This file is a Site Logistics Plan for the Ealy Elementary School project, part of the WDS Bond Proposal Phase 1 in Michigan. The plan outlines construction logistics and site management for a boiler room demolition and roof replacement project at Ealy Elementary School. The project is scheduled to commence on April 2, 2027, with the last day of school occurring on June 4, 2027, and construction completion targeted for August 11, 2027. The plan designates specific areas for dumpster placement during the initial boiler room demolition and roof replacement phase, as well as additional dumpster locations during the summer break period. The document identifies portable toilet locations, establishes a defined construction access route, and designates contractor parking areas. The Clark Construction field office is located at the White Lake Community Center, 541 E. Slocum Street, Whitehall, Michigan 49461, serving as the project's administrative hub.

The Site Logistics Plan establishes operational procedures to minimize disruption to school activities by scheduling major construction activities during the summer break period when students are not present. The plan provides visual representation through a legend indicating dumpster locations, portable toilet facilities, construction access routes, and contractor parking zones. The document indicates coordination with the school calendar, ensuring that the initial demolition and roof replacement activities occur after the school year concludes, thereby reducing impact on daily educational operations. No specific pricing, funding sources, or set-aside information is contained within this logistics planning document.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TomBrennan Text Box Ealy Elementary Site Logistics Plan

TomBrennan Rectangle

TomBrennan PolyLine

TomBrennan Rectangle

TomBrennan Architect

DUMPSTER DURING INITIAL BOILER ROOM DEMOLITION AND ROOF REPLACEMENT

TomBrennan Architect

DUMPSTERS DURING SUMMER BREAK PERIOD

TomBrennan Text Box

LEGEND

DUMPSTERS

PORTABLE TOILETS

CONSTRUCTION ACCESS ROUTE

TomBrennan Rectangle

TomBrennan Switch

TomBrennan PolyLine

TomBrennan Polygon

TomBrennan Text Box

CONTRACTOR

PARKING

TomBrennan Text Box

CLARK CONSTRUCTION FIELD OFFICE

White Lake Community Center 541 E. Slocum St., Whitehall, MI 49461

TomBrennan Callout

CONSTRUCTION ENTRANCE/EXIT

TomBrennan Rectangle

TomBrennan Text Box

BOILER ROOM

(BASEMENT LEVEL)

TomBrennan Text Box

KEY DATES

Construction Start Date: 4/2/2027 Last Day of School: 6/4/2027 Construction End Date: 8/11/2027