EOPC_7-16-2025.pdf
PDF 48 KB Posted
- Solicitation number
- 25-23
- Issued by
- Walton County, Florida
About this file
This document is a Construction Cost Summary for the Walton County CR 395 North Road Reconstruction & Multi-Use Path project. The comprehensive construction project involves roadway reconstruction, multi-use path construction, and various infrastructure improvements, with a total construction cost of $3,359,370.57. The project includes extensive work such as asphalt concrete placement, concrete work, lime rock base installation, roadway and driveway reconstruction, stormwater management, utility relocations, signage, pavement markings, and landscaping. Key quantities include 830 tons of 2" Superpave asphalt for the multi-use path, 1,460 tons of 1.5" Superpave asphalt for roadways, and multiple drainage infrastructure installations like 1,522 linear feet of 18" ADS N-12 piping and 53 18" MES inlet installations.
The project's financial breakdown includes a construction cost subtotal of $3,139,598.67, with additional costs for bonds (maximum 2% of bid at $62,791.97) and mobilization (maximum 5% of bid at $156,979.93). Additional scope items include clearing and grubbing 2.32 acres, earthwork and excavation, hydro-seeding 24,667 square yards, sodding 16,444 square yards, and maintenance of traffic. The project includes multiple relocation elements such as 21 mailboxes, 27 signs, 8 water valves, 4 fire hydrant assemblies, and various other utility infrastructure movements. The project is scheduled for completion by 7/16/2025, as indicated on the document.
View the file
Other files
Show all 34
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
WALTON COUNTY CR 395 NORTH RECONSTRUCTION MULTI-USE PATH
NO. ITEM QUANTITY UNIT UNIT PRICE TOTAL PRICE
0334 1 12 2" SUPERPAVE ASPH CONC, TRAF B (SP-12.5 MULT-PATH) 830 TN $180.00 $149,400.00
0522 1 (4") CONCRETE 3000 PSI (MULTI-USE PATH) 415 SY $65.00 $26,975.00
285704 OPTIONAL BASE GROUP 4 (MULTI-USE PATH) 6" LIME ROCK BASE (LBR-100) 8671 SY $20.00 $173,420.00
0334 1 12 1.5" SUPERPAVE ASPH CONC, TRAF B, PG76-22 (SP-12.5 ROADWAY) 1460 TN $170.00 $248,200.00
0334 1 12 1.25" SUPERPAVE ASPH CONC, TRAF B, PG76-22 (SP-9.5 ROADWAY) 1290 TN $145.00 $187,050.00
285706 OPTIONAL BASE GROUP 6 (ROADWAY) 8" LIME ROCK BASE (LBR-100) 17322 SY $32.00 $554,304.00
0160 4 (12") TYPE "B" STABILIZED SUBGRADE LBR 40 MIN (ROADWAY) 17322 SY $6.00 $103,932.00
0334 1 12 2" SUPERPAVE ASPH CONC, TRAF B, (SP-12.5 DRIVEWAYS) 788 TN $180.00 $141,840.00
285706 OPTIONAL BASE GROUP 6 (DRIVEWAYS) 7167 SY $32.00 $229,344.00
0160 4 (12") TYPE "B" STABILIZED SUBGRADE LBR 40 MIN (DRIVEWAYS) 7167 SY $6.00 $43,002.00
0334 1 12 1.25" SUPERPAVE ASPH CONC, TRAF B (SP-9.5 OVERLAY) 230 TN $145.00 $33,350.00
0110 3 SAW CUT, DEMOLISH AND REMOVE EXISTING ASPHALT 15645 SY $10.00 $156,450.00
0110 3 SAW CUT, DEMOLISH AND REMOVE EXISTING BRICK PAVER 198 SY $10.00 $1,980.00
0110 3 SAW CUT, DEMOLISH AND REMOVE EXISTING CONCRETE 166 SY $10.00 $1,660.00
S-1
TEMPORARY STRIPING IN ACCORDANCE WITH MUTCD INCLUDING LAYOUT,
CENTERLINE, AND STOP BARS
1 LS $14,500.00 $14,500.00
S-2
THERMOPLASTIC PAVEMENT MARKINGS IN ACCORDANCE WITH MUTCD
INCLUDING EDGE, CENTER, STOP BARS, LAYOUT, RPMs, AND PAVED SIDE
STREETS
1 LS $33,000.00 $33,000.00
S-3 SIGNAGE PER PLANS INSTALLED WITH 3" ALUMINUM POLES 31 AS $950.00 $29,450.00
S-4 RELOCATE EXISTING MAILBOX 21 EA $450.00 $9,450.00
S-5 RELOCATE EXISTING SIGN 27 EA $350.00 $9,450.00
S-6 RELOCATE EXISTING WATER VALVE 8 EA $950.00 $7,600.00
S-7 RELOCATE EXISTING BACK FLOW PREVENTER 1 EA $950.00 $950.00
S-8 RELOCATE EXISTING FIRE HYDRANT ASSEMBLY 4 EA $3,500.00 $14,000.00
S-9 RELOCATE EXISTING FORCE MAIN VALVE 2 EA $750.00 $1,500.00
430174130 24"x38" ELLIPTICAL RCP (INSTALLED) 70 LF $65.00 $4,550.00
430174118 18" ADS N-12 (INSTALLED) 1522 LF $45.00 $68,490.00
430982125 18" MES INDEX 430-022 (INSTALLED) 53 EA $2,500.00 $132,500.00
0425 1521 TYPE "C" INLET INDEX 232 (INSTALLED) 12 EA $5,000.00 $60,000.00
0425 1541 TYPE "D" INLET INDEX 430-052 (INSTALLED) 1 EA $5,500.00 $5,500.00
430536100 STRAIGHT 18" ROUND CONCRETE HEADWALL SINGLE (INSTALLED) 1 EA $5,000.00 $5,000.00
430536100 STRAIGHT 24"x38" ELLIPTICAL CONCRETE HEADWALL SINGLE (INSTALLED) 2 EA $6,500.00 $13,000.00
0515 2311 PIPE GUARDRAIL (ALUMINUM) INDEX 515-070 1050 LF $100.00 $105,000.00
0110 3 DEMOLISH AND REMOVE EXISTING MES 52 EA $150.00 $7,800.00
MISCELLANEOUS
50084172 CR 395 NORTH ROAD RECONSTRUCTION & MULTI-USE PATH CONSTRUCTION COST SUMMARY
ROADWAY ITEMS
STORMWATER ITEMS
DPR PROJECT NO.: 50084172 7/16/2025 Page 1
WALTON COUNTY CR 395 NORTH RECONSTRUCTION MULTI-USE PATH
50084172 CR 395 NORTH ROAD RECONSTRUCTION & MULTI-USE PATH CONSTRUCTION COST SUMMARY
0110 3 DEMOLISH OF EXISTING PIPE 1309 LF $35.00 $45,815.00
S-5 TIMBER RETAINING WALL (2'-5' HEIGHT) 1064 LF $110.00 $117,040.00
0104 10 3 SEDIMENT BARRIER (DOUBLE TYPE III SILT FENCE) 1350 LF $6.00 $8,100.00
0104 10 3 SEDIMENT BARRIER (SINGLE TYPE III SILT FENCE) 11750 LF $3.00 $35,250.00
0104 11 FLOATING TURBIDITY BARRIER 520 LF $9.00 $4,680.00
S-6 MAINTENANCE OF TRAFFIC 1 LS $75,000.00 $75,000.00
0120 1 OVER EXCAVATION (DEMUCKING) 1 LS $40,000.00 $40,000.00
0110 1 1 CLEARING AND GRUBBING 2.32 AC $7,500.00 $17,400.00
0120 1 EARTHWORK LUMP SUM (EXCAVATION AND BORROW) 1 LS $125,000.00 $125,000.00
0570 1 1 HYDROSEED 24667 SY $1.50 $37,000.00
0570 1 2 SODDING 16444 SY $3.75 $61,666.67
CONSTRUCTION COST SUBTOTAL $3,139,598.67
S-10 BONDS (MAX 2% OF BID) 1 LS $62,791.97
S-11 MOBILIZATION (MAX 5% OF BID) 1 LS $156,979.93
TOTAL CONSTRUCTION COST $3,359,370.57 $3,359,370.57
ALTERNATE BID ITEM
GENERAL
DPR PROJECT NO.: 50084172 7/16/2025 Page 2