This statement of work outlines phase-in activities for the NASA Balloon Operations Contract II. The contractor shall perform phase-in from February 1, 2021 through March 31, 2021 to transition management, operations, engineering and administrative functions from the incumbent contractor. During this period the contractor shall review NASA regulations and procedures, submit required deliverables including quality plans and certifications, and integrate contract requirements to ensure full performance begins on April 1, 2021. Major deliverables such as safety and training plans must be submitted within 60 days of the contract effective date. The contractor shall coordinate the transition team and maintain continuity of operations to meet NASA mission schedules and costs. The phase-in period will ready the contractor to assume responsibility for all contractual obligations under solicitation number 80GSFC20R0031, the NASA Balloon Operations Contract II follow-on awarded by the National Aeronautics and Space Administration Goddard Space Center.
View the file
Other files for this federal contract opportunity
Show all 47
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
FOR
PHASE-IN ACTIVITIES
NASA BALLOON OPERATIONS CONTRACT (NBOC II) JANUARY 2020
1. BACKGROUND INFORMATION
A complete description of the NASA Balloon Operations Contract (NBOC II) is contained in contract number NNG20WATBD. The purpose of this Statement of Work (SOW) is to conduct phase-in activities associated with this contract. Phase-in will be conducted under this contract at the Columbia Scientific Balloon Facility (CSBF), Palestine, TX and any remote locations identified in the NBOC II SOW in which operations activities are ongoing.
The contractor shall perform phase-in activities leading to readiness to assume full performance of the NBOC II on April 1, 2021. During the phase-in period, the contractor shall not be responsible for performance of the effort described in the NBOC0-2 SOW, Attachment A, of contract number NNG20WATBD.
2. PURPOSE AND OBJECTIVES
During the phase-in period, the contractor shall review and become familiar with applicable NASA regulations, policies, and procedures. The contractor shall take necessary action to submit deliverables and ensure staff has obtained all required licenses and certifications to begin full contract performance on April 1, 2021, under contract number NNG20WATBD.
The contractor shall use the phase-in period to begin integrating the requirements and deliverables of the contract while obtaining knowledge of the facilities, grounds, and operations required to support the NASA Balloon Program. During this period of time, the incoming contractor shall work with the Government and the incumbent contractor to ensure a smooth and effective transition.
Upon completion of the phase-in period, the contractor shall be completely responsible for all services and operations required under the NBOC II.
3. REQUIREMENTS
The Contractor shall develop and implement a phase-in plan to be approved by NASA that defines the Contractor’s approach to fully and optimally transition management, operations, engineering, technical, and administrative functions from the incumbent contractor. The Contractor shall assume full responsibility for all contractual obligations beginning with the effective date of the contract. The phase-in period shall be performed within 59 days immediately prior to the effective date of the contract (currently phase-in is anticipated for
February 1, 2021 through March 31, 2021). The Contractor shall coordinate and lead the transition team. The phase-in process shall not adversely affect work performed by the incumbent. The Contractor is responsible for ensuring continuity of operations, technology development, program planning support, management and administrative support, pending procurements, and fulfillment of all contract deliverables pending from the previous contract as well as those on the next contract in order to meet all of NASA’s mission schedules, requirements, and planned costs. A written weekly status report shall be submitted that identifies and summarizes new and ongoing major and critical activities, schedule, progress, risk, and contingency operations. Informal, as needed, teleconferences shall be conducted by the Contractor with the COR.
During the phase-in period the contractor is expected to begin and/or continue work on meeting contract deliverables stated in contract NNG20WATBD. Table 1 identifies major contract deliverables that shall be submitted after contract effective date.
Deliverable Periodic Date or Specific Due Date Comments Contract Ref. Delivery Method
Quality Manual Within 30 days of contract effective date
Implementation of quality processes for all critical elements
SOW Section 3.1.2
Electronic Copies to COR
Reliability and Quality Assurance Plan
Within 30 days of contract effective date
Define track and record for quality performance, implementation, and improvement
SOW Section 3.1.3
Electronic Copies to COR
Configuration Management Control Plan
Within 30 days of contract effective date
Define the process for identification, control, and verification of the development, reconfiguration, and refurbishment of all mission and safety critical systems and processes
SOW Section 3.1.4
Electronic Copies to COR
Training and Certification Plan
Within 30 days of contract effective date
How the Contractor will identify, maintain, schedule, conduct, and document training, licensing, and certification for personnel and equipment
SOW Section 3.1.7
Electronic Copies to COR
IT Security Plan Within 30 days of contract effective date
Describe the security measures and program safeguards for all IT assets
SOW Section 3.1.8
Electronic Copies to COR
Define Management Positions
45 days prior to contract effective date
Names of critical management positions for Contractor Program and CSBF Management
SOW Section 3.1.9
Electronic Copies to COR
Safety and Health Plan
Within 60 day of contract effective date
A comprehensive safety and health program plan
SOW Section 3.1.6
Electronic Copies to COR in accordance with the
SOW
Risk Assessment Within 15 days prior to contract effective date
A comprehensive risk assessment in accordance with the SOW
SOW Section 3.1.5
Electronic Copies to COR
Aircraft Support Within 30 days prior to contract effective date
A concise and comprehensive plan on execution of aircraft support requirements in accordance with the SOW
SOW Section 3.2.8
Electronic Copies to COR
4. PERIOD OF PERFORMANCE
The phase-in period for the NBOC will last 60 days beginning February 1, 2021 and ending March 31, 2021.
End of SOW