About this file
This document is a Phase 1 Project Schedule for the Whitehall District Schools (WDS) Bond Proposal project in Michigan, involving construction and improvements at Ealy Middle School and Shoreline facilities. The schedule outlines the project timeline and key milestones for Phase 1 of the bond-funded initiative, detailing the sequencing of construction activities, procurement phases, and project delivery stages. The document establishes the framework for managing project execution across multiple school sites, with specific attention to scheduling dependencies and resource allocation necessary to meet overall project completion objectives within the bond proposal framework.
The schedule serves as an essential planning and coordination tool for contractors and subcontractors involved in the WDS Bond Proposal Phase 1 work, establishing baseline timelines against which actual project progress will be measured. The document defines critical path activities and milestone dates that drive procurement decisions, material ordering, labor allocation, and completion deadlines. This schedule is fundamental to the project management process and ensures all stakeholders maintain alignment on deliverable dates and sequencing requirements throughout Phase 1 execution.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ID Description Original
Duration Start Finish Responsible Party
Whitehall District Schools - Phase 1 420 01/16/26 09/09/27
Preconstruction 351 01/16/26 06/02/27
Design/Estimating 280 01/16/26 02/22/27
Owner Items / Construction Bid Package 65 09/21/26 12/22/26
Bid & Award 54 09/30/26 12/16/26
23 Finalize Bid Docs/Front End/Scopes 15 09/30/26 10/20/26 Clark/Pure
24 Bid Period 15 10/21/26 11/10/26 Clark
75 Pre-Bid Meeting 1 10/29/26 10/29/26 Clark
77 Pre-Bid RFIs Deadline 0 11/03/26 Clark
73 Bid Opening 1 11/11/26 11/11/26 Clark/Pure/WDS
26 Post Bid Interviews 7 11/12/26 11/20/26 Clark
28 Award Recommendations 5 11/23/26 12/01/26 Clark
29 WDS Board Approval (12/02/26 - 6:30PM) 1 12/02/26 12/02/26 WDS
35 Award Contracts 10 12/03/26 12/16/26 Clark/WDS
Procurement 117 12/17/26 06/02/27
36 Submittals 30 12/17/26 01/29/27 Clark
42 Material Procurement 50 02/01/27 04/09/27 Clark
322 Middle School Cafeteria Windows/Doors Leadtime 24 04/29/27 06/02/27 Clark
Construction 253 08/20/26 09/09/27
Key Milestones & Schedules 253 08/20/26 09/09/27
97 2026-27 School Year 201 08/20/26 06/04/27
565 Clark Project Office Setup 14 03/15/27 04/01/27
89 Kick-off / Pre-Construction Meeting 1 04/01/27 04/01/27
93 Spring Break 6 04/02/27 04/09/27
95 Summer Break 52 06/07/27 08/18/27
567 Substantial Completion 0 08/11/27
140 Owner Move-In 0 08/12/27
101 2027-28 School Year First Day 0 08/19/27
568 Final Completion 0 09/09/27
Whitehall Middle School 106 03/19/27 08/17/27
88 Asbestos Abatement 10-Day Notice 10 03/19/27 04/01/27 WDS
110 Mobilize (Signage; Temp Fencing; Dumpsters) 5 03/26/27 04/01/27 Clark
124 Asbestos Abatement & Clearance (General) 6 04/02/27 04/09/27 WDS
Cafeteria Wing Renovation 96 04/02/27 08/17/27
Cafeteria Boiler Room 96 04/02/27 08/17/27
135 MEP Cut/Cap/Make Safe 2 04/02/27 04/05/27 Trade Partner
141 Selective Demo (MEP, Materials, Equipment, etc.) 15 04/02/27 04/22/27 Trade Partner
142 Lead/Asbestos Abatement & Clearance 5 04/02/27 04/08/27 WDS
143 Temporary Power & Lighting 2 04/02/27 04/05/27 Trade Partner
147 Remove Windows & Temporary Infill 3 04/02/27 04/06/27 Trade Partner
145 RTU Structural Reinforcement 3 04/16/27 04/20/27 Trade Partner
150 Set Roof Curbs, Flash & Temporarily Cover 2 04/21/27 04/22/27 Trade Partner
223 Sawcut Floor & Concrete Removal 3 04/23/27 04/27/27 Trade Partner
228 Corridor Wall Opening & Structural Support 3 04/23/27 04/27/27 Trade Partner
227 Boiler Room Underslab Plumbing & Lift Station Rough-in 5 04/28/27 05/04/27 Trade Partner
144 Underslab Plumbing Inspection 1 05/05/27 05/05/27 Trade Partner
224 Block Wall Footings & Slab Infill (Including Cure Time) 5 05/06/27 05/12/27 Trade Partner
222 Interior Block Walls (Restroom Perimeter) 8 05/13/27 05/24/27 Trade Partner
312 Restroom Sanitary Plumbing Rough-in 5 05/13/27 05/19/27 Trade Partner
318 Restroom Sanitary Plumbing Inspection 1 05/20/27 05/20/27 Trade Partner
146 Exterior Block/Brick Infill & Trim 20 05/25/27 06/22/27 Trade Partner
220 Restroom Structural Geofoam Infill 5 05/25/27 06/01/27 Trade Partner
2026 2027 2028
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
P ro je ct
F in is h
Finalize Bid Docs/Front End/Scopes
Bid Period
Pre-Bid Meeting
Pre-Bid RFIs Deadline
Bid Opening
Post Bid Interviews
Award Recommendations
WDS Board Approval (12/02/26 - 6:30PM)
Award Contracts
Submittals
Material Procurement
Middle School Cafeteria Windows/Doors Leadtime
2026-27 School Year
Clark Project Office Setup
Kick-off / Pre-Construction Meeting
Spring Break
Summer Break
Substantial Completion
Owner Move-In
2027-28 School Year First Day
Final Completion
Asbestos Abatement 10-Day Notice
Mobilize (Signage; Temp Fencing; Dumpsters)
Asbestos Abatement & Clearance (General)
MEP Cut/Cap/Make Safe
Selective Demo (MEP, Materials, Equipment, etc.)
Lead/Asbestos Abatement & Clearance
Temporary Power & Lighting
Remove Windows & Temporary Infill
RTU Structural Reinforcement
Set Roof Curbs, Flash & Temporarily Cover
Sawcut Floor & Concrete Removal
Corridor Wall Opening & Structural Support
Boiler Room Underslab Plumbing & Lift Station Rough-in
Underslab Plumbing Inspection
Block Wall Footings & Slab Infill (Including Cure Time)
Interior Block Walls (Restroom Perimeter)
Restroom Sanitary Plumbing Rough-in
Restroom Sanitary Plumbing Inspection
Exterior Block/Brick Infill & Trim
Restroom Structural Geofoam Infill
Start Date: 11/26/25
Finish Date: 09/09/27
Data Date: 11/26/25
Run Date: 10/21/26
Whitehall District Schools 2025 Bond Project Schedule 20261012.ppx
Whitehall District Schools
2025 Bond Schedule - Phase 1 Page 1A
Duration Start Finish Responsible Party
221 Restroom Trench Drains Rough-in 5 05/25/27 06/01/27 Trade Partner
230 Restroom Slab Installation 5 06/02/27 06/08/27 Trade Partner
226 Restroom Interior Block Walls 5 06/09/27 06/15/27 Trade Partner
236 Overhead & In-Wall MEP Rough-in 10 06/09/27 06/22/27 Trade Partner
245 Set Door Frames 2 06/16/27 06/17/27 Trade Partner
247 Install Hot Water Heaters/Boilers 5 06/23/27 06/29/27 Trade Partner
250 Above Ceiling & In-Wall MEP Rough Inspection 1 06/23/27 06/23/27 Trade Partner
234 Ceiling Framing 3 06/24/27 06/28/27 Trade Partner
239 Drywall Install & Finish 6 06/29/27 07/07/27 Trade Partner
313 Prime/First Coat Paint 3 07/08/27 07/12/27 Trade Partner
308 Tile Flooring & Walls 10 07/13/27 07/26/27 Trade Partner
311 MEP Final Fixtures/Trim 6 07/27/27 08/03/27 Trade Partner
314 Final Paint 4 07/27/27 07/30/27 Trade Partner
310 Install Restroom Accessories and Partitions 4 08/02/27 08/05/27 Trade Partner
315 MEP Commissioning 10 08/04/27 08/17/27 Trade Partner
316 Hang Doors & Hardware 1 08/05/27 08/05/27 Trade Partner
317 Final Inspections 5 08/06/27 08/12/27 Clark
Cafeteria/Kitchen 93 04/02/27 08/12/27
288 Furnishings, Stored Food, Kitchen Equipment Removal 4 04/02/27 04/07/27 WDS
289 Asbestos Abatement & Clearance 4 04/02/27 04/07/27 WDS
291 Walk-in Freezer Temporary Protection 2 04/06/27 04/07/27 Trade Partner
292 MEP Cut/Cap/Make Safe 2 04/06/27 04/07/27 Trade Partner
293 Electrical Room Switchgear Removal/Replacement 40 04/08/27 06/03/27 Trade Partner
294 Temporary Power/Lighting 3 04/08/27 04/12/27 Trade Partner
296 Selective Demo: Walls, Ceilings, Flooring, MEP 15 04/08/27 04/28/27 Trade Partner
301 Remove Windows & Temporary Infill 10 04/15/27 04/28/27 Trade Partner
303 Asbestos Abatement: Kitchen Pipe Utility Tunnel 10 04/15/27 04/28/27 WDS
306 Selective Demo: South Exterior Door Openings 5 04/22/27 04/28/27 Trade Partner
325 Exterior Wall Block/Brick Infill 20 04/22/27 05/19/27 Trade Partner
321 MEP Overhead Rough-in 15 04/29/27 05/19/27 Trade Partner
365 Underslab MEP: Plumbing & Electrical Rough-in 15 04/29/27 05/19/27 Trade Partner
298 Attic Ductwork Rough-in and Drops 15 04/30/27 05/20/27 Trade Partner
370 Replace Exterior Grease Interceptor 10 05/06/27 05/19/27 Trade Partner
324 Kitchen Hood Installation/Exhaust Fan 5 05/20/27 05/26/27 Trade Partner
326 Cafeteria Feature Ceiling Bulkhead Framing 5 05/20/27 05/26/27 Trade Partner
330 MEP Overhead Rough Inspection 1 05/20/27 05/20/27 Trade Partner
366 Below Slab Inspection 1 05/20/27 05/20/27 Trade Partner
331 RTU Installation/Hook-up 5 05/21/27 05/27/27 Trade Partner
367 Infill Slab Openings 3 05/21/27 05/25/27 Trade Partner
323 Interior Stud Wall Layout/Framing 10 05/26/27 06/09/27 Trade Partner
327 Install Exterior Windows 10 06/03/27 06/16/27 Trade Partner
329 MEP In-wall Rough-in 10 06/03/27 06/16/27 Trade Partner
333 Hang Drywall & Finish 10 06/10/27 06/23/27 Trade Partner
335 Hang Door Frames 5 06/10/27 06/16/27 Trade Partner
328 Overhead Door Installation 5 06/17/27 06/23/27 Trade Partner
332 MEP In-wall Inspection 1 06/17/27 06/17/27 Trade Partner
334 Prime/First-Coat Paint 5 06/24/27 06/30/27 Trade Partner
336 FRP Wall Panels & Decorative Columns 5 07/01/27 07/08/27 Trade Partner
337 Ceiling Grid 10 07/01/27 07/15/27 Trade Partner
344 Interior Storefront Glass & Doors 5 07/01/27 07/08/27 Trade Partner
341 Kitchen Tile Flooring 10 07/09/27 07/22/27 Trade Partner
342 Cafeteria Feature Ceiling Finishes 5 07/09/27 07/15/27 Trade Partner
338 Ceiling Mechanical, Lighting, Low Volt Fixtures 10 07/16/27 07/29/27 Trade Partner
343 Cafeteria/Corridor Flooring 10 07/16/27 07/29/27 Trade Partner
361 Install South Exterior Doors 5 07/16/27 07/22/27 Trade Partner
339 Ceiling Pads 5 07/23/27 07/29/27 Trade Partner
2026 2027 2028
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
P ro je ct
F in is h
Restroom Trench Drains Rough-in
Restroom Slab Installation
Restroom Interior Block Walls
Overhead & In-Wall MEP Rough-in
Set Door Frames
Install Hot Water Heaters/Boilers
Above Ceiling & In-Wall MEP Rough Inspection
Ceiling Framing
Drywall Install & Finish
Prime/First Coat Paint
Tile Flooring & Walls
MEP Final Fixtures/Trim
Final Paint
Install Restroom Accessories and Partitions
MEP Commissioning
Hang Doors & Hardware
Final Inspections
Furnishings, Stored Food, Kitchen Equipment Removal
Asbestos Abatement & Clearance
Walk-in Freezer Temporary Protection
MEP Cut/Cap/Make Safe
Electrical Room Switchgear Removal/Replacement
Temporary Power/Lighting
Selective Demo: Walls, Ceilings, Flooring, MEP
Remove Windows & Temporary Infill
Asbestos Abatement: Kitchen Pipe Utility Tunnel
Selective Demo: South Exterior Door Openings
Exterior Wall Block/Brick Infill
MEP Overhead Rough-in
Underslab MEP: Plumbing & Electrical Rough-in
Attic Ductwork Rough-in and Drops
Replace Exterior Grease Interceptor
Kitchen Hood Installation/Exhaust Fan
Cafeteria Feature Ceiling Bulkhead Framing
MEP Overhead Rough Inspection
Below Slab Inspection
RTU Installation/Hook-up
Infill Slab Openings
Interior Stud Wall Layout/Framing
Install Exterior Windows
MEP In-wall Rough-in
Hang Drywall & Finish
Hang Door Frames
Overhead Door Installation
MEP In-wall Inspection
Prime/First-Coat Paint
FRP Wall Panels & Decorative Columns
Ceiling Grid
Interior Storefront Glass & Doors
Kitchen Tile Flooring
Cafeteria Feature Ceiling Finishes
Ceiling Mechanical, Lighting, Low Volt Fixtures
Cafeteria/Corridor Flooring
Install South Exterior Doors
Ceiling Pads
Start Date: 11/26/25
Finish Date: 09/09/27
Data Date: 11/26/25
Run Date: 10/21/26
Whitehall District Schools 2025 Bond Project Schedule 20261012.ppx
Whitehall District Schools
Page 2A
Duration Start Finish Responsible Party
346 Final Paint 5 07/23/27 07/29/27 Trade Partner
340 MEP Commissioning 10 07/30/27 08/12/27 Trade Partner
347 Final MEP Inspections 3 07/30/27 08/03/27 Trade Partner
354 Hang Doors & Hardware 2 07/30/27 08/02/27 Trade Partner
359 Final Cleaning 2 07/30/27 08/02/27 Trade Partner
353 Kitchen Equipment Installation/Hook-up 5 08/03/27 08/09/27 WDS
357 Cafeteria Furnishings 5 08/03/27 08/09/27 WDS
369 Final Building/BFS Inspections 5 08/03/27 08/09/27 Clark
358 Health Department Licensing Inspection 1 08/10/27 08/10/27 WDS/Clark
356 Owner Move-In 0 08/10/27 WDS
Cafeteria Courtyard/Exterior 39 06/07/27 07/30/27
345 Remove Trees & Stumps 3 06/07/27 06/09/27 Trade Partner
349 Excavate For Patio 5 06/10/27 06/16/27 Trade Partner
350 Remove North Sidewalk & Concrete Stub Walls 5 06/17/27 06/23/27 Trade Partner
351 Patio Grading & Subgrade 5 06/17/27 06/23/27 Trade Partner
352 Patio Concrete & Planter Boxes 15 06/24/27 07/15/27 Trade Partner
355 Regrading & Asphalt Repairs 5 07/16/27 07/22/27 Trade Partner
360 Gutters & Downspouts 5 07/16/27 07/22/27 Trade Partner
362 Final Grading, Topsoil, & Grass Seeding 5 07/23/27 07/29/27 Trade Partner
363 Planter Box Landscaping 5 07/23/27 07/29/27 Trade Partner
364 Mulch Refresh 1 07/30/27 07/30/27 Trade Partner
368 Patio Furnishings 1 07/30/27 07/30/27 Trade Partner
Media Center Renovation 31 06/07/27 07/20/27
410 Remove Furnishings & Materials 5 06/07/27 06/11/27 WDS
415 Temporary Protection 3 06/14/27 06/16/27 Trade Partner
420 Selective Interior Demolition (salvage ceiling pads) 3 06/17/27 06/21/27 Trade Partner
430 Paint Bulkheads and Ceiling Grid 5 06/22/27 06/28/27 Trade Partner
440 Lighting and HVAC Diffusers 5 06/29/27 07/06/27 Trade Partner
450 Reface Main Desk and Install Countertops 10 06/29/27 07/13/27 Trade Partner
460 Paint Walls 3 06/29/27 07/01/27 Trade Partner
465 Install Ceiling Tiles & Fixtures 3 07/07/27 07/09/27 Trade Partner
470 Install New Carpet Tile/Base 5 07/12/27 07/16/27 Trade Partner
475 Final Cleaning 1 07/19/27 07/19/27 Trade Partner
480 Reinstall Furnishings 1 07/20/27 07/20/27 WDS
MEP Infrastructure Improvements 90 04/02/27 08/09/27
508 School Boiler Room MEP Cut/Cap/Make Safe 3 04/02/27 04/06/27 Trade Partner
515 Remove & Salvage Exterior Window & Temporary Infill 3 04/02/27 04/06/27 Trade Partner
507 School Boiler Room Selective Demolition 15 04/07/27 04/27/27 Trade Partner
540 Boilers/Pumps Installation 25 04/28/27 06/02/27 Trade Partner
550 Electrical Switchgear/Panel Replacements 35 06/07/27 07/26/27 Trade Partner
558 Temporary Floor Protection (Classrooms & Corridors) 5 06/07/27 06/11/27 Trade Partner
500 Selective Ceiling Demolition 10 06/08/27 06/21/27 Trade Partner
505 Install Pipe Runs, Line Sets, Electrical Conduit 20 06/10/27 07/08/27 Trade Partner
509 Existing HVAC Equipment Demolition 20 06/14/27 07/12/27 Trade Partner
520 Framed Pipe Chases (Classrooms) 20 06/17/27 07/15/27 Trade Partner
530 Pipe Insulation / Metal Enclosures 20 06/17/27 07/15/27 Trade Partner
510 HVAC Equipment Installation 20 06/28/27 07/26/27 Trade Partner
555 Above Ceiling Inspections 1 07/09/27 07/09/27 Trade Partner
557 Reinstall Ceilings 10 07/12/27 07/23/27 Trade Partner
560 Final Cleaning 5 07/26/27 07/30/27 Trade Partner
511 Final MEP Inspections 5 07/27/27 08/02/27 Trade Partner
512 Test & Balance Mechanical 5 07/27/27 08/02/27 Trade Partner
545 Reinstall Permanent Window 3 07/27/27 07/29/27 Trade Partner
559 Commissioning 5 08/03/27 08/09/27 Trade Partner
Roof Replacements 80 04/09/27 08/02/27
2026 2027 2028
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
P ro je ct
F in is h
Final Paint
MEP Commissioning
Final MEP Inspections
Hang Doors & Hardware
Final Cleaning
Kitchen Equipment Installation/Hook-up
Cafeteria Furnishings
Final Building/BFS Inspections
Health Department Licensing Inspection
Owner Move-In
Remove Trees & Stumps
Excavate For Patio
Remove North Sidewalk & Concrete Stub Walls
Patio Grading & Subgrade
Patio Concrete & Planter Boxes
Regrading & Asphalt Repairs
Gutters & Downspouts
Final Grading, Topsoil, & Grass Seeding
Planter Box Landscaping
Mulch Refresh
Patio Furnishings
Remove Furnishings & Materials
Temporary Protection
Selective Interior Demolition (salvage ceiling pads)
Paint Bulkheads and Ceiling Grid
Lighting and HVAC Diffusers
Reface Main Desk and Install Countertops
Paint Walls
Install Ceiling Tiles & Fixtures
Install New Carpet Tile/Base
Final Cleaning
Reinstall Furnishings
School Boiler Room MEP Cut/Cap/Make Safe
Remove & Salvage Exterior Window & Temporary Infill
School Boiler Room Selective Demolition
Boilers/Pumps Installation
Electrical Switchgear/Panel Replacements
Temporary Floor Protection (Classrooms & Corridors)
Selective Ceiling Demolition
Install Pipe Runs, Line Sets, Electrical Conduit
Existing HVAC Equipment Demolition
Framed Pipe Chases (Classrooms)
Pipe Insulation / Metal Enclosures
HVAC Equipment Installation
Above Ceiling Inspections
Reinstall Ceilings
Final Cleaning
Final MEP Inspections
Test & Balance Mechanical
Reinstall Permanent Window
Commissioning
Start Date: 11/26/25
Finish Date: 09/09/27
Data Date: 11/26/25
Run Date: 10/21/26
Whitehall District Schools 2025 Bond Project Schedule 20261012.ppx
Whitehall District Schools
Page 3A
Duration Start Finish Responsible Party
Roof Section 18 20 04/09/27 05/06/27
139 Roof Replacement & Deck Infill 15 04/09/27 04/29/27 Trade Partner
148 Roof Installation 15 04/16/27 05/06/27
149 Roofing Details/Flashings/Venting/Accessories 10 04/23/27 05/06/27
Roof Section 17 40 06/07/27 08/02/27
562 Roof Tear-Off 35 06/07/27 07/26/27 Trade Partner
563 Roof Installation 35 06/14/27 08/02/27 Trade Partner
564 Roofing Details/Flashings/Venting/Accessories 20 07/06/27 08/02/27 Trade Partner
Ealy Elementary 90 04/02/27 08/09/27
120 Asbestos Abatement & Clearance 6 04/02/27 04/09/27 WDS
Media Center Renovation 31 06/07/27 07/20/27
600 Remove Furnishings & Materials 5 06/07/27 06/11/27 WDS
605 Temporary Protection 3 06/14/27 06/16/27 Trade Partner
610 Selective Interior Demolition (salvage ceiling pads) 3 06/17/27 06/21/27 Trade Partner
620 Paint Bulkheads and Ceiling Grid 5 06/22/27 06/28/27 Trade Partner
630 Lighting and HVAC Diffusers 5 06/29/27 07/06/27 Trade Partner
640 Reface Main Desk and Install Countertops 10 06/29/27 07/13/27 Trade Partner
650 Paint Walls 3 06/29/27 07/01/27 Trade Partner
660 Install Ceiling Tiles & Fixtures 3 07/07/27 07/09/27 Trade Partner
670 Install New Carpet Tile/Base 5 07/12/27 07/16/27 Trade Partner
675 Final Cleaning 1 07/19/27 07/19/27 Trade Partner
680 Reinstall Furnishings 1 07/20/27 07/20/27 WDS
MEP Infrastructure Improvements 90 04/02/27 08/09/27
690 School Boiler Room MEP Cut/Cap/Make Safe 3 04/02/27 04/06/27 Trade Partner
850 School Boiler Room Selective Demolition 15 04/07/27 04/27/27 Trade Partner
860 Boilers/Pumps Installation 25 04/28/27 06/02/27 Trade Partner
870 Electrical Switchgear/Panel Replacements 35 06/07/27 07/26/27 Trade Partner
880 Temporary Floor Protection (Classrooms & Corridors) 5 06/07/27 06/11/27 Trade Partner
890 Selective Ceiling Demolition 10 06/08/27 06/21/27 Trade Partner
900 Install Pipe Runs, Line Sets, Electrical Conduit 20 06/10/27 07/08/27 Trade Partner
910 Existing HVAC Equipment Demolition 20 06/14/27 07/12/27 Trade Partner
920 Framed Pipe Chases (Classrooms) 20 06/17/27 07/15/27 Trade Partner
930 Pipe Insulation / Metal Enclosures 20 06/17/27 07/15/27 Trade Partner
940 HVAC Equipment Installation 20 06/28/27 07/26/27 Trade Partner
950 Above Ceiling Inspections 1 07/09/27 07/09/27 Trade Partner
960 Reinstall Ceilings 10 07/12/27 07/23/27 Trade Partner
970 Final Cleaning 5 07/26/27 07/30/27 Trade Partner
990 Final MEP Inspections 5 07/27/27 08/02/27 Trade Partner
1000 Test & Balance Mechanical 5 07/27/27 08/02/27 Trade Partner
1010 Commissioning 5 08/03/27 08/09/27 Trade Partner
Roof Replacements 77 04/07/27 07/26/27
Roof Section 22 20 04/07/27 05/04/27
855 Roof Tear-Off 15 04/07/27 04/27/27
573 Roof Installation 15 04/14/27 05/04/27
572 Roofing Details/Flashings/Venting/Accessories 10 04/21/27 05/04/27
Roof Section 1 35 06/07/27 07/26/27
570 Roof Tear-Off 30 06/07/27 07/19/27 Trade Partner
580 Roof Installation 30 06/14/27 07/26/27 Trade Partner
590 Roofing Details/Flashings/Venting/Accessories 15 07/06/27 07/26/27 Trade Partner
Shoreline Elementary 43 06/07/27 08/05/27
Bus Loop Improvements 43 06/07/27 08/05/27
70 Remove Asphalt/Concrete 5 06/07/27 06/11/27
2026 2027 2028
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
P ro je ct
F in is h
Roof Replacement & Deck Infill
Roof Installation
Roofing Details/Flashings/Venting/Accessories
Roof Tear-Off
Roof Installation
Roofing Details/Flashings/Venting/Accessories
Asbestos Abatement & Clearance
Remove Furnishings & Materials
Temporary Protection
Selective Interior Demolition (salvage ceiling pads)
Paint Bulkheads and Ceiling Grid
Lighting and HVAC Diffusers
Reface Main Desk and Install Countertops
Paint Walls
Install Ceiling Tiles & Fixtures
Install New Carpet Tile/Base
Final Cleaning
Reinstall Furnishings
School Boiler Room MEP Cut/Cap/Make Safe
School Boiler Room Selective Demolition
Boilers/Pumps Installation
Electrical Switchgear/Panel Replacements
Temporary Floor Protection (Classrooms & Corridors)
Selective Ceiling Demolition
Install Pipe Runs, Line Sets, Electrical Conduit
Existing HVAC Equipment Demolition
Framed Pipe Chases (Classrooms)
Pipe Insulation / Metal Enclosures
HVAC Equipment Installation
Above Ceiling Inspections
Reinstall Ceilings
Final Cleaning
Final MEP Inspections
Test & Balance Mechanical
Commissioning
Roof Tear-Off
Roof Installation
Roofing Details/Flashings/Venting/Accessories
Roof Tear-Off
Roof Installation
Roofing Details/Flashings/Venting/Accessories
Remove Asphalt/Concrete
Start Date: 11/26/25
Finish Date: 09/09/27
Data Date: 11/26/25
Run Date: 10/21/26
Whitehall District Schools 2025 Bond Project Schedule 20261012.ppx
Whitehall District Schools
Page 4A
Duration Start Finish Responsible Party
90 Clear and Grub at New Parking Lot Entry 10 06/07/27 06/18/27
92 Sawcut, Excavate, Grading, & Subgrade 10 06/21/27 07/02/27
94 Concrete Curbs & Sidewalks 10 06/30/27 07/14/27
103 Fine Grading 2 07/15/27 07/16/27
96 Base Course Asphalt 2 07/19/27 07/20/27
99 Top Course Asphalt 2 07/21/27 07/22/27
100 Landscaping, Bollards & Signage 10 07/23/27 08/05/27
105 Pavement Markings 1 07/23/27 07/23/27
Closeout 20 08/12/27 09/09/27
569 Punchlist 15 08/12/27 09/01/27
575 Closeout Documentation 20 08/12/27 09/09/27
2026 2027 2028
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
P ro je ct
F in is h
Clear and Grub at New Parking Lot Entry
Sawcut, Excavate, Grading, & Subgrade
Concrete Curbs & Sidewalks
Fine Grading
Base Course Asphalt
Top Course Asphalt
Landscaping, Bollards & Signage
Pavement Markings
Punchlist
Closeout Documentation
Start Date: 11/26/25
Finish Date: 09/09/27
Data Date: 11/26/25
Run Date: 10/21/26
Whitehall District Schools 2025 Bond Project Schedule 20261012.ppx
Whitehall District Schools
Page 5A
File details come from the government source that posted it. Updated .