The document is a comprehensive project manual for the Orange County Courthouse Elevator Modernization Project (Y20-821), prepared by Lerch Bates, Inc. in Tampa, Florida. The project involves the modernization of 19 of 20 elevators located in the Orange County Courthouse Complex, specifically Elevators 1-14, 16-19, and 24, with Elevator 15 being excluded due to recent upgrades. The modernization is an emergency bid scheduled for sealed offer submission by 4:00 pm EST on Tuesday, July 16, 2024, with an estimated project cost of $13,000,000. The project requires comprehensive elevator system upgrades, including replacing major and minor components, refurbishing existing components, and ensuring full code compliance across all applicable regulations.
The project will be constructed under a lump sum contract, with work primarily performed inside the existing building during normal business hours, Monday through Friday. Contractors must coordinate closely with the Owner to minimize disruptions to courthouse operations, with specific requirements for noise, material transportation, and work phasing. The modernization includes detailed specifications for electrical systems, machine room equipment, hoistway components, car equipment, communication systems, and identification protocols. Bidders are required to submit responses electronically via the OpenGov e-Procurement Platform, with technical support available and a specific timeline for submitting questions (deadline: Monday, July 8, 2024 at 5:00 pm EST). The project emphasizes maintaining existing building functionality, preserving fire resistance ratings, and ensuring comprehensive code compliance throughout the elevator modernization process.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT MANUAL
100% CONSTRUCTION
DOCUMENTS
Orange County Courthouse Elevator Modernization Y20-821
Lerch Bates, Inc.
3802 Ehrlich Rd
Suite 110, Tampa, FL 33624
November 2023 Volume No. 1 of 1
Table of Contents
Division Section Title
SPECIFICATIONS GROUP
DIVISION 01 - GENERAL REQUIREMENTS
010100 SUMMARY OF WORK
010270 APPLICATION FOR PAYMENT
010350 MODIFICATION PROCEDURES
010400 QUALITY REQUIREMENTS
011000 SUMMARY
013300 SUBMITTAL PROCEDURES
014000 QUALITY REQUIREMENTS
016000 MATERIAL AND HANDLING
016310 SUBSTITUTIONS
017000 FINAL COMPLIANCE REVIEW
017329 CUTTING AND PATCHING
017400 WARRANTIES
017823 OPERATION AND MAINTENANCE DATA
018000 MAINTANANCE
019000 RELATED WORK
DIVISION 14 - CONVEYING EQUIPMENT
142200 ELEVATOR TECHNICAL SPECIFICATIONS
DIVISION 26 - ELECTRICAL
260500 COMMON WORK RESULTS FOR ELECTRICAL
260501 INVESTIGATION OF EXISTING ELECTRICAL SYSTEMS
260519 LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES
260526 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS
260529 HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS
260533 RACEWAY AND BOXES FOR ELECTRICAL SYSTEMS
260553 IDENTIFICATION FOR ELECTRICAL SYSTEMS
262726 WIRING DEVICES
END OF TABLE OF CONTENTS
ORANGE COUNTY COURTHOUSE
ELEVATOR MODERNIZATION
SECTION 01 00 00
INSTRUCTIONS TO CONTRACTOR
SECTION 00100
TABLE OF CONTENTS
PART 1 GENERAL
1.01 EXAMINATION
SECTION 01 00 00
INSTRUCTIONS TO CONTRACTOR
INSTRUCTIONS TO CONTRACTOR 010000 - 1
SECTION 01 00 00
INSTRUCTIONS TO CONTRACTOR
PART 1 GENERAL
1.01 EXAMINATION
A. In order to discover and resolve conflicts or lack of definition which might create problems, Contractor must review Contract Documents, existing site conditions, and existing equipment specified to be retained for compatibility with its product prior to submitting Bid. Site review shall include, but not be limited to: adequacy of access, retained equipment, elevator hoistways, pits, machine rooms, overhead clearances, electrical power characteristics, structural supports, etc. Investigation and structural calculations required to determine compliance of existing elevator components including machine support beams, with ASME A17.1 are responsibility of Contractor. Owner will not pay for change to building structure, structural supports, mechanical, electrical, or other systems required to accommodate Contractor’s equipment.
B. Submission of Bid is considered evidence that Contractor has visited and is conversant with the site facilities, site conditions, requirements of the Contract Documents, pertinent state and local codes, state of labor and material markets, and has made due allowance in his Bid for all contingencies. Should Contractor’s investigation of site conditions or local codes or rules reveal requirements contrary to Contract Documents, or if Contractor finds any discrepancies or omissions from Contract Documents, or if Contractor is in doubt as to their meaning, it shall contact the Owner for clarification at least ten (10) working days prior to Bid due date.
C. No oral explanation will be made and no oral instructions will be given before Bid due date. Contractor shall act promptly and allow sufficient time for a reply to reach it before submission of its Bid. Any required interpretation or supplemental instructions will be issued in the form of an addendum to the specifications and forwarded to all Contractors.
D. Provide everything necessary for and incidental to the satisfactory completion of work required by Contract Documents. All required preparations and hoisting and movement of equipment, or removal of existing equipment shall be the responsibility of Contractor.
END OF SECTION
Orange County Courthouse Elevator Modernization
SUMMARY 01 01 00 - 1
SECTION 01 01 00 - SUMMARY
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. This Section includes the following:
1. Work covered by the Contract Documents.
2. Use of premises.
3. Owner's occupancy requirements.
4. Work restrictions.
5. Specification formats and conventions.
1.3 WORK COVERED BY CONTRACT DOCUMENTS
A. The Work consists of the following:
1. The Work includes the Alteration for 19 of 20 elevators located at the Orange County Courthouse Complex, specifically Elevators 1-14, 16-19, 24. Elevator 15 shall not be modernized as it has undergone recent upgrades and shall have an estimated remaining life cycle of 10 years. For the purpose of the specification’s intent, the alteration shall be referred to as an elevator modernization, replacing major and minor components, refurbishing components and testing all systems to ensure full code compliance with all applicable codes is the Elevator Contractor’s sole responsibility, inclusive of the building related work required by Electrician, Mechanical, Fire Alarm and General Contractor(s).
2. Elevators 1-5, 7-9, 12-14, 16-19 (15 total cabs); require cab interior work, inclusive of a like for like interior replacement (excluding flooring) and new cab ceilings to achieve code compliant lighting levels.
3. This scope is complimented by the set of construction drawings and specifications.
1.4 TYPE OF CONTRACT
A. Project will be constructed under lump sum contract.
1.5 USE OF PREMISES
A. General: Contractor shall have limited use of premises for construction operations as indicated on Drawings by the Contract limits.
SUMMARY 01 01 00 - 2
B. Use of Site: Limit use of premises to work in areas indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.
1. Owner Occupancy: Allow for Owner occupancy of Project site and use by the public.
2. Driveways and Entrances: Keep driveways, parking areas, loading areas, and entrances serving premises clear and available to Owner, Owner's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.
a. Schedule deliveries to minimize use of driveways and entrances.
b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
C. Use of Existing Building: Maintain existing building in a weathertight condition throughout construction period. Repair damage caused by construction operations. Protect building and its occupants during construction period.
1.6 OWNER'S OCCUPANCY REQUIREMENTS
A. Full Owner Occupancy: Owner will occupy site and existing building during entire construction period.
Cooperate with Owner during construction operations to minimize conflicts and facilitate Owner usage.
Perform the Work so as not to interfere with Owner's day-to-day operations. Maintain existing exits, unless otherwise indicated.
1. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities.
Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Owner and authorities having jurisdiction.
2. Provide not less than 72 hours' notice to Owner of activities that will affect Owner's operations.
1.7 WORK RESTRICTIONS
A. On-Site Work Hours: Work shall be generally performed inside the existing building during normal business working hours of the facility., Monday through Friday, except otherwise indicated for odorous and work that has noise levels that impact the facility’s operation.
1. Weekend Hours: To be coordinated with Owner as needed to keep from obstructing Owners occupancy during change out of equipment or any outage requirements.
2. Hours for Utility Shutdowns: to be coordinated with Owners Representative with a minimum of 72 hours required for shut down.
B. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Owner or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:
1. Notify Owner not less than 3 days in advance of proposed utility interruptions.
2. Do not proceed with utility interruptions without Owner's written permission.
1.8 SPECIFICATION FORMATS AND CONVENTIONS
A. Specification Format: The Specifications are organized into Divisions and Sections using the 50-division format and CSI/CSC's "MasterFormat" numbering system.
SUMMARY 01 01 00 - 3
1. Section Identification: The Specifications use Section numbers and titles to help cross-referencing in the Contract Documents. Sections in the Project Manual are in numeric sequence;
however, the sequence is incomplete because all available Section numbers are not used.
Consult the table of contents at the beginning of the Project Manual to determine numbers and names of Sections in the Contract Documents.
2. Division 01: Sections in Division 01 govern the execution of the Work of all Sections in the Specifications.
B. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations. These conventions are as follows:
1. Abbreviated Language: Language used in the Specifications and other Contract Documents is abbreviated. Words and meanings shall be interpreted as appropriate. Words implied, but not stated, shall be inferred as the sense requires. Singular words shall be interpreted as plural, and plural words shall be interpreted as singular where applicable as the context of the Contract Documents indicates.
2. Imperative mood and streamlined language are generally used in the Specifications.
Requirements expressed in the imperative mood are to be performed by Contractor.
Occasionally, the indicative or subjunctive mood may be used in the Section Text for clarity to describe responsibilities that must be fulfilled indirectly by Contractor or by others when so noted.
a. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 10 00
PAGE INTENTIONALLY LEFT BLANK
SUMMARY 01 01 00 - 4
SECTION 01 04 00
PROJECT PROCEDURES
SECTION 01 04 00
TABLE OF CONTENTS
PART 1 GENERAL
1.01 APPLICABLE CODES
1.02 STAGING AREA
1.03 WORK PHASE
1.04 OCCUPANCY AND WORK BY OTHERS
SECTION 01 04 00
PROJECT PROCEDURES
PROJECT PROCEDURES 01 04 00 - 1
SECTION 01 04 00
PROJECT PROCEDURES
PART 1 GENERAL
1.01 APPLICABLE CODES
A. Compliance with Regulatory Agencies: Comply with most stringent applicable provisions of following Codes, laws, and/or Authorities, including revisions and changes in effect:
1. Safety Code for Elevators and Escalators, ASME A17.1
2. Guide for Inspection of Elevators, Escalators, and Moving Walks, ASME
A17.2
3. Elevator and Escalator Electrical Equipment, ASME A17.5
4. National Electrical Code, NFPA 70
5. Americans with Disabilities Act, ADA
6. Local Fire Authority
7. Requirements of most stringent provision of local applicable building code.
8. Life Safety Code, NFPA 101
9. Applicable Florida Accessibility Codes.
1.02 STAGING AREA
A. As directed by Owner.
1.03 WORK PHASE
A. Perform work by removing only one elevator from service in the same group at a time with the exception for testing and interfacing purposes which shall be performed during afterhours per the Owner’s approval.
APPLICATION FOR PAYMENT SECTION 011027 - 1
SECTION 010270 - APPLICATION FOR PAYMENT
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this Section.
1.2 SUMMARY
A. This Section specifies administrative and procedural requirements governing the Contractor's Applications for Payment.
1. Coordinate the Schedule of Values and Applications for Payment with the Contractor's Construction Schedule, Submittal Schedule, and List of Subcontracts.
1.3 SCHEDULE OF VALUES
A. Coordination: Coordinate preparation of the Schedule of Values with preparation of the Contractor's Construction Schedule.
1. Correlate line items in the Schedule of Values with other required administrative schedules and forms, including:
a. Contractor's Construction Schedule.
b. Application for Payment forms, including Continuation Sheets.
c. List of subcontractors.
d. Schedule of allowances.
e. Schedule of alternates.
f. List of products.
g. List of principal suppliers and fabricators.
h. Schedule of submittals.
2. Submit the Schedule of Values to the County’s designated Representative and Architect at the Pre-Construction meeting.
B. Format and Content: Use the County form
1. Identification: Include the following Project identification on the Schedule of Values:
a. Project name and location.
b. Name of the Architect.
c. Project number.
d. Contractor's name and address.
e. Date of submittal.
f. Change Orders shall be added as they are approved.
APPLICATION FOR PAYMENT SECTION 011027 - 2
2. Percentage of Contract Sum to nearest one-hundredth percent, adjusted to total 100 percent.
3. Provide a breakdown of the Contract Sum in sufficient detail to facilitate continued evaluation of Applications for Payment and progress reports. Coordinate with the Project Manual table of contents. Break principal subcontract amounts down into several line items.
4. Provide a separate line item in the Schedule of Values for each part of the Work where Applications for Payment may include materials or equipment, purchased or fabricated and stored, but not yet installed.
a. Materials shall be stored on-site only to be included in the Application for Payment.
5. Provide separate line items on the Schedule of Values for initial cost of the materials, for each subsequent stage of completion, and for total installed value of that part of the Work.
6. Margins of Cost: Show line items for indirect costs and margins on actual costs only when such items are listed individually in Applications for Payment. Each item in the Schedule of Values and Applications for Payment shall be complete. Include the total cost and proportionate share of general overhead and profit margin for each item.
a. Temporary facilities and other major cost items that are not direct cost of actual work-in-place may be shown either as separate line items in the Schedule of Values or distributed as general overhead expense, at the Contractor's option.
1.4 APPLICATIONS FOR PAYMENT
A. Each Application for Payment shall be consistent with previous applications and payments as certified by the Architect and paid for by the Owner.
1. The initial Application for Payment, the Application for Payment at time of Substantial Completion, and the final Application for Payment involve additional requirements.
B. Payment-Application Times: Each progress-payment date is indicated in the Agreement.
The period of construction Work covered by each Application for Payment is the period indicated in the Agreement.
C. Payment-Application Forms: Use County form for Applications for Payment.
D. Application Preparation: Complete every entry on the form. Include notarization and execution by a person authorized to sign legal documents on behalf of the Contractor. The Architect will return incomplete applications without action.
1. Entries shall match data on the Schedule of Values and the Contractor's Construction Schedule.
2. Change Orders amounts may only be shown on the Application for Payment when they are fully executed and approved by the County.
APPLICATION FOR PAYMENT SECTION 011027 - 3
E. A field review shall be made by the Owner, Architect and the General Contractor one week before Final copies are transmitted to the Architect for his recommendation to the Owner.
The Application for Payment shall only include work completed and materials used or stored on site as of the time and date of the field review.
F. Transmittal: Submit 5 signed and notarized original copies of each Application for Payment.
G. Application for Payment at Substantial Completion: Following issuance of the Certificate of Substantial Completion, submit an Application for Payment.
1. Administrative actions and submittals that shall precede or coincide with this application include:
a. Occupancy permits and similar approvals.
b. Test/adjust/balance records.
c. Equipment demonstrations.
d. Final cleaning.
e. Keys.
H. Final Payment Application: Administrative actions and submittals that must precede or coincide with submittal of the final Application for Payment include the following:
1. Completion of Project closeout requirements.
2. Completion of items specified for completion after Substantial Completion.
3. Ensure that unsettled claims will be settled.
4. Ensure that incomplete Work is not accepted and will be completed without undue delay.
5. Transmittal of required Project construction records to the Owner.
6. Removal of temporary facilities and services.
7. Removal of surplus materials, rubbish, and similar elements.
8. Warranties (guarantees) and maintenance agreements.
9. Maintenance instructions.
10. Meter readings.
11. Contractor’s release of lien (on County form)
12. Sub-Contractor’s and supplier’s release of lien
13. Consent of Surety (dated and notarized)
14. Power-of-Attorney (dated and notarized)
15. Asbestos-Free statement on Contractor’s letterhead (dated and notarized)
PART 2 - PRODUCTS - (Not Applicable)
PART 3 - EXECUTION - (Not Applicable)
MODIFICATION PROCEDURES SECTION 011035 - 1
SECTION 010350 - MODIFICATION PROCEDURES
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this Section.
1.2 SUMMARY
A. This Section specifies administrative and procedural requirements for handling and processing contract modifications.
B. Related Sections: The following Sections contain requirements that relate to this Section:
1. Section 013000 "Submittals" for requirements for the Contractor's Construction Schedule.
2. Section 010270 "Applications for Payment" for administrative procedures governing Applications for Payment.
3. Section 016310 "Substitutions" for administrative procedures for handling requests for substitutions made after award of the Contract.
1.3 MINOR CHANGES IN THE WORK
A. The Architect will issue supplemental instructions authorizing minor changes in the Work, not involving adjustment to the Contract Sum or Contract Time, on Architect's standard Supplemental Instructions form.
1.4 CHANGE ORDER PROPOSAL REQUESTS
A. Owner-Initiated Proposal Requests: The Architect will issue a detailed description of proposed changes in the Work that will require adjustment to the Contract Sum or Contract Time. If necessary, the description will include supplemental or revised Drawings and Specifications.
1. Proposal requests issued by the Architect are for information only. Do not consider them as an instruction either to stop work in progress or to execute the proposed change.
2. Within 14 days of receipt of a proposal request, submit an estimate of cost necessary to execute the change to the Architect for the Owner's review.
a. Include a list of quantities of products required and unit costs, with the total amount of purchases to be made. Where requested, furnish survey data to substantiate quantities.
b. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.
MODIFICATION PROCEDURES SECTION 011035 - 2
c. Include a statement indicating the effect the proposed change in the Work will have on the Contract Time.
B. Contractor-Initiated Proposals: When latent or unforeseen conditions require modifications to the Contract, the Contractor may propose changes by submitting a request for a change to the Architect.
1. Include a statement outlining the reasons for the change and the effect of the change on the Work. Provide a complete description of the proposed change. Indicate the effect of the proposed change on the Contract Sum and Contract Time.
2. Include a list of quantities of products required and unit costs, with the total amount of purchases to be made. Where requested, furnish survey data to substantiate quantities.
3. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.
4. Comply with requirements in Section "Product Substitutions" if the proposed change requires substitution of one product or system for a product or system specified.
5. Contractor-initiated proposals shall be submitted within 15 days of the event causing the change.
C. Proposal Request Form: Use forms which will be provided by the Architect. Sample copies are included at the end of this Section.
1.6 CONSTRUCTION CHANGE DIRECTIVE
A. Construction Change Directive: When the Owner and the Contractor disagree on the terms of a Proposal Request, the Architect may issue a Construction Change Directive. The Construction Change Directive instructs the Contractor to proceed with a change in the Work, for subsequent inclusion in a Change Order.
1. The Construction Change Directive contains a complete description of the change in the Work. It also designates the method to be followed to determine change in the Contract Sum or Contract Time.
B. Documentation: Maintain detailed records on a time and material basis of work required by the Construction Change Directive.
1. After completion of the change, submit an itemized account and supporting data necessary to substantiate cost and time adjustments to the Contract.
1.7 CHANGE ORDER PROCEDURES
A. On the County’s standard form.
PART 2 - PRODUCTS - (Not Applicable)
MODIFICATION PROCEDURES SECTION 011035 - 3
MODIFICATION PROCEDURES SECTION 011035 - 4
THIS SHEET INTENTIONALLY LEFT BLANK
SUBMITTAL PROCEDURES 01 33 00 - 1
SECTION 01 33 00 - SUBMITTAL PROCEDURES
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. This Section includes administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other submittals.
1.3 DEFINITIONS
A. Action Submittals: Written and graphic information that requires Owner’s responsive action.
B. Informational Submittals: Written information that does not require Engineer’s and Owner’s responsive action. Submittals may be rejected for not complying with requirements.
1.4 SUBMITTAL PROCEDURES
A. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.
1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.
2. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination.
a. Owner and Engineer’s reserve the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.
B. Submittals Schedule: All submittals shall be received by the Owner within 14 days of notice to proceed. Submittals shall be approved prior to commencement of work.
C. Processing Time: Allow enough time for submittal review, including time for resubmittals, as follows. Time for review shall commence on Engineers receipt of submittal. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including resubmittals.
1. Initial Review: Allow 15 days for initial review of each submittal. Allow additional time if coordination with subsequent submittals is required. The Owner will advise Contractor when a submittal being processed must be delayed for coordination.
2. Intermediate Review: If intermediate submittal is necessary, process it in same manner as initial submittal.
3. Resubmittal Review: Allow 15 days for review of each resubmittal.
SUBMITTAL PROCEDURES 01 33 00 - 2
4. Sequential Review: Where sequential review of submittals by Architect's consultants, Owner, or other parties is indicated, allow 21 days for initial review of each submittal.
D. Identification: Place a permanent label or title block on each submittal for identification.
1. Indicate name of firm or entity that prepared each submittal on label or title block.
2. Provide a space approximately 6 by 8 inches on label or beside title block to record
Contractor's review and approval markings and action taken by Engineer.
3. Include the following information on label for processing and recording action taken:
a. Project name.
b. Date.
c. Name and address of Engineer.
d. Name and address of Contractor.
e. Name and address of subcontractor.
f. Name and address of supplier.
g. Name of manufacturer.
h. Submittal number or other unique identifier, including revision identifier.
1) Submittal number shall use Specification Section number followed by a decimal point and then a sequential number (e.g., 06100.01). Resubmittals shall include an alphabetic suffix after another decimal point (e.g., 06100.01.A).
E. Resubmittals: Make resubmittals in same form and number of copies as initial submittal.
1. Note date and content of previous submittal.
2. Note date and content of revision in label or title block and clearly indicate extent of revision.
F. Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers, fabricators, installers, authorities having jurisdiction, and others as necessary for performance of construction activities. Show distribution on transmittal forms.
PART 2 - PRODUCTS
2.1 ACTION SUBMITTALS
A. General: Prepare and submit Action Submittals required by individual Specification Sections.
B. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.
1. If information must be specially prepared for submittal because standard printed data are not suitable for use, submit as Shop Drawings, not as Product Data.
2. Mark each copy of each submittal to show which products and options are applicable.
3. Include the following information, as applicable:
a. Manufacturer's written recommendations.
b. Manufacturer's product specifications.
c. Manufacturer's installation instructions.
d. Standard color charts.
e. Manufacturer's catalog cuts.
f. Wiring diagrams showing factory-installed wiring.
SUBMITTAL PROCEDURES 01 33 00 - 3
g. Printed performance curves.
h. Operational range diagrams.
i. Mill reports.
j. Standard product operation and maintenance manuals.
k. Compliance with specified referenced standards.
l. Testing by recognized testing agency.
m. Application of testing agency labels and seals.
n. Notation of coordination requirements.
4. Submit Product Data before or concurrent with Samples.
5. Number of Copies: Submit 7 copies of Product Data, unless otherwise indicated. Engineer will return 6 copies. Mark up and retain one returned copy as a Project Record Document.
C. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data
1. Preparation: Fully illustrate requirements in the Contract Documents. Include the following information, as applicable:
a. Dimensions.
b. Identification of products.
c. Fabrication and installation drawings.
d. Roughing-in and setting diagrams.
e. Wiring diagrams showing field-installed wiring, including power, signal, and control wiring.
f. Shopwork manufacturing instructions.
g. Templates and patterns.
h. Schedules.
i. Design calculations.
j. Compliance with specified standards.
k. Notation of coordination requirements.
l. Notation of dimensions established by field measurement.
m. Relationship to adjoining construction clearly indicated.
n. Seal and signature of professional engineer if specified.
o. Wiring Diagrams: Differentiate between manufacturer-installed and field-installed wiring.
2. Sheet Size: Except for templates, patterns, and similar full-size drawings, submit Shop Drawings on sheets at least 8-1/2 by 11 inches but no larger than 30 by 40 inches.
PART 3 - EXECUTION
3.1 CONTRACTOR'S REVIEW
A. Review each submittal and check for coordination with other Work of the Contract and for compliance with the Contract Documents. Note corrections and field dimensions. Mark with approval stamp before submitting to Engineer.
B. Approval Stamp: Stamp each submittal with a uniform, approval stamp.
SUBMITTAL PROCEDURES 01 33 00 - 4
3.2 ENGINEER’S ACTION
A. General: Engineer will not review submittals that do not bear Contractor's approval stamp and will return them without action.
B. Action Submittals: Engineer will review each submittal, make marks to indicate corrections or modifications required, and return it.
C. Partial submittals are not acceptable, will be considered nonresponsive, and will be returned without review.
D. Submittals not required by the Contract Documents may not be reviewed and may be discarded.
END OF SECTION 01 33 00
QUALITY REQUIREMENTS 01 40 00 - 1
SECTION 01 40 00 - QUALITY REQUIREMENTS
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. This Section includes administrative and procedural requirements for quality assurance and quality control.
B. Testing and inspecting services are required to verify compliance with requirements specified or indicated. These services do not relieve Contractor of responsibility for compliance with the Contract Document requirements.
1. Specific quality-assurance and -control requirements for individual construction activities are specified in the Sections that specify those activities. Requirements in those Sections may also cover production of standard products.
2. Specified tests, inspections, and related actions do not limit Contractor's other quality-assurance and -control procedures that facilitate compliance with the Contract Document requirements.
3. Requirements for Contractor to provide quality-assurance and -control services required by Engineer or authorities having jurisdiction are not limited by provisions of this Section.
C. Related Sections include the following:
1. Division 01 Section "Cutting and Patching" for repair and restoration of construction disturbed by testing and inspecting activities.
2. Divisions 02 through 49 Sections for specific test and inspection requirements.
1.3 DEFINITIONS
A. Quality-Assurance Services: Activities, actions, and procedures performed before and during execution of the Work to guard against defects and deficiencies and substantiate that proposed construction will comply with requirements.
B. Quality-Control Services: Tests, inspections, procedures, and related actions during and after execution of the Work to evaluate that actual products incorporated into the Work and completed construction comply with requirements. Services do not include contract enforcement activities performed by Engineer.
C. Product Testing: Tests and inspections that are performed by an NRTL, an NVLAP, or a testing agency qualified to conduct product testing and acceptable to authorities having jurisdiction, to establish product performance and compliance with industry standards.
D. Source Quality-Control Testing: Tests and inspections that are performed at the source, i.e., plant, mill, factory, or shop.
QUALITY REQUIREMENTS 01 40 00 - 2
E. Field Quality-Control Testing: Tests and inspections that are performed on-site for installation of the Work and for completed Work.
F. Testing Agency: An entity engaged to perform specific tests, inspections, or both. Testing laboratory shall mean the same as testing agency.
G. Installer/Applicator/Erector: Contractor or another entity engaged by Contractor as an employee, Subcontractor, or Sub-subcontractor, to perform a particular construction operation, including installation, erection, application, and similar operations.
1. Using a term such as "carpentry" does not imply that certain construction activities must be performed by accredited or unionized individuals of a corresponding generic name, such as "carpenter." It also does not imply that requirements specified apply exclusively to tradespeople of the corresponding generic name.
1.4 CONFLICTING REQUIREMENTS
A. General: If compliance with two or more standards is specified and the standards establish different or conflicting requirements for minimum quantities or quality levels, comply with the most stringent requirement. Refer uncertainties and requirements that are different, but apparently equal, to Architect for a decision before proceeding.
B. Minimum Quantity or Quality Levels: The quantity or quality level shown or specified shall be the minimum provided or performed. The actual installation may comply exactly with the minimum quantity or quality specified, or it may exceed the minimum within reasonable limits. To comply with these requirements, indicated numeric values are minimum or maximum, as appropriate, for the context of requirements. Refer uncertainties to Architect for a decision before proceeding.
1.5 SUBMITTALS
A. Schedule of Tests and Inspections: Prepare in tabular form and include the following:
1. Specification Section number and title.
2. Description of test and inspection.
3. Identification of applicable standards.
4. Identification of test and inspection methods.
5. Number of tests and inspections required.
6. Time schedule or time span for tests and inspections.
7. Entity responsible for performing tests and inspections.
8. Requirements for obtaining samples.
9. Unique characteristics of each quality-control service.
B. Reports: Prepare and submit certified written reports that include the following:
1. Date of issue.
2. Project title and number.
3. Name, address, and telephone number of testing agency.
4. Dates and locations of samples and tests or inspections.
5. Names of individuals making tests and inspections.
6. Description of the Work and test and inspection method.
7. Identification of product and Specification Section.
8. Complete test or inspection data.
QUALITY REQUIREMENTS 01 40 00 - 3
9. Test and inspection results and an interpretation of test results.
10. Record of temperature and weather conditions at time of sample taking and testing and inspecting.
11. Comments or professional opinion on whether tested or inspected Work complies with the
Contract Document requirements.
12. Name and signature of laboratory inspector.
13. Recommendations on retesting and reinspecting.
C. Permits, Licenses, and Certificates: For Owner's records, submit copies of permits, licenses, certifications, inspection reports, releases, jurisdictional settlements, notices, receipts for fee payments, judgments, correspondence, records, and similar documents, established for compliance with standards and regulations bearing on performance of the Work.
1.6 QUALITY ASSURANCE
A. General: Qualifications paragraphs in this Article establish the minimum qualification levels required; individual Specification Sections specify additional requirements.
B. Installer Qualifications: A firm or individual experienced in installing, erecting, or assembling work similar in material, design, and extent to that indicated for this Project, whose work has resulted in construction with a record of successful in-service performance.
C. Manufacturer Qualifications: A firm experienced in manufacturing products or systems similar to those indicated for this Project and with a record of successful in-service performance, as well as sufficient production capacity to produce required units.
D. Fabricator Qualifications: A firm experienced in producing products similar to those indicated for this Project and with a record of successful in-service performance, as well as sufficient production capacity to produce required units.
E. Professional Engineer Qualifications: A professional engineer who is legally qualified to practice in jurisdiction where Project is located and who is experienced in providing engineering services of the kind indicated. Engineering services are defined as those performed for installations of the system, assembly, or product that are similar to those indicated for this Project in material, design, and extent.
F. Specialists: Certain sections of the Specifications require that specific construction activities shall be performed by entities who are recognized experts in those operations. Specialists shall satisfy qualification requirements indicated and shall be engaged for the activities indicated.
1. Requirement for specialists shall not supersede building codes and regulations governing the Work.
G. Testing Agency Qualifications: An NRTL, an NVLAP, or an independent agency with the experience and capability to conduct testing and inspecting indicated, as documented according to ASTM E 548; and with additional qualifications specified in individual Sections; and where required by authorities having jurisdiction, that is acceptable to authorities.
1. NRTL: A nationally recognized testing laboratory according to 29 CFR 1910.7.
2. NVLAP: A testing agency accredited according to NIST's National Voluntary Laboratory
Accreditation Program.
H. Factory-Authorized Service Representative Qualifications: An authorized representative of manufacturer who is trained and approved by manufacturer to inspect installation of
QUALITY REQUIREMENTS 01 40 00 - 4
manufacturer's products that are similar in material, design, and extent to those indicated for this Project.
I. Preconstruction Testing: Where testing agency is indicated to perform preconstruction testing for compliance with specified requirements for performance and test methods, comply with the following:
1. Contractor responsibilities include the following:
a. Provide test specimens representative of proposed products and construction.
b. Submit specimens in a timely manner with sufficient time for testing and analyzing results to prevent delaying the Work.
c. Provide sizes and configurations of test assemblies, mockups, and laboratory mockups to adequately demonstrate capability of products to comply with performance requirements.
d. Build site-assembled test assemblies and mockups using installers who will perform same tasks for Project.
e. Build laboratory mockups at testing facility using personnel, products, and methods of construction indicated for the completed Work.
f. When testing is complete, remove test specimens, assemblies, mockups, and laboratory mockups; do not reuse products on Project.
1.7 QUALITY CONTROL
A. Owner Responsibilities: Where quality-control services are indicated as Owner's responsibility, Owner will engage a qualified testing agency to perform these services.
1. Owner will furnish Contractor with names, addresses, and telephone numbers of testing agencies engaged and a description of types of testing and inspecting they are engaged to perform.
2. Payment for these services will be made from testing and inspecting allowances, as authorized by Change Orders.
3. Costs for retesting and reinspecting construction that replaces or is necessitated by work that failed to comply with the Contract Documents will be charged to Contractor, and the Contract Sum will be adjusted by Change Order.
B. Tests and inspections not explicitly assigned to Owner are Contractor's responsibility. Unless otherwise indicated, provide quality-control services specified and those required by authorities having jurisdiction. Perform quality-control services required of Contractor by authorities having jurisdiction, whether specified or not.
1. Where services are indicated as Contractor's responsibility, engage a qualified testing agency to perform these quality-control services.
a. Contractor shall not employ same entity engaged by Owner, unless agreed to in writing by Owner.
2. Where quality-control services are indicated as Contractor's responsibility, submit a certified written report, in duplicate, of each quality-control service.
3. Testing and inspecting requested by Contractor and not required by the Contract Documents are Contractor's responsibility.
4. Submit additional copies of each written report directly to authorities having jurisdiction, when they so direct.
QUALITY REQUIREMENTS 01 40 00 - 5
C. Manufacturer's Field Services: Where indicated, engage a factory-authorized service representative to inspect field-assembled components and equipment installation, including service connections. Report results in writing as specified in Division 01 Section "Submittal Procedures."
D. Retesting/Reinspecting: Regardless of whether original tests or inspections were Contractor's responsibility, provide quality-control services, including retesting and reinspecting, for construction that replaced Work that failed to comply with the Contract Documents.
E. Testing Agency Responsibilities: Cooperate with Engineer and Contractor in performance of duties. Provide qualified personnel to perform required tests and inspections.
1. Notify Engineer and Contractor promptly of irregularities or deficiencies observed in the Work during performance of its services.
2. Determine the location from which test samples will be taken and in which in-situ tests are conducted.
3. Conduct and interpret tests and inspections and state in each report whether tested and inspected work complies with or deviates from requirements.
4. Submit a certified written report, in duplicate, of each test, inspection, and similar quality-control service through Contractor.
5. Do not release, revoke, alter, or increase the Contract Document requirements or approve or accept any portion of the Work.
6. Do not perform any duties of Contractor.
F. Associated Services: Cooperate with agencies performing required tests, inspections, and similar quality-control services, and provide reasonable auxiliary services as requested. Notify agency sufficiently in advance of operations to permit assignment of personnel. Provide the following:
1. Access to the Work.
2. Incidental labor and facilities necessary to facilitate tests and inspections.
3. Adequate quantities of representative samples of materials that require testing and inspecting. Assist agency in obtaining samples.
4. Facilities for storage and field curing of test samples.
5. Delivery of samples to testing agencies.
6. Preliminary design mix proposed for use for material mixes that require control by testing agency.
7. Security and protection for samples and for testing and inspecting equipment at Project site.
G. Coordination: Coordinate sequence of activities to accommodate required quality-assurance and -control services with a minimum of delay and to avoid necessity of removing and replacing construction to accommodate testing and inspecting.
1. Schedule times for tests, inspections, obtaining samples, and similar activities.
QUALITY REQUIREMENTS 01 40 00 - 6
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 REPAIR AND PROTECTION
A. General: On completion of testing, inspecting, sample taking, and similar services, repair damaged construction and restore substrates and finishes.
1. Provide materials and comply with installation requirements specified in other Specification Sections. Restore patched areas and extend restoration into adjoining areas with durable seams that are as invisible as possible.
2. Comply with the Contract Document requirements for Division 01 Section "Cutting and Patching."
B. Protect construction exposed by or for quality-control service activities.
C. Repair and protection are Contractor's responsibility, regardless of the assignment of responsibility for quality-control services.
END OF SECTION 01 40 00
SECTION 01 60 00
MATERIAL AND HANDLING
SECTION 01 60 00
TABLE OF CONTENTS
PART 1 GENERAL
1.01 SITE CONDITION INSPECTION
1.02 PRODUCT DELIVERY, STORAGE, AND HANDLING
1.03 INSTALLATION REQUIREMENTS
1.04 MANUFACTURER’S NAMEPLATES
1.05 COLORS OF FACTORY-FINISHED EQUIPMENT
1.06 MATERIALS AND FINISHES
SECTION 01 60 00
MATERIAL AND HANDLING
MATERIAL AND HANDLING 016000 - 1
SECTION 01 60 00
MATERIAL AND HANDLING
PART 1 GENERAL
1.01 SITE CONDITION INSPECTION
A. Prior to beginning installation of equipment, examine hoistway and machine room areas. Verify no irregularities exist which affect execution of work specified.
B. Do not proceed with installation until work in place conforms to project requirements.
1.02 PRODUCT DELIVERY, STORAGE, AND HANDLING
A. Deliver material in Contractor’s original, unopened protective packaging.
B. Store material in original protective packaging. Prevent soiling, physical damage, or moisture damage.
C. Protect equipment and exposed finishes from damage and stains during transportation, erection, and construction.
D. Allocate available site storage areas and coordinate their use with Owner and other Contractors.
E. Provide suitable temporary weather-tight storage facilities as may be required for materials which will be stored in the open.
1.03 INSTALLATION REQUIREMENTS
A. Install all equipment in accordance with Contractor’s instructions, referenced codes, specification, and approved submittals.
B. Install machine room equipment with clearances in accordance with referenced codes and specification.
C. Install all equipment so it may be easily removed for maintenance and repair.
D. Install all equipment for ease of maintenance.
E. Install all equipment to afford maximum accessibility, safety, and continuity of operation.
F. Remove oil, grease, scale, and other foreign matter from the following equipment and apply one coat of field-applied machinery enamel.
SECTION 01 60 00
MATERIAL AND HANDLING
MATERIAL AND HANDLING 016000 - 2
1. All exposed equipment and metal work installed as part of this work which does not have architectural finish.
2. Machine room equipment, and pit equipment.
3. Hoistway equipment including guide rails, guide rail brackets, and pit equipment.
4. Neatly touch up damaged factory-painted surfaces with original paint color.
Protect machine-finish surfaces against corrosion.
1.04 MANUFACTURER’S NAMEPLATES
A. Manufacturer’s name plates and other identifying markings shall not be affixed on surfaces exposed to public view. This requirement does not apply to Underwriter’s Laboratories and code required labels.
B. Each major component of mechanical and electrical equipment shall have identification plate with the Manufacturer’s name, address, model number, rating, and any other information required by governing codes.
1.05 COLORS OF FACTORY-FINISHED EQUIPMENT
A. All colors will be selected from the Manufacturer’s standard range unless custom colors are specified herein.
B. Submit samples of all standard colors available and/or specified custom colors for review and approval. See Section 01300, Submittals
C. Submit samples of all specified architectural metals specified for review and approval. See Section 01300, Submittals.
1.06 MATERIALS AND FINISHES
A. Steel:
1. Sheet Steel (Furniture Steel for Exposed Work): Stretcher-leveled, cold-rolled, commercial quality carbon steel, complying with ASTM A366, matte finish.
2. Sheet Steel (for Unexposed Work): Hot-rolled, commercial quality carbon steel, pickled and oiled, complying with ASTM A568/A568M-03.
3. Structural Steel Shapes and Plates: ASTM A36.
B. Stainless Steel: Type 316 complying with ASTM A240, with standard tempers and hardness required for fabrication, strength and durability. Apply mechanical finish on fabricated work in the locations shown or specified, Federal Standard and NAAMM nomenclature, with texture and reflectivity required to match Architect’s sample. Protect with adhesive paper covering.
1. No. 4 Satin: Directional polish finish. Graining directions in vertical dimension.
SECTION 01 60 00
MATERIAL AND HANDLING
MATERIAL AND HANDLING 016000 - 3
C. Aluminum: Extrusions per ASTM B221; sheet and plate per ASTM B209.
D. Prime Finish: Clean all metal surfaces receiving a baked enamel paint finish of oil, grease, and scale. Apply one coat of rust-resistant primer followed by a filler coat over uneven surfaces. Sand smooth and apply final coat of primer.
SUBSTITUTIONS SECTION 016310 - 1
SECTION 016310 - SUBSTITUTIONS
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Specification Sections, apply to this Section. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1
1.2 SUMMARY
A. This Section includes administrative and procedural requirements for handling requests for substitutions.
B. Substitutions:
1. After the Award of Contract:
a. The Procurement Division will consider a request by the contractor for substitution where the specified product cannot receive necessary approval by a governing authority, and the requested substitution can be approved.
b. The Procurement Division will consider a request by the Contractor for a substitution after the award of the Contract where substantial advantage is offered to the Owner in terms of:
1) A credit is offered for substitution of a Product accepted as an approved equal to a specified item by the Architect.
2) A Product has been accepted by the Architect as being of greater quality at no additional cost to the Owner.
3) The Products specified, for no fault of the Contractor, cannot be obtained.
4) The Architect will consider a request for substitution when the specified Product cannot be provided in a manner which is compatible with other materials of the work.
5) The Architect will consider a request for substitution when the specified Product cannot be properly coordinated with other materials in the work
6) The Architect will consider a request for substitution when the specified Product cannot receive a warranty as required by the Contract Documents.
2. The Contractor, Subcontractor or Supplier who is recommending the Substitution shall compensate the Architect/Engineer for expenditures necessary in reviewing the proposed substitution. Prevailing hourly billing rates shall be used plus 20%.
1.3 DEFINITIONS
A. Definitions in this Article do not change or modify the meaning of other terms used in the Contract Documents.
SUBSTITUTIONS SECTION 016310 - 2
1. Products, are items purchased for incorporation in the Work, regardless of whether they were specifically purchased for the project or…