESBD_374441_1724691790419_ATTACHMENT G.J - Ellington Field (EF) Operation And Maintenance Data.pdf PDF
ESBD_374441_1724692312038_ATTACHMENT G.T - Ellington Field (EF) Post Award Submittals.pdf PDF
ESBD_374441_1724692020055_ATTACHMENT G.M - Ellington AFB (EF) Material Equipment.pdf PDF
ESBD_374441_1724692121362_ATTACHMENT G.O - Ellington Field (EF) Starting Of Systems.pdf PDF
ESBD_374441_1724690507683_ATTACHMENT G.D - Ellington AFB (EF) Field Engineering.pdf PDF
ESBD_374441_1724690315307_ATTACHMENT G.1 Direct Deposit Authorization Form.pdf PDF
ESBD_374441_1724692161504_ATTACHMENT G.Q - Ellington AFB (EF) Cutting And Patching.pdf PDF
ESBD_374441_1724691956363_ATTACHMENT G.K - Ellington AFB (EF) Construction Facilities And Temporary Controls.pdf PDF
ESBD_374441_1724691815157_ATTACHMENT G.J.1 - Ellington AFB (EF) Maintenance Summary Form.pdf PDF
ESBD_374441_1724692399005_ATTACHMENT G.V - Ellington Field (EF) Houston Texas Standard Operating Procedure (Sop) For Inadvertent Discovery Of Unmarked Burials.pdf PDF
ESBD_374441_1724692037243_ATTACHMENT G.N - Ellington Field (EF) Manufacturers’ Services.pdf PDF
ESBD_374441_1724690553865_ATTACHMENT G.F - Ellington Field (EF) EMS Hazardous Material Procedures.pdf PDF
ESBD_374441_1724690355671_ATTACHMENT G.4 Pricing Schedule.pdf PDF
ESBD_374441_1725392781473_ESBD Addendum 2 - TMD24-ANG-WJ-24150007.pdf PDF
ESBD_374441_1724691712762_ATTACHMENT G.I - Ellington Field (EF) Houston Texas Standard Operating Procedure (Sop) For Inadvertent Discovery Of Cultural Materials.pdf PDF
ESBD_374441_1724694211190_ESBD Addendum 1 - TMD24-ANG-WJ-24150007.pdf PDF
ESBD_374441_1724692143764_ATTACHMENT G.P - Ellington Field (EF) Contract Closeout.pdf PDF
ESBD_374441_1724690368368_ATTACHMENT G.5 Photo of Hush House Transformer and new ALAMO Transformer.pdf PDF
ESBD_374441_1724692447571_ATTACHMENT G.X - Ellington AFB (EF) AF3000.pdf PDF
ESBD_374441_1724690540926_ATTACHMENT G.E - Ellington Field (EF) Safety Policies And Procedures.pdf PDF
ESBD_374441_1724692509041_ATTACHMENT G.Y - ELLINGTON AFB (EF) Form 17 - VISITOR CONTRACTOR PASS REQUEST (01OCT23).pdf PDF
ESBD_374441_1724692099667_ATTACHMENT G.N.1 - Ellington Field (EF) Manufacturer’s Certificate Of Proper Installation.pdf PDF
ESBD_374441_1724691998089_ATTACHMENT G.L - Ellington Field JRB Final Asbestos Abatement Report Template.pdf PDF
ESBD_374441_1724690490077_ATTACHMENT G.C - Ellington AFB (EF) Project Coordination.pdf PDF
ESBD_374441_1724691612581_ATTACHMENT G.H - Ellington Field (EF) EMS Environmental Protection.pdf PDF
ESBD_374441_1724692341515_ATTACHMENT G.U - Ellington Field (EF) Sustainable Design Requirements.pdf PDF
ESBD_374441_1724692242063_ATTACHMENT G.S - Ellington AFB (EF) Substitutions Request Form.pdf PDF
ESBD_374441_1724691585489_ATTACHMENT G.G - Ellington AFB (EF) Quality Control.pdf PDF
ESBD_374441_1724690331895_ATTACHMENT G.2 Application for Texas Identification Number.pdf PDF
ESBD_374441_1726259554868_Addendum 3 - TMD24-ANG-WJ-24150007.pdf PDF
ESBD_374441_1724692217506_ATTACHMENT G.R - Ellington Field (EF) EMS Construction Waste Management And Disposal Part 1 - General.pdf PDF
ESBD_374441_1724690388476_ATTACHMENT G.A - Ellington Field (EF) General Requirements.pdf PDF
ESBD_374441_1725392736305_TMD24-ANG-WJ-24150007 Hush House Transformer Replacement.pdf PDF
ESBD_374441_1724691585489_ATTACHMENT G.G - Ellington AFB (EF) Quality Control.pdf PDF
ESBD_374441_1726259554868_Addendum 3 - TMD24-ANG-WJ-24150007.pdf PDF
ESBD_374441_1725392736305_TMD24-ANG-WJ-24150007 Hush House Transformer Replacement.pdf PDF
ESBD_374441_1724692020055_ATTACHMENT G.M - Ellington AFB (EF) Material Equipment.pdf PDF
ESBD_374441_1724692447571_ATTACHMENT G.X - Ellington AFB (EF) AF3000.pdf PDF
ESBD_374441_1724690315307_ATTACHMENT G.1 Direct Deposit Authorization Form.pdf PDF
ESBD_374441_1724692161504_ATTACHMENT G.Q - Ellington AFB (EF) Cutting And Patching.pdf PDF
ESBD_374441_1724691790419_ATTACHMENT G.J - Ellington Field (EF) Operation And Maintenance Data.pdf PDF
ESBD_374441_1724692242063_ATTACHMENT G.S - Ellington AFB (EF) Substitutions Request Form.pdf PDF
ESBD_374441_1725392781473_ESBD Addendum 2 - TMD24-ANG-WJ-24150007.pdf PDF
ESBD_374441_1724692121362_ATTACHMENT G.O - Ellington Field (EF) Starting Of Systems.pdf PDF
ESBD_374441_1724694211190_ESBD Addendum 1 - TMD24-ANG-WJ-24150007.pdf PDF
Show 40 more

Latest 50 of 76 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT G.B - ELLINGTON AFB (EF) COORDINATION AND

MEETINGS

PART 1 – GENERAL

1. SUMMARY

A. This Section includes:

a. Coordination

b. Preconstruction meeting

c. Progress meetings

d. Pre-installation meetings

e. Examination

f. Preparation

2. COORDINATION

A. Coordinate scheduling, submittals, and Work of the various sections of the Project

Manual to assure efficient and orderly sequence of installation of interdependent construction elements, [with provisions for accommodating items installed later].

B. Verify utility requirements and characteristics of operating equipment are compatible with building utilities. Coordinate work of various sections having interdependent responsibilities for installing, connecting to, and placing in service, such equipment.

C. Coordinate space requirements and installation of mechanical and electrical work which are indicated diagrammatically on Drawings. Follow routing shown for pipes, ducts, and conduit, as closely as practicable; place runs parallel with line of building.

Utilize spaces efficiently to maximize accessibility for other installations, for maintenance, and for repairs.

D. In finished areas [except as otherwise indicated], conceal pipes, ducts, and wiring within the construction. Coordinate locations of fixtures and outlets with finish elements.

E. Coordinate completion and cleanup of Work of separate sections in preparation for

Substantial Completion.

F. After Owner occupancy of premises, coordinate access to site for correction of defective Work and Work not in accordance with Contract Documents, to minimize disruption of Owner's activities.

3. PRE-CONSTRUCTION MEETING

A. The Project Manager will schedule a meeting after Notice of Award.

B. Agenda:

a. Distribution of Contract Documents

b. Submission of list of Subcontractors, list of Products, schedule of values, and proposed construction schedule.

c. Designation of personnel representing the parties in Contract

d. Procedures and processing of field decisions, submittals, substitutions, applications for payments, proposal request, Change Orders, and Contract closeout procedures

e. Scheduling

f. Safety plan submittal

ELLINGTON FIELD, HOUSTON, TX 21 May 2024

4. PROGRESS MEETINGS

A. The Contractor will in Coordination with the Project Manager:

a. Schedule and administer meetings throughout progress of the Work at maximum monthly intervals, every 2-weeks is preferred.

b. Make arrangements for meetings, prepare agenda with copies for participants, and preside at meetings.

c. Review coordination with related work

d. Provide written documentation of the meeting minutes for review and acceptance by all present within 3 working days of each meeting.

B. Attendance Required: Job superintendent, major Subcontractors and suppliers, the

Project Manager as appropriate to agenda topics for each meeting.

C. Agenda:

a. Review minutes of previous meetings

b. Review of Work progress

c. Field observations, problems, and decisions

d. Identification of problems which impede planned progress.

e. Review of submittals schedule with emphasis on Critical Path Items and status of submittals

f. Review of off-site fabrication and delivery schedules

g. Maintenance of progress schedule

h. Corrective measures to regain projected schedules.

i. Planned progress during succeeding work period.

j. Coordination of projected progress

k. Maintenance of quality and work standards

l. Effect of proposed changes on progress schedule and coordination

m. Other business relating to Work.

5. PRE-INSTALLATION MEETING

A. When required in individual specification sections, convene a pre-installation meeting at work site prior to commencing work of the section.

B. Require attendance of parties directly affecting, or affected by, work of the

C. specific section.

D. Notify the Project Manager four days in advance of meeting date.

E. Contractor will prepare agenda and preside at meeting:

a. Review conditions of installation, preparation, and installation procedures

b. Provide written documentation of the minutes of the meeting within 3 working days of each meeting.

PART 2 – EXECUTION

1. EXAMINATION

A. Verify that existing site conditions and substrate surfaces are acceptable for subsequent Work. Beginning new Work means acceptance of existing conditions.

B. Verify that existing substrate is capable of structural attachment of new Work being applied or attached.

ELLINGTON FIELD, HOUSTON, TX 21 May 2024

C. Examine and verify specific conditions described in individual specification sections.

D. Verify that utility services are available, of the correct characteristics, and in the correct location.

2. PREPARATION

A. Clean substrate surfaces prior to applying next material or substance.

B. Seal cracks or openings of substrate prior to applying next material or substance.

C. Apply any manufacturer required or recommended substrate primer, sealer, or conditioner prior to applying any new material or substance in contact or bond.