BID_SCHEDULE_10.2.2025_CR395_TO_COUNTY_(1).xlsx

XLSX spreadsheet 12 KB Posted

Attached to
CR 395 North Road Reconstruction Multi-Use Path Project
Solicitation number
25-23
Issued by
Walton County, Florida

About this file

This is a Bid Schedule document for the CR 395 North Road Reconstruction Multi-Use Path Project prepared by Walton County, Florida. The project encompasses comprehensive roadway improvements including construction of a 10-foot wide asphalt multi-use path along approximately 7,200 linear feet of County Road 395 North in Santa Rosa Beach. The schedule details 52 line items organized into roadway, stormwater, and miscellaneous categories, including asphalt concrete in multiple specifications (1", 1.25", 1.5", and 2" thickness), concrete work for the multi-use path, base materials, drainage infrastructure (18" and 24"x38" elliptical RCP pipes), inlet and headwall installations, pavement markings, signage, sediment barriers, grading, hydroseeding, and sodding totaling approximately 35,000 square yards. The contract term is 365 days for substantial completion with an additional 30 days for punch list items. A non-mandatory pre-bid conference is scheduled for September 8, 2025, with bid responses due by October 1, 2025, at 3:30 pm.

The estimated construction cost subtotal is $3,139,598.67, with additional allocations for bonds (maximum 2% of bid) and mobilization (maximum 5% of bid), bringing the estimated total construction cost to $3,359,370.57. Bidders must be prequalified by the Florida Department of Transportation in specified work classes including drainage, flexible paving, grading, grassing, pavement marking, and roadway signage. A mandatory 5% bid security is required. Liquidated damages are set at $2,667 per day for failure to achieve substantial completion and $1,333 per day for final completion delays. The project includes alternative bid items for timber headwall demolition and replacement with concrete headwall, and for removal and replacement of existing 15" CMP pipe. Environmental permits from the Northwest Florida Water Management District and Florida Department of Environmental Protection have been secured, including wetland mitigation through the purchase of 0.56 credits from the Nokuse Plantation Mitigation Bank. The county reserves the right to reject any or all bids, with project funding through the county's annual appropriation.

View the file

Other files

File Type Posted
CR_395_North_Road_Reconstruction_Multi-Use_Path_Project_(Addendum_#12_Revision).pdf PDF
Copy_of_BID_SCHEDULE_11.3.2025_CR395_TO_COUNTY.xlsx XLSX spreadsheet
50084172_CR_395_2025-10-2_BID_SET_CIVIL_(2).pdf PDF
50084172_CR_395_FOR_BID_11.3.2025.pdf PDF
CR_395_North_Road_Reconstruction_Multi-Use_Path_Project_(Addendum_#6_Revision).pdf PDF
MOT_Sketch_CR395.pdf PDF
MOT_Sketch_CR395.pdf PDF
50084172_CR_395-Bid_Set_2025-7-16-1.pdf PDF
BID_SCHEDULE_7-16-2025_PDF.pdf PDF
50084172_CR_395-Bid_Set_2025-7-16-1.pdf PDF
50084172_CR_395_2025-10-2_BID_SET_CIVIL_(2).pdf PDF
BID_SCHEDULE_10.2.2025_CR395_TO_COUNTY_(1).xlsx XLSX spreadsheet
BID_SCHEDULE_7-16-2025_PDF.pdf PDF
CR_395_North_Road_Reconstruction_Multi-Use_Path_Project.pdf PDF
Contract_No._25-23.pdf PDF
Contract_No._25-23.pdf PDF
Contract_No._25-23.pdf PDF
ERP_permit_395.pdf PDF
395.pdf PDF
ERP_permit_395.pdf PDF
395.pdf PDF
395.pdf PDF
ERP_permit_395.pdf PDF
50182251_CR395_North_Road_Reconstruction_Multi-Use_Path_Specs_8.4.25.pdf PDF
50084172_CR_395-Bid_Set_2025-7-16-1.pdf PDF
EOPC_7-16-2025.pdf PDF
50182251_CR395_North_Road_Reconstruction_Multi-Use_Path_Specs_8.4.25.pdf PDF
EOPC_7-16-2025.pdf PDF
50182251_CR395_North_Road_Reconstruction_Multi-Use_Path_Specs_8.4.25.pdf PDF
EOPC_7-16-2025.pdf PDF
BID_SCHEDULE_7-16-2025_PDF.pdf PDF
Public_Construction_Bond_(25).doc DOC document
Public_Construction_Bond_(25).doc DOC document
Public_Construction_Bond_(25).doc DOC document
Show all 34

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Untitled

Line ItemNO.DescriptionQuantityUnit of MeasureUnit CostTotal
ROADWAY ITEMS
10334 1 121.5" SUPERPAVE ASPH CONC, TRAF B (SP-12.5 MULT-PATH) FOR M.O.T.415TN
20334 1 121" SUPERPAVE ASPH CONC, TRAF B (SP-9.5 MULT-PATH)280TN
30334 1 122" SUPERPAVE ASPH CONC, TRAF B (SP-12.5 MULT-PATH)265TN
40522 1(4") CONCRETE 3000 PSI (MULTI-USE PATH)415SY
5285704OPTIONAL BASE GROUP 4 (MULTI-USE PATH) 6" LIME ROCK BASE (LBR-100)8671SY
60334 1 121.5" SUPERPAVE ASPH CONC, TRAF B, PG76-22 (SP-12.5 ROADWAY)1460TN
70334 1 121.25" SUPERPAVE ASPH CONC, TRAF B, PG76-22 (SP-9.5 ROADWAY)1290TN
8285706OPTIONAL BASE GROUP 6 (ROADWAY) 8" LIME ROCK BASE (LBR-100)17322SY
90160 4(12") TYPE "B" STABILIZED SUBGRADE LBR 40 MIN (ROADWAY)17322SY
100334 1 122" SUPERPAVE ASPH CONC, TRAF B, (SP-12.5 DRIVEWAYS)788TN
11285706OPTIONAL BASE GROUP 6 (DRIVEWAYS)7167SY
120160 4(12") TYPE "B" STABILIZED SUBGRADE LBR 40 MIN (DRIVEWAYS)7167SY
13-TEMP. ROADWAY BASE (TEMP. LANE WIDENING) 6" ASPHALT MILLINGS FOR M.O.T.3344SY
14285706TYPE "B" STABILIZED SUBGRADE LBR 40 MIN (TEMP. LANE WIDENING) FOR M.O.T.3822SY
150334 1 121.25" SUPERPAVE ASPH CONC, TRAF B (SP-9.5 OVERLAY)230TN
160110 3SAW CUT, DEMOLISH AND REMOVE EXISTING ASPHALT15645SY
170110 3SAW CUT, DEMOLISH AND REMOVE EXISTING BRICK PAVER198SY
180110 3SAW CUT, DEMOLISH AND REMOVE EXISTING CONCRETE166SY
19S-1TEMPORARY STRIPING IN ACCORDANCE WITH MUTCD INCLUDING LAYOUT, CENTERLINE, AND STOP BARS1LS
20S-2THERMOPLASTIC PAVEMENT MARKINGS IN ACCORDANCE WITH MUTCD INCLUDING EDGE, CENTER, STOP BARS, LAYOUT, RPMs, AND PAVED SIDE STREETS1LS
21S-3SIGNAGE PER PLANS INSTALLED WITH 3" ALUMINUM POLES31AS
22S-4RELOCATE EXISTING MAILBOX21EA
23S-5RELOCATE EXISTING SIGN27EA
24S-6RELOCATE EXISTING WATER VALVE8EA
25S-7RELOCATE EXISTING BACK FLOW PREVENTER1EA
26S-8ADJUST EXISTING FIRE HYDRANT ASSEMBLY4EA
27S-9RELOCATE EXISTING FORCE MAIN VALVE2EA
STORMWATER ITEMS
2843017413024"x38" ELLIPTICAL RCP (INSTALLED)70LF
2943017411818" HP (INSTALLED)1522LF
3043098212518" MES INDEX 430-022 (INSTALLED)53EA
310425 1521TYPE "C" INLET INDEX 232 (INSTALLED)8EA
320425 1541TYPE "D" INLET INDEX 430-052 (INSTALLED)1EA
33430536100STRAIGHT 18" ROUND CONCRETE HEADWALL SINGLE (INSTALLED)1EA
34430536100STRAIGHT 24"x38" ELLIPTICAL CONCRETE HEADWALL SINGLE (INSTALLED)2EA
350515 2311PIPE GUARDRAIL (ALUMINUM) INDEX 515-0701050LF
MISCELLANEOUS
360110 3DEMOLISH AND REMOVE EXISTING MES52EA
370110 3DEMOLISH OF EXISTING PIPE1309LF
38S-5TIMBER RETAINING WALL (1'-3' HEIGHT)1064LF
390104 10 3SEDIMENT BARRIER (DOUBLE TYPE III SILT FENCE)1350LF
400104 10 3SEDIMENT BARRIER (SINGLE TYPE III SILT FENCE)11750LF
410104 11FLOATING TURBIDITY BARRIER520LF
42S-6MAINTENANCE OF TRAFFIC1LS
430120 1OVER EXCAVATION (REMOVAL OF UNSUITABLE MATERIALS)1720CY
440110 1 1CLEARING AND GRUBBING2.32AC
450120 1EARTHWORK LUMP SUM (EXCAVATION AND BORROW)1LS
460570 1 1HYDROSEED35000SY
470570 1 2SODDING10000SY
48-12" RIBBON CURB150LF
CONSTRUCTION COST SUBTOTAL
GENERAL
49S-10BONDS (MAX 2% OF BID)1LS
50S-11MOBILIZATION (MAX 5% OF BID)1LS
TOTAL CONSTRUCTION COST
ALT. BID ITEMS
511DEMOLISH AND REMOVE EXISTING TIMBER HEAD WALL. CONSTRUCT CONCRETE HEADWALL.1EA
522DEMOLISH AND REMOVE EXISTING 15" CMP PIPE. REPLACE W/ 15" ADS N-12 PIPE (DR-153 & DR-154)30LF