Enclosure 3 - Balloon Phase-In SOW 1.10.2020 LBH-TS Inspected - Copy.pdf

PDF 43 KB Posted

Attached to
NASA Balloon Operations Contract (NBOC) II Federal contract opportunity
Solicitation number
80GSFC20R0031
Issued by
National Aeronautics and Space Administration Goddard Space Center

About this file

This statement of work outlines phase-in activities for the NASA Balloon Operations Contract II. The contractor shall perform phase-in from February 1, 2021 through March 31, 2021 to transition management, operations, engineering and administrative functions from the incumbent contractor. During this period the contractor shall review NASA regulations and procedures, submit required deliverables including quality plans and certifications, and integrate contract requirements to ensure full performance begins on April 1, 2021. Major deliverables such as safety and training plans must be submitted within 60 days of the contract effective date. The contractor shall coordinate the transition team and maintain continuity of operations to meet NASA mission schedules and costs. The phase-in period will ready the contractor to assume responsibility for all contractual obligations under solicitation number 80GSFC20R0031, the NASA Balloon Operations Contract II follow-on awarded by the National Aeronautics and Space Administration Goddard Space Center.

View the file

Other files for this federal contract opportunity

Other files attached to NASA Balloon Operations Contract (NBOC) II, newest first.
File Type Posted
SF30 amend 4 1-6-21 LBH Signed.pdf PDF
Questions and Responses January 6 2021 LBH.pdf PDF
SF30 amend 3 1-5-21 Signed.pdf PDF
RFP NBOC II Contract Clauses - Sections B-M Final 1-5-21 LBH.pdf PDF
Attachment F - Direct Indirect Labor Rates 12-2-20 LBH - AMW.pdf PDF
Enclosure 3 NBOC II - Phase-In SOW 12.17.2020 LBH - AMW.pdf PDF
Exh Cost Plus AF or FF Hybrid CORE-IDIQ RTOs Onsite and Offsite by GFY -RFP Final Revision 12-14-2020 719pm LBH - AMW.pdf PDF
SF33-14a 12-17-20 Revised -AMW.pdf PDF
RFP NBOC II Contract Clauses - Sections B-M Final 12-17-20 with changes accepted LBH-AMW.pdf PDF
RFP questions-12-17-20 500pm-TS - LBH redacted - AMW.pdf PDF
SF30 amend 2 12-17-20 page 1 and 2 - AMW Signed.pdf PDF
Wage Determination 2015-5454- Rev 14 LBH - AMW.pdf PDF
Attach A SOW 12-17-20 Redacted LBH - AMW.pdf PDF
Exhibit 18-NBOC 2 - PastPerfQuestionaire 12-2-20 redacted LBH - AMW.pdf PDF
FRFP Cover Letter 12-17-20-Revised Final - AMW.pdf PDF
SF30 amend 1 Signed 12-10-20.pdf PDF
Attachment J - Reliability and Quality Assurance Plan Cover TS-Inspected TS.pdf PDF
Attachment M- Contract Historical Data TS-TS Inspected.pdf PDF
Attachment P - IT Security Applicable Documents List 11-13-2020 LBH-TS Inspected.pdf PDF
Attachment R - CSBF FY20 Real Property Manual 05-15-20 TS-TS Inspected.pdf PDF
Exh Cost Plus AF or FF Hybrid CORE-IDIQ RTOs Onsite and Offsite by GFY -RFP Final Revision 11-13-2020-TS Inspected.pdf PDF
Attachment B - Balloon Inventory 1.14.20 Sanitized TS.pdf PDF
FRFP Cover Letter 11-13-20-Inspected TS.pdf PDF
RFP NBOC II Contract Clauses - Sections B-M Final sanitized-TS Inspected.pdf PDF
SF33-14a 11-13-20.pdf PDF
Attachment B - Complete inventory 01-2020 Sanitized TS.pdf PDF
Enclosure 2 - NBOC Surveillance Plan September 2019.pdf PDF
Exhibit 18-NBOC 2 - PastPerfQuestionaire LBH-TS Inspected.pdf PDF
Attachment A - NBOC II SOW LBH-Inspected TS.pdf PDF
Attachment B CSBF FHW Inventory 8-28-2020 LBH-Inspected TS.pdf PDF
Attachment B - CSBF Real Property List Sanitized TS.pdf PDF
Attachment D - Safety and Health Plan Cover TS-Inspected TS.pdf PDF
Attachment E - Financial management instructions 533 Attach Core and IDIQ--Both Onsite and Offsite LBH-TS Inspected.pdf PDF
Attachment H - IT Security Management Plan Cover TS-Inspected TS.pdf PDF
Attachment K - WBS - SOW Dictionary August 26 2020 LBH-Inspected TS.pdf PDF
Enclosure 1 NBOC II Scenarios 2-10-20 LBH-TS Inspected.pdf PDF
Enclosure 5 Historical Data - NBOC II LBH-TS Inspected.pdf PDF
Attachment C WD 15-5812 Rev 13 TX-TS Inspected.pdf PDF
Attachment F - Direct Indirect Labor Rates TS-TS Inspected.pdf PDF
Attachment G - Organizational Conflicts of Interest Avoidance Plan Cover TS-TS Inspected.pdf PDF
Attachment L - New Technology Reporting Plan (cover) TS-Inspected TS.pdf PDF
Attachment N - Personal Identiy Verification Issuance Procedures LBH-TS Inspected.pdf PDF
Attachment O -NBOC II- Applicable Standards and Policy Documents 9-29-2020 LBH-TS Inspected.pdf PDF
Attachment Q Contractor Proposed Enhancements Attachment LBH-TS Inspected.pdf PDF
Enclosure 4 - Information Technology Security Management Plan Template Sanitized-TS Inspected - Copy.pdf PDF
Attachment C WD 15-5445 Rev 10 NM-TS Inspected.pdf PDF
Attachment I - Small Business Subcontracting Plan Cover TS-TS Inspected.pdf PDF
Show all 47

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

FOR

PHASE-IN ACTIVITIES

NASA BALLOON OPERATIONS CONTRACT (NBOC II) JANUARY 2020

1. BACKGROUND INFORMATION

A complete description of the NASA Balloon Operations Contract (NBOC II) is contained in contract number NNG20WATBD. The purpose of this Statement of Work (SOW) is to conduct phase-in activities associated with this contract. Phase-in will be conducted under this contract at the Columbia Scientific Balloon Facility (CSBF), Palestine, TX and any remote locations identified in the NBOC II SOW in which operations activities are ongoing.

The contractor shall perform phase-in activities leading to readiness to assume full performance of the NBOC II on April 1, 2021. During the phase-in period, the contractor shall not be responsible for performance of the effort described in the NBOC0-2 SOW, Attachment A, of contract number NNG20WATBD.

2. PURPOSE AND OBJECTIVES

During the phase-in period, the contractor shall review and become familiar with applicable NASA regulations, policies, and procedures. The contractor shall take necessary action to submit deliverables and ensure staff has obtained all required licenses and certifications to begin full contract performance on April 1, 2021, under contract number NNG20WATBD.

The contractor shall use the phase-in period to begin integrating the requirements and deliverables of the contract while obtaining knowledge of the facilities, grounds, and operations required to support the NASA Balloon Program. During this period of time, the incoming contractor shall work with the Government and the incumbent contractor to ensure a smooth and effective transition.

Upon completion of the phase-in period, the contractor shall be completely responsible for all services and operations required under the NBOC II.

3. REQUIREMENTS

The Contractor shall develop and implement a phase-in plan to be approved by NASA that defines the Contractor’s approach to fully and optimally transition management, operations, engineering, technical, and administrative functions from the incumbent contractor. The Contractor shall assume full responsibility for all contractual obligations beginning with the effective date of the contract. The phase-in period shall be performed within 59 days immediately prior to the effective date of the contract (currently phase-in is anticipated for

February 1, 2021 through March 31, 2021). The Contractor shall coordinate and lead the transition team. The phase-in process shall not adversely affect work performed by the incumbent. The Contractor is responsible for ensuring continuity of operations, technology development, program planning support, management and administrative support, pending procurements, and fulfillment of all contract deliverables pending from the previous contract as well as those on the next contract in order to meet all of NASA’s mission schedules, requirements, and planned costs. A written weekly status report shall be submitted that identifies and summarizes new and ongoing major and critical activities, schedule, progress, risk, and contingency operations. Informal, as needed, teleconferences shall be conducted by the Contractor with the COR.

During the phase-in period the contractor is expected to begin and/or continue work on meeting contract deliverables stated in contract NNG20WATBD. Table 1 identifies major contract deliverables that shall be submitted after contract effective date.

Deliverable Periodic Date or Specific Due Date Comments Contract Ref. Delivery Method

Quality Manual Within 30 days of contract effective date

Implementation of quality processes for all critical elements

SOW Section 3.1.2

Electronic Copies to COR

Reliability and Quality Assurance Plan

Within 30 days of contract effective date

Define track and record for quality performance, implementation, and improvement

SOW Section 3.1.3

Electronic Copies to COR

Configuration Management Control Plan

Within 30 days of contract effective date

Define the process for identification, control, and verification of the development, reconfiguration, and refurbishment of all mission and safety critical systems and processes

SOW Section 3.1.4

Electronic Copies to COR

Training and Certification Plan

Within 30 days of contract effective date

How the Contractor will identify, maintain, schedule, conduct, and document training, licensing, and certification for personnel and equipment

SOW Section 3.1.7

Electronic Copies to COR

IT Security Plan Within 30 days of contract effective date

Describe the security measures and program safeguards for all IT assets

SOW Section 3.1.8

Electronic Copies to COR

Define Management Positions

45 days prior to contract effective date

Names of critical management positions for Contractor Program and CSBF Management

SOW Section 3.1.9

Electronic Copies to COR

Safety and Health Plan

Within 60 day of contract effective date

A comprehensive safety and health program plan

SOW Section 3.1.6

Electronic Copies to COR in accordance with the

SOW

Risk Assessment Within 15 days prior to contract effective date

A comprehensive risk assessment in accordance with the SOW

SOW Section 3.1.5

Electronic Copies to COR

Aircraft Support Within 30 days prior to contract effective date

A concise and comprehensive plan on execution of aircraft support requirements in accordance with the SOW

SOW Section 3.2.8

Electronic Copies to COR

4. PERIOD OF PERFORMANCE

The phase-in period for the NBOC will last 60 days beginning February 1, 2021 and ending March 31, 2021.

End of SOW