ATTACHMENT 2 SPECIFICATIONS (pdf)

View the file

Other files

File Type Posted
ATTACHMENT 7 CONTRACTOR'S RELEASE.doc DOC document
Attachment 27 - 232500 fl - HVAC water treatment.pdf PDF
ATTACHMENT 6 SF25A.doc DOC document
SIR/RFO DTFAAC-17-R-00023.pdf PDF
Attachment 22 - Title Sheet.pdf PDF
ATTACHMENT 8 OPERATIONAL CONTROL DOCUMENTS.pdf PDF
Attachment 18 - M4-01 - Hangar 8 Details & Schedules.pdf PDF
Attachment 13 - Addendum 2.pdf PDF
ATTACHMENT 9 DBA WAGE DETERMINATION.pdf PDF
Attachment 20 - Section 237313 - Central Station Air Handling Units.pdf PDF
Attachment 28 - 236514.13 fl - open-circuit, induced-draft, counterflow cooling towers.pdf PDF
Pre-Proposal Conference Sign-In Sheet.pdf PDF
ATTACHMENT 3 DRAWINGS.pdf PDF
ATTACHMENT 4 CHAPTER 33.pdf PDF
Amendment 0001.pdf PDF
Attachment 17 - M2-01 - Hangar 9 Site Plan and First Floor Plan.pdf PDF
ATTACHMENT 12 CLIENT AUTHORIZATION LETTER.docx DOCX document
ATTACHMENT 10 PAST PERFORMANCE EXPERIENCE FORM.pdf PDF
Amendment 000002.pdf PDF
Attachment 23 - Addendum 3.pdf PDF
Attachment 30 - Hangar 9 M Addendum 3.pdf PDF
Attachment 29 - Hangar 9 E Addendum 3.pdf PDF
ATTACHMENT 5 SF25.pdf PDF
ATTACHMENT 2 SPECIFICATIONS.pdf PDF
Attachment 15 - Hangar 8 E Addendum 2.pdf PDF
Attachment 19 - Section 232113-Hydronic Piping.pdf PDF
Amendment 0003.pdf PDF
Attachment 21 - Section 237416.13-Packaged, Large-Capacity, Rooftop Air-Conditioning Units.pdf PDF
Amendment 0004.pdf PDF
Attachment 26 - 232123 FL Hydronic Pumps.pdf PDF
Attachment 14 - 16-044 Addendum #2.pdf PDF
Attachment 16 - Hangar 9 E Addendum 2.pdf PDF
ATTACHMENT 1 SECTION B SUPPLIES OR SERVICES-PRICES.xlsx XLSX spreadsheet
Attachment 24 - 16-044 Addendum #3.pdf PDF
Attachment 25 - 230719 fl - hvac piping insulation.pdf PDF
ATTACHMENT 11 PAST PERFORMANCE SURVEY.pdf PDF
Attachment 13 - Addendum 2.pdf PDF
Attachment 22 - Title Sheet.pdf PDF
ATTACHMENT 6 SF25A.doc DOC document
ATTACHMENT 12 CLIENT AUTHORIZATION LETTER.docx DOCX document
ATTACHMENT 9 DBA WAGE DETERMINATION.pdf PDF
Attachment 25 - 230719 fl - hvac piping insulation.pdf PDF
Attachment 19 - Section 232113-Hydronic Piping.pdf PDF
Attachment 29 - Hangar 9 E Addendum 3.pdf PDF
Attachment 24 - 16-044 Addendum #3.pdf PDF
Attachment 26 - 232123 FL Hydronic Pumps.pdf PDF
ATTACHMENT 5 SF25.pdf PDF
ATTACHMENT 3 DRAWINGS.pdf PDF
Attachment 30 - Hangar 9 M Addendum 3.pdf PDF
ATTACHMENT 8 OPERATIONAL CONTROL DOCUMENTS.pdf PDF
Show 40 more

Latest 50 of 174 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

jsemtner Snapshot

16.31.001 / FAA Hangar 8 & 9 HVAC Renovations

00.01.07 - 1 SEAL AND SIGNATURE PAGE

SEAL AND SIGNATURE PAGE

ARCHITECT

(Sections denoted in the Table of Contents with the designation ARCH after the section name are prepared by the Architect)

The Small Group 108 South Broadway Edmond, OK 73034 Phone 405.840.1111

Contact:

Thomas Small, AIA

ARCHITECT

STRUCTURAL ENGINEER

(Sections denoted in the Table of Contents with the designation STRUCT after the section name are prepared by the Structural Engineer)

Kirpatrick Forest Curtis, PC 205 NW 63rd St. Suite 390 Oklahoma City, OK 73116 Phone 405.528.4596 Fax 405.528.4580

Contact:

Brian Rayner, P.E.

STRUCTURAL

MECH/PLUMBING ENGINEER

(Sections denoted in the Table of Contents with the designation MECH/PLUM after the section name are prepared by the Mechanical/Plumbing Engineer)

ADG, PC

920 West Main

OKC, OK 73106

Phone 405.223.5700

Contact:

John Semtner, P.E.

MECH/PLUMBING

ELECTRICAL ENGINEER

00.01.07 - 2 SEAL AND SIGNATURE PAGE

(Sections denoted in the Table of Contents with the designation ELECT after the section name are prepared by the Electrical Engineer)

ADG, PC

920 West Main

OKC, OK 73106

Phone 405.232.5700

Contact:

Mark Nickel, P.E.

ELECTRICAL

00.01.10 - 1 TABLE OF CONTENTS

SECTION 00.01.10

TABLE OF CONTENTS

PROCUREMENT AND CONTRACTING REQUIREMENTS

DIVISION 00 -- PROCUREMENT AND CONTRACTING REQUIREMENTS

00.01.07 - Seal and Signature Page

00.01.10 - Table of Contents

SPECIFICATIONS

DIVISION 01 -- GENERAL REQUIREMENTS

01.10.00 - Summary (ARCH)

01.30.00 - Administrative Requirements (ARCH)

01.40.00 - Quality Requirements (ARCH)

01.50.00 - Temporary Facilities and Controls (ARCH)

01.60.00 - Product Requirements (ARCH)

01.70.00 - Execution and Closeout Requirements (ARCH)

01.74.19 - Construction Waste Management and Disposal (ARCH)

01.78.00 - Closeout Submittals (ARCH)

01.79.00 - Demonstration and Training (ARCH)

DIVISION 02 -- EXISTING CONDITIONS

02.41.00 - Demolition (ARCH)

DIVISION 03 -- CONCRETE

03.30.00 - Cast-in-Place Concrete (STRUCT)

DIVISION 05 -- METALS

05.12.00 - Structural Steel Framing (STRUCT)

05.50.01 - Metal Ladder Fabrications (Arch)

DIVISION 07 -- THERMAL AND MOISTURE PROTECTION

07.54.00 - Thermoplastic Membrane Roofing (ARCH)

07.84.00 - Firestopping (ARCH)

DIVISION 23 -- HEATING, VENTILATING, AND AIR-CONDITIONING (HVAC)

23.05.13 - Common Motor Requirements for HVAC Equipment (MECH/PLUMB)

23.05.18 - Escutcheons for HVAC Piping

23.05.19 - Meters and Gages for HVAC Piping (MECH/PLUMB)

23.05.23.12 - Ball Valves for HVAC Piping (MECH/PLUMB)

23.05.23.13 - Butterfly Valves for HVAC Piping (MECH/PLUMB)

23.05.23.14 - Check Valves for HVAC Piping (MECH/PLUMB)

23.05.29 - Hangers and Supports for HVAC Piping (MECH/PLUMB)

23.05.53 - Identification for HVAC Piping and Equipment

23.05.93 - Testing, Adjusting, and Balancing for HVAC (MECH/PLUMB)

23.07.16 - HVAC Equipment Insulation (MECH/PLUMB)

23.07.19 - HVAC Piping Insulation (MECH/PLUMB)

23.09.13 - Instrumentation and Control Devices for HVAC (MECH/PLUMB)

23.09.23 - Direct-Digital Control System for HVAC (MECH/PLUMB)

23.21.13 - Hydronic Piping (MECH/PLUMB)

00.01.10 - 2 TABLE OF CONTENTS

23.21.16 - Hydronic Piping Specialties (MECH/PLUMB)

23.21.23 - Hydronic Pumps (MECH/PLUMB)

23.65.14.13 - Open-Circuit, Induced-Draft, Counterflow Cooling Towers (MECH/PLUMB)

23.73.13 - Modular Indoor Central-Station Air-Handling Units (MECH/PLUMB)

23.74.16.13 - Packaged, Large-Capacity, Rooftop Air-conditioning Units (MECH/PLUMB)

DIVISION 26 -- ELECTRICAL

26.05.19 - Low-Voltage Electrical Power Conductors and Cables (ELECT)

26.05.23 - Control-Voltage Electrical Power Cables (ELECT)

26.05.26 - Grounding and Bonding for Electrical Systems (ELECT)

26.05.29 - Hangers and Supports for Electrical Systems (ELECT)

26.05.33 - Raceways and Boxes for Electrical Systems (ELECT)

26.05.44 - Sleeves and Sleeve Seals for Electrical Raceways and Cabling (ELECT)

26.05.53 - Identification for Electrical Systems (ELECT)

26.24.16 - Panelboards (ELECT)

26.28.13 - Fuses (ELECT)

26.28.16 - Enclosed Switches and Circuit Breakers (ELECT)

26.29.13.03 - Manual and Magnetic Motor Controllers (ELECT)

26.29.23 - Variable-Frequency Motor Controllers (ELECT)

END OF SECTION

01.10.00 - 1 SUMMARY

SECTION 01.10.00

SUMMARY

PART 1 GENERAL

1.01 PROJECT

A. Project Name: FAA Hangar 8 & 9 HVAC Renovations B. Owner's Name: FAA.

C. Architect's Name: Small Architects.

D. Mechanical/Electrical Engineer's Name: ADG, PC.

E. Structural Engineer's Name: Kilpatrick Forest Curtis, PC

1.02 CONTRACT DESCRIPTION

A. Contract Type: A single prime contract based on a Stipulated Price as described in Document

00.52.00 - Agreement Form.

1.03 WORK DESCRIPTION

A. Work Location: Federal Aviation Administration Mike Monrony Aeronautical Center Hangars 8 and 9.

B. Project Schedule Requirements:

1. Refer to the SIR for the number of days allowed to complete all required work.

2. Bid Option 1 – Areas served by air handling units 1 through 5 (AHU-1 thru 5) cannot be without conditioned supply air at any time during normal business hours.

C. Work includes: All labor, materials, and equipment neccessary for the following packages.

Refer to section 01.70.00 3.05B for bird net removal and reinstallation after high bay work.

1. Base Bid – Hangar 9: Replace the existing cooling tower on the roof with a new two-cell, cooling tower. During the replacement temporary air cooled chillers must be provided to maintain proper building cooling.

2. Bid Option 1 – Hangar 8: Replace four existing air handling units (AHU) with new units on the roof and replacement of one existing AHU with a new unit located in a first floor mechanical room of Hangar 8.

D. Plumbing: Alter existing system.

E. HVAC: Replace existing system with new construction.

F. Electrical Power and Lighting: Alter existing and add new construction.

G. Fire Alarm: Alter existing system and add new construction, keeping existing in operation.

1.04 OWNER OCCUPANCY

A. Owner intends to continue to occupy portions of the existing building during the entire construction period. The Contractor is responsible to make sure each day's work is completely weather-tight at the close of the work day.

B. Cooperate with Owner to minimize conflict and to facilitate Owner's operations.

C. Work Sequence: Contractor shall submit a detailed construction phasing schedule describing when each phase of constrution is scheduled.

D. Suggested phasing plans are indicated on the drawings.

E. During construction of the infared heaters and the boiler replacement will be phased into 3 areas: North, SE, and SW. Refer to the mechanical plans for phasing information.

1.05 CONTRACTOR USE OF SITE AND PREMISES

A. Provide access to and from site as required by law and by Owner:

1. Emergency Building Exits During Construction: Keep all exits required by code open during construction period; provide temporary exit signs if exit routes are temporarily altered.

2. Do not obstruct roadways, sidewalks, or other public ways without permit.

01.10.00 - 2 SUMMARY

B. Safety Requirements: Contractor shall comply with the Safety FAA/MMAC standards. A copy of this report will be attached to the contract sent by the Contracting Officer.

C. Security Requirements: Contractor shall comply with all applicable Department of Transportation (DOT), FAA, and MMAC security directives while performing Work of this Contract.

D. Time Restrictions: Work shall be conducted between 7:00 a.m. and 4:30 p.m. on normal government work days. No Work shall occur at night, or on Saturday's, Sundays, or designated government holidays unless approved by the Contracting Officer seven (7) days in advance.

E. Existing building spaces may not be used for storage.

F. Utility Outages and Shutdown: Coordinate with the Contracting Office and Project Manager at

954-4574. Outages affecting FAA Operations are required to be accomplished at night, or on Saturday's, Sunday's, or designated government holidays. Prior to any outage or shutdown, fourteen (14) working days notification must be made to coordinate scheduling of any Work to be performed during any hours.

1. Prevent accidental disruption of utility services to other facilities.

G. The FAA project Manager's phone number is 405-954-4765.

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION - NOT USED

01.30.00 - 1 ADMINISTRATIVE

REQUIREMENTS

SECTION 01.30.00

ADMINISTRATIVE REQUIREMENTS

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Preconstruction meeting.

B. Progress meetings.

C. Construction progress schedule.

D. Submittals for review, information, and project closeout.

E. Number of copies of submittals.

F. Submittal procedures.

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION

3.01 PRECONSTRUCTION MEETING

A. Owner will schedule a meeting after Notice of Award.

B. Attendance Required:

1. Owner.

2. Architect.

3. Contractor.

C. Agenda:

1. Distribution of Contract Documents.

2. Submission of list of Subcontractors, list of Products, schedule of values, and progress schedule.

3. Designation of personnel representing the parties to Contract, Owner and Architect.

4. Procedures and processing of field decisions, submittals, substitutions, applications for payments, proposal request, Change Orders, and Contract closeout procedures.

5. Scheduling.

D. Record minutes and distribute copies within two days after meeting to participants, with copies to Architect, Owner, participants, and those affected by decisions made.

3.02 PROGRESS MEETINGS

A. Schedule and administer meetings throughout progress of the Work at maximum bi-monthly intervals.

B. Make arrangements for meetings, prepare agenda with copies for participants, preside at meetings.

C. Attendance Required:

1. Contractor.

2. Owner.

3. Architect.

4. Contractor's Superintendent.

5. Major Subcontractors.

D. Agenda:

1. Review minutes of previous meetings.

2. Review of Work progress.

3. Field observations, problems, and decisions.

4. Identification of problems that impede, or will impede, planned progress.

5. Review of submittals schedule and status of submittals.

6. Maintenance of progress schedule.

7. Corrective measures to regain projected schedules.

8. Planned progress during succeeding work period.

01.30.00 - 2 ADMINISTRATIVE

REQUIREMENTS

9. Maintenance of quality and work standards.

10. Effect of proposed changes on progress schedule and coordination.

11. Other business relating to Work.

E. Record minutes and distribute copies within two days after meeting to participants, with copies to Architect, Owner, participants, and those affected by decisions made.

3.03 CONSTRUCTION PROGRESS SCHEDULE

A. If preliminary schedule requires revision after review, submit revised schedule within 10 days.

B. Within 10 days after joint review, submit complete schedule.

C. Submit updated schedule with each Application for Payment.

3.04 SUBMITTALS FOR REVIEW

A. When the following are specified in individual sections, submit them for review:

1. Product data.

2. Shop drawings.

3. Samples for selection.

4. Samples for verification.

B. Submit to Architect for review for the limited purpose of checking for conformance with information given and the design concept expressed in the contract documents.

C. Samples will be reviewed only for aesthetic, color, or finish selection.

D. After review, provide copies and distribute in accordance with SUBMITTAL PROCEDURES article below and for record documents purposes described in Section 01.78.00 - Closeout Submittals.

E. A Contractor's Waste Management Plan shall be submitted to the contractoring officer and AMP-400 prior to the NTP.

3.05 SUBMITTALS FOR INFORMATION

A. When the following are specified in individual sections, submit them for information:

1. Design data.

2. Certificates.

3. Test reports.

4. Inspection reports.

5. Manufacturer's instructions.

6. Manufacturer's field reports.

7. Other types indicated.

B. Periodic (monthly demolition waste management/disposition inventories shall be sent to AMP-400 who will forward to AMP-100.

3.06 SUBMITTALS FOR PROJECT CLOSEOUT

A. Submit Correction Punch List for Substantial Completion.

B. Submit Final Correction Punch List for Substantial Completion.

C. When the following are specified in individual sections, submit them at project closeout:

1. Project record documents.

2. Operation and maintenance data.

3. Warranties.

4. Bonds.

5. Other types as indicated.

3.07 NUMBER OF COPIES OF SUBMITTALS

A. Electronic Documents: Submit one electronic copy in PDF format; an electronically-marked up file will be returned. Create PDFs at native size and right-side up; illegible files will be rejected.

B. All Mechanical Submittals must be submitted Electronically and 2 physical paper copies.

01.30.00 - 3 ADMINISTRATIVE

REQUIREMENTS

C. Samples: Submit the number specified in individual specification sections; one of which will be retained by Architect.

1. Retained samples will not be returned to Contractor unless specifically so stated.

3.08 SUBMITTAL PROCEDURES

A. Shop Drawing Procedures:

1. Prepare accurate, drawn-to-scale, original shop drawing documentation by interpreting the Contract Documents and coordinating related Work.

2. Generic, non-project specific information submitted as shop drawings do not meet the requirements for shop drawings.

B. Submittals shall be submitted electronically thru an online project management software. If Contractor does not have access to an online project management software, the Architect will provide access to Procore software for the Contractor's use.

C. Transmit each submittal with approved form.

D. Sequentially number the transmittal form. Revise submittals with original number and a sequential alphabetic suffix.

E. Identify Project, Contractor, Subcontractor or supplier; pertinent drawing and detail number, and specification section number, as appropriate on each copy.

F. Apply Contractor's stamp, signed or initialed certifying that review, approval, verification of

Products required, field dimensions, adjacent construction Work, and coordination of information is in accordance with the requirements of the Work and Contract Documents.

G. Schedule submittals to expedite the Project, and coordinate submission of related items.

H. For each submittal for review, allow 14 days for the A/E to review plus 7 days for the FAA to review excluding delivery time to and from the Contractor.

I. Identify variations from Contract Documents and Product or system limitations that may be detrimental to successful performance of the completed Work.

J. Provide space for Contractor and Architect review stamps.

K. When revised for resubmission, identify all changes made since previous submission.

L. Distribute reviewed submittals as appropriate. Instruct parties to promptly report any inability to comply with requirements.

M. Submittals not requested will not be recognized or processed.

01.40.00 - 1 QUALITY REQUIREMENTS

SECTION 01.40.00

QUALITY REQUIREMENTS

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Submittals.

B. Testing and inspection agencies and services.

C. Control of installation.

D. Mock-ups.

E. Tolerances.

F. Defect Assessment.

1.02 SUBMITTALS

A. See Section 01.30.00 - Administrative Requirements, for submittal procedures.

B. Design Data: Submit for Architect's knowledge as contract administrator for the limited purpose of assessing conformance with information given and the design concept expressed in the contract documents, or for Owner's information.

C. Test Reports: After each test/inspection, promptly submit two copies of report to Architect and to Contractor.

1. Include:

a. Date issued.

b. Project title and number.

c. Name of inspector.

d. Date and time of sampling or inspection.

e. Identification of product and specifications section.

f. Location in the Project.

g. Type of test/inspection.

h. Date of test/inspection.

i. Results of test/inspection.

j. Conformance with Contract Documents.

k. When requested by Architect, provide interpretation of results.

2. Test report submittals are for Architect's knowledge as contract administrator for the limited purpose of assessing conformance with information given and the design concept expressed in the contract documents, or for Owner's information.

1.03 TESTING AND INSPECTION AGENCIES AND SERVICES

A. Contractor shall employ and pay for services of an independent testing agency to perform other specified testing.

B. Employment of agency in no way relieves Contractor of obligation to perform Work in accordance with requirements of Contract Documents.

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION

3.01 CONTROL OF INSTALLATION

A. Monitor quality control over suppliers, manufacturers, products, services, site conditions, and workmanship, to produce Work of specified quality.

B. Comply with manufacturers' instructions, including each step in sequence.

C. Should manufacturers' instructions conflict with Contract Documents, request clarification from

Architect before proceeding.

01.40.00 - 2 QUALITY REQUIREMENTS

D. Comply with specified standards as minimum quality for the Work except where more stringent tolerances, codes, or specified requirements indicate higher standards or more precise workmanship.

E. Have Work performed by persons qualified to produce required and specified quality.

F. Verify that field measurements are as indicated on shop drawings or as instructed by the manufacturer.

G. Secure products in place with positive anchorage devices designed and sized to withstand stresses, vibration, physical distortion, and disfigurement.

3.02 MOCK-UPS

A. Tests shall be performed under provisions identified in this section and identified in the respective product specification sections.

B. Assemble and erect specified items with specified attachment and anchorage devices, flashings, seals, and finishes.

C. Accepted mock-ups shall be a comparison standard for the remaining Work.

D. Where mock-up has been accepted by Architect and is specified in product specification sections to be removed, protect mock-up throughout construction, remove mock-up and clear area when directed to do so by Architect.

3.03 TOLERANCES

A. Monitor fabrication and installation tolerance control of products to produce acceptable Work.

Do not permit tolerances to accumulate.

B. Comply with manufacturers' tolerances. Should manufacturers' tolerances conflict with Contract

Documents, request clarification from Architect before proceeding.

C. Adjust products to appropriate dimensions; position before securing products in place.

3.04 TESTING AND INSPECTION

A. Testing Agency Duties:

1. Provide qualified personnel at site. Cooperate with Architect and Contractor in performance of services.

2. Perform specified sampling and testing of products in accordance with specified standards.

3. Ascertain compliance of materials and mixes with requirements of Contract Documents.

4. Promptly notify Architect and Contractor of observed irregularities or non-conformance of

Work or products.

5. Perform additional tests and inspections required by Architect.

6. Submit reports of all tests/inspections specified.

B. Limits on Testing/Inspection Agency Authority:

1. Agency may not release, revoke, alter, or enlarge on requirements of Contract Documents.

2. Agency may not approve or accept any portion of the Work.

3. Agency may not assume any duties of Contractor.

4. Agency has no authority to stop the Work.

C. Contractor Responsibilities:

1. Deliver to agency at designated location, adequate samples of materials proposed to be used that require testing, along with proposed mix designs.

2. Cooperate with laboratory personnel, and provide access to the Work and to manufacturers' facilities.

3. Provide incidental labor and facilities:

a. To provide access to Work to be tested/inspected.

b. To obtain and handle samples at the site or at source of Products to be tested/inspected.

c. To facilitate tests/inspections.

d. To provide storage and curing of test samples.

01.40.00 - 3 QUALITY REQUIREMENTS

4. Notify Architect and laboratory 24 hours prior to expected time for operations requiring testing/inspection services.

5. Employ services of an independent qualified testing laboratory and pay for additional samples, tests, and inspections required by Contractor beyond specified requirements.

D. Re-testing required because of non-conformance to specified requirements shall be performed by the same agency on instructions by Architect.

E. Re-testing required because of non-conformance to specified requirements shall be paid for by Contractor.

3.05 DEFECT ASSESSMENT

A. Replace Work or portions of the Work not conforming to specified requirements.

B. If, in the opinion of Architect, it is not practical to remove and replace the Work, Architect will direct an appropriate remedy or adjust payment.

01.50.00 - 1 TEMPORARY FACILITIES AND

CONTROLS

SECTION 01.50.00

TEMPORARY FACILITIES AND CONTROLS

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Temporary utilities.

B. Temporary telecommunications services.

C. Temporary sanitary facilities.

D. Temporary Controls: Barriers, enclosures, and fencing.

E. Security requirements.

F. Vehicular access and parking.

G. Waste removal facilities and services.

H. Project identification sign.

I. Field offices.

1.02 TEMPORARY UTILITIES

A. Provide and pay for all electrical power, lighting, water, heating and cooling, and ventilation required for construction purposes.

B. Use trigger-operated nozzles for water hoses, to avoid waste of water.

1.03 TELECOMMUNICATIONS SERVICES

A. Provide, maintain, and pay for telecommunications services to field office at time of project mobilization.

B. Telecommunications services shall include:

1. Windows-based personal computer dedicated to project telecommunications, with necessary software and laser printer.

2. Telephone Land Lines: One line, minimum; one handset per line.

3. Internet Connections: Minimum of one; DSL modem or faster.

4. Email: Account/address reserved for project use.

1.04 TEMPORARY SANITARY FACILITIES

A. Provide and maintain required facilities and enclosures. Provide at time of project mobilization.

B. Maintain daily in clean and sanitary condition.

1.05 BARRIERS

A. Provide barriers to prevent unauthorized entry to construction areas, to prevent access to areas that could be hazardous to workers or the public, to allow for owner's use of site and to protect existing facilities and adjacent properties from damage from construction operations and demolition.

B. Protect non-owned vehicular traffic, stored materials, site, and structures from damage.

1.06 FENCING

A. Provide 6 foot (1.8 m) high fence around construction site; equip with vehicular and pedestrian gates with locks.

1.07 INTERIOR ENCLOSURES

A. Provide temporary partitions and ceilings as indicated to separate work areas from

Owner-occupied areas, to prevent penetration of dust and moisture into Owner-occupied areas, and to prevent damage to existing materials and equipment.

B. Construction: Framing and reinforced polyethylene sheet materials with closed joints and sealed edges at intersections with existing surfaces:

01.50.00 - 2 TEMPORARY FACILITIES AND

CONTROLS

1.08 SECURITY - SEE SECTION 01.35.53

A. Provide security and facilities to protect Work, existing facilities, and Owner's operations from unauthorized entry, vandalism, or theft.

1.09 VEHICULAR ACCESS AND PARKING

A. Comply with regulations relating to use of streets and sidewalks, access to emergency facilities, and access for emergency vehicles.

B. Coordinate access and haul routes with governing authorities and Owner.

C. Provide and maintain access to fire hydrants, free of obstructions.

D. Provide means of removing mud from vehicle wheels before entering streets.

E. Provide temporary parking areas to accommodate construction personnel. When site space is not adequate, provide additional off-site parking.

1.10 WASTE REMOVAL

A. See Section 01.74.19 - Construction Waste Management and Disposal, for additional requirements.

B. Provide waste removal facilities and services as required to maintain the site in clean and orderly condition.

C. Provide containers with lids. Remove trash from site periodically.

D. If materials to be recycled or re-used on the project must be stored on-site, provide suitable non-combustible containers; locate containers holding flammable material outside the structure unless otherwise approved by the authorities having jurisdiction.

E. Open free-fall chutes are not permitted. Terminate closed chutes into appropriate containers with lids.

1.11 FIELD OFFICES

A. Office: Weathertight, with lighting, electrical outlets, heating, cooling equipment, and equipped with sturdy furniture, drawing rackand drawing display table.

B. Provide space for Project meetings, with table and chairs to accommodate 6 persons.

C. Locate offices a minimum distance of 30 feet (10 m) from existing and new structures.

1.12 REMOVAL OF UTILITIES, FACILITIES, AND CONTROLS

A. Remove temporary utilities, equipment, facilities, materials, prior to Date of Substantial

Completion inspection.

B. Remove underground installations to a minimum depth of 2 feet (600 mm). Grade site as indicated.

C. Clean and repair damage caused by installation or use of temporary work.

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION - NOT USED

01.60.00 - 1 PRODUCT REQUIREMENTS

SECTION 01.60.00

PRODUCT REQUIREMENTS

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Re-use of existing products.

B. Transportation, handling, storage and protection.

C. Product option requirements.

D. Substitution limitations and procedures.

E. Procedures for Owner-supplied products.

F. Maintenance materials, including extra materials, spare parts, tools, and software.

1.02 SUBMITTALS

A. Product Data Submittals: Submit manufacturer's standard published data. Mark each copy to identify applicable products, models, options, and other data. Supplement manufacturers' standard data to provide information specific to this Project.

B. All chemicals, lubricants, paints, solvents, sealants, adhesives, patching materials, cements, foam insulation and gypsum wall board and other materials that may potentially contain ACM must have Material Safety Data Sheets (SDS) submitted prior to installation.

C. Shop Drawing Submittals: Prepared specifically for this Project; indicate utility and electrical characteristics, utility connection requirements, and location of utility outlets for service for functional equipment and appliances.

D. Sample Submittals: Illustrate functional and aesthetic characteristics of the product, with integral parts and attachment devices. Coordinate sample submittals for interfacing work.

1. For selection from standard finishes, submit samples of the full range of the manufacturer's standard colors, textures, and patterns.

PART 2 PRODUCTS

2.01 EXISTING PRODUCTS

A. Do not use materials and equipment removed from existing premises unless specifically required or permitted by the Contract Documents.

B. Unforeseen historic items encountered remain the property of the Owner; notify Owner promptly upon discovery; protect, remove, handle, and store as directed by Owner.

C. Existing materials and equipment indicated to be removed, but not to be re-used, relocated, reinstalled, delivered to the Owner, or otherwise indicated as to remain the property of the Owner, become the property of the Contractor; remove from site.

2.02 NEW PRODUCTS

A. Provide new products unless specifically required or permitted by the Contract Documents.

2.03 PRODUCT OPTIONS

A. Products Specified by Reference Standards or by Description Only: Use any product meeting those standards or description.

B. Products Specified by Naming One or More Manufacturers: Use a product of one of the manufacturers named and meeting specifications, no options or substitutions allowed.

C. Products Specified by Naming One or More Manufacturers with a Provision for Substitutions:

Submit a request for substitution for any manufacturer not named.

2.04 MAINTENANCE MATERIALS

A. Furnish extra materials, spare parts, tools, and software of types and in quantities specified in individual specification sections.

B. Deliver to Project site; obtain receipt prior to final payment.

01.60.00 - 2 PRODUCT REQUIREMENTS

PART 3 EXECUTION

3.01 SUBSTITUTION PROCEDURES

A. Contracting Officer will consider requests for Substitutions only within ten (10) days after award of Contract.

B. Substitutions may be considered when a Product becomes unavailable through no fault of the Contractor.

C. Document each request with complete data substantiating compliance of proposed Substitution with Contract Documents.

D. A request constitutes a representation that the Contractor:

1. Has investigated proposed Product and determined that it meets or exceeds the quality level of the specified Product.

2. Will provide the same warranty for the Substitution as for the specified Product.

3. Will coordinate installation and make changes to other Work, which may be required for the Work to be completed with no additional cost to the FAA.

4. Waives claims for additional costs or time extension, which may subsequently become apparent.

5. Will reimburse Contracting Officer for review or redesign services associated with re-approval for authorities.

E. Substitutions will not be considered when they are indicated or implied on shop drawing or

Product data submittals, without separate written request, or when acceptance will require revision to the Contract Documents.

F. Substitution Submittal Procedure:

1. Submit three (3) copies of request for Substitution for consideration on Substitution

Request Form attached to this section. Limit each Substitution Request Form to one (1) proposed Substitution.

2. Submit shop drawings, Product data, and certified test results attesting to the proposed Product equivalence.

3. The Contracting Officer will notify Contractor in writing of decision to accept or reject request.

G. If request for substitution is not accepted by the Contracting Officer, Contractor is responsible for supplying item as origionally specified or an acceptable substitution without additional cost to the FAA.

3.02 OWNER-SUPPLIED PRODUCTS

A. Owner's Responsibilities:

1. Arrange for and deliver Owner reviewed shop drawings, product data, and samples, to Contractor.

2. Arrange and pay for product delivery to site.

3. On delivery, inspect products jointly with Contractor.

4. Submit claims for transportation damage and replace damaged, defective, or deficient items.

5. Arrange for manufacturers' warranties, inspections, and service.

B. Contractor's Responsibilities:

1. Review Owner reviewed shop drawings, product data, and samples.

2. Receive and unload products at site; inspect for completeness or damage jointly with

Owner.

3. Handle, store, install and finish products.

4. Repair or replace items damaged after receipt.

3.03 TRANSPORTATION AND HANDLING

A. Package products for shipment in manner to prevent damage; for equipment, package to avoid loss of factory calibration.

01.60.00 - 3 PRODUCT REQUIREMENTS

B. If special precautions are required, attach instructions prominently and legibly on outside of packaging.

C. Coordinate schedule of product delivery to designated prepared areas in order to minimize site storage time and potential damage to stored materials.

D. Transport and handle products in accordance with manufacturer's instructions.

E. Transport materials in covered trucks to prevent contamination of product and littering of surrounding areas.

F. Promptly inspect shipments to ensure that products comply with requirements, quantities are correct, and products are undamaged.

G. Provide equipment and personnel to handle products by methods to prevent soiling, disfigurement, or damage, and to minimize handling.

H. Arrange for the return of packing materials, such as wood pallets, where economically feasible.

3.04 STORAGE AND PROTECTION

A. Designate receiving/storage areas for incoming products so that they are delivered according to installation schedule and placed convenient to work area in order to minimize waste due to excessive materials handling and misapplication.

B. Store and protect products in accordance with manufacturers' instructions.

C. Store with seals and labels intact and legible.

D. Store sensitive products in weather tight, climate controlled, enclosures in an environment favorable to product.

E. For exterior storage of fabricated products, place on sloped supports above ground.

F. Provide bonded off-site storage and protection when site does not permit on-site storage or protection.

G. Protect products from damage or deterioration due to construction operations, weather, precipitation, humidity, temperature, sunlight and ultraviolet light, dirt, dust, and other contaminants.

H. Comply with manufacturer's warranty conditions, if any.

I. Cover products subject to deterioration with impervious sheet covering. Provide ventilation to prevent condensation and degradation of products.

J. Prevent contact with material that may cause corrosion, discoloration, or staining.

K. Provide equipment and personnel to store products by methods to prevent soiling, disfigurement, or damage.

L. Arrange storage of products to permit access for inspection. Periodically inspect to verify products are undamaged and are maintained in acceptable condition.

01.70.00 - 1 EXECUTION AND CLOSEOUT

REQUIREMENTS

SECTION 01.70.00

EXECUTION AND CLOSEOUT REQUIREMENTS

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Examination, preparation, and general installation procedures.

B. Requirements for alterations work, including selective demolition, except removal, disposal, and/or remediation of hazardous materials and toxic substances.

C. Pre-installation meetings.

D. Cutting and patching.

E. Surveying for laying out the work.

F. Cleaning and protection.

G. Starting of systems and equipment.

H. Demonstration and instruction of Owner personnel.

I. Closeout procedures, including Contractor's Correction Punch List, except payment procedures.

J. General requirements for maintenance service.

1.02 RELATED REQUIREMENTS

A. Section 01.79.00 - Demonstration and Training: Demonstration of products and systems to be commissioned and where indicated in specific specification sections B. Section 07.84.00 - Firestopping.

1.03 QUALIFICATIONS

A. For design of temporary shoring and bracing, employ a Professional Engineer experienced in design of this type of work and licensed in the State in which the Project is located.

1.04 PROJECT CONDITIONS

A. Ventilate enclosed areas to assist cure of materials, to dissipate humidity, and to prevent accumulation of dust, fumes, vapors, or gases.

PART 2 PRODUCTS

2.01 PATCHING MATERIALS

A. New Materials: As specified in product sections; match existing products and work for patching and extending work.

B. Type and Quality of Existing Products: Determine by inspecting and testing products where necessary, referring to existing work as a standard.

C. Product Substitution: For any proposed change in materials, submit request for substitution described in Section 01.60.00 - Product Requirements.

PART 3 EXECUTION

3.01 EXAMINATION

A. Verify that existing site conditions and substrate surfaces are acceptable for subsequent work.

Start of work means acceptance of existing conditions.

B. Verify that existing substrate is capable of structural support or attachment of new work being applied or attached.

C. Examine and verify specific conditions described in individual specification sections.

D. Take field measurements before confirming product orders or beginning fabrication, to minimize waste due to over-ordering or misfabrication.

E. Verify that utility services are available, of the correct characteristics, and in the correct locations.

01.70.00 - 2 EXECUTION AND CLOSEOUT

REQUIREMENTS

F. Prior to Cutting: Examine existing conditions prior to commencing work, including elements subject to damage or movement during cutting and patching. After uncovering existing work, assess conditions affecting performance of work. Beginning of cutting or patching means acceptance of existing conditions.

3.02 PREPARATION

A. Clean substrate surfaces prior to applying next material or substance.

B. Seal cracks or openings of substrate prior to applying next material or substance.

C. Apply manufacturer required or recommended substrate primer, sealer, or conditioner prior to applying any new material or substance in contact or bond.

3.03 PREINSTALLATION MEETINGS

A. When required in individual specification sections, convene a preinstallation meeting at the site prior to commencing work of the section.

B. Require attendance of parties directly affecting, or affected by, work of the specific section.

C. Notify Architect four days in advance of meeting date.

D. Prepare agenda and preside at meeting:

1. Review conditions of examination, preparation and installation procedures.

2. Review coordination with related work.

E. Record minutes and distribute copies within two days after meeting to participants, with two copies to Architect, Owner, participants, and those affected by decisions made.

3.04 GENERAL INSTALLATION REQUIREMENTS

A. Install products as specified in individual sections, in accordance with manufacturer's instructions and recommendations, and so as to avoid waste due to necessity for replacement.

B. Make vertical elements plumb and horizontal elements level, unless otherwise indicated.

C. Install equipment and fittings plumb and level, neatly aligned with adjacent vertical and horizontal lines, unless otherwise indicated.

D. Make consistent texture on surfaces, with seamless transitions, unless otherwise indicated.

E. Make neat transitions between different surfaces, maintaining texture and appearance.

3.05 ALTERATIONS

A. Drawings showing existing construction and utilities are based on casual field observation and existing record documents only.

1. Verify that construction and utility arrangements are as shown.

2. Report discrepancies to Architect before disturbing existing installation.

3. Beginning of alterations work constitutes acceptance of existing conditions.

B. Remove existing work as indicated and as required to accomplish new work.

1. Remove items indicated on drawings.

2. Relocate items indicated on drawings.

3. Where new surface finishes are to be applied to existing work, perform removals, patch, and prepare existing surfaces as required to receive new finish; remove existing finish if necessary for successful application of new finish.

4. Where new surface finishes are not specified or indicated, patch holes and damaged surfaces to match adjacent finished surfaces as closely as possible.

5. A bird net is existing on the underside of the building structure. Contractor shall remove netting prior to starting High Bay work in Hangar 8. Contractor shall install new bird netting with zippers in netting where equipment or valves are located. Contractor shall install netting after High Bay Work is completed.

C. Services (Including but not limited to HVAC, Plumbing, Fire Protection, Electrical, and Telecommunications): Remove, relocate, and extend existing systems to accommodate new construction.

01.70.00 - 3 EXECUTION AND CLOSEOUT

REQUIREMENTS

1. Maintain existing active systems that are to remain in operation; maintain access to equipment and operational components; if necessary, modify installation to allow access or provide access panel.

2. Where existing systems or equipment are not active and Contract Documents require reactivation, put back into operational condition; repair supply, distribution, and equipment as required.

3. Where existing active systems serve occupied facilities but are to be replaced with new services, maintain existing systems in service until new systems are complete and ready for service.

a. Disable existing systems only to make switchovers and connections; minimize duration of outages.

b. Provide temporary connections as required to maintain existing systems in service.

4. Verify that abandoned services serve only abandoned facilities.

5. Remove abandoned pipe, ducts, conduits, and equipment, including those above accessible ceilings; remove back to source of supply where possible, otherwise cap stub and tag with identification; patch holes left by removal using materials specified for new construction.

D. Protect existing work to remain.

1. Prevent movement of structure; provide shoring and bracing if necessary.

2. Perform cutting to accomplish removals neatly and as specified for cutting new work.

3. Repair adjacent construction and finishes damaged during removal work.

E. Adapt existing work to fit new work: Make as neat and smooth transition as possible.

F. Patching: Where the existing surface is not indicated to be refinished, patch to match the surface finish that existed prior to cutting. Where the surface is indicated to be refinished, patch so that the substrate is ready for the new finish.

G. Refinish existing surfaces as indicated:

1. Where rooms or spaces are indicated to be refinished, refinish all visible existing surfaces to remain to the specified condition for each material, with a neat transition to adjacent finishes.

2. If mechanical or electrical work is exposed accidentally during the work, re-cover and refinish to match.

H. Remove demolition debris and abandoned items from alterations areas and dispose of off-site per Waste Management Plan submitted and approved by the FAA per Section 017419 Construction Waste Management and Disposal ; do not burn or bury.

I. Comply with all other applicable requirements of this section.

3.06 CUTTING AND PATCHING

A. Whenever possible, execute the work by methods that avoid cutting or patching.

B. See Alterations article above for additional requirements.

C. Perform whatever cutting and patching is necessary to:

1. Complete the work.

2. Fit products together to integrate with other work.

3. Provide openings for penetration of mechanical, electrical, and other services.

4. Match work that has been cut to adjacent work.

5. Repair areas adjacent to cuts to required condition.

6. Repair new work damaged by subsequent work.

7. Remove samples of installed work for testing when requested.

8. Remove and replace defective and non-conforming work.

D. Execute work by methods that avoid damage to other work and that will provide appropriate surfaces to receive patching and finishing. In existing work, minimize damage and restore to original condition.

01.70.00 - 4 EXECUTION AND CLOSEOUT

REQUIREMENTS

E. Employ original installer to perform cutting for weather exposed and moisture resistant elements, and sight exposed surfaces.

F. Cut rigid materials using masonry saw or core drill. Pneumatic tools not allowed without prior approval.

G. Restore work with new products in accordance with requirements of Contract Documents.

H. Fit work air tight to pipes, sleeves, ducts, conduit, and other penetrations through surfaces.

I. At penetrations of fire rated walls, partitions, ceiling, or floor construction, completely seal voids with fire rated material in accordance with Section 07.84.00, to full thickness of the penetrated element.

J. Patching:

1. Finish patched surfaces to match finish that existed prior to patching. On continuous surfaces, refinish to nearest intersection or natural break. For an assembly, refinish entire unit.

2. Match color, texture, and appearance.

3. Repair patched surfaces that are damaged, lifted, discolored, or showing other imperfections due to patching work. If defects are due to condition of substrate, repair substrate prior to repairing finish.

3.07 PROGRESS CLEANING

A. Maintain areas free of waste materials, debris, and rubbish. Maintain site in a clean and orderly condition.

B. Remove debris and rubbish from pipe chases, plenums, attics, crawl spaces, and other closed or remote spaces, prior to enclosing the space.

C. Broom and vacuum clean interior areas prior to start of surface finishing, and continue cleaning to eliminate dust.

D. Collect and remove waste materials, debris, and trash/rubbish from site daily and dispose off-site; do not burn or bury.

3.08 PROTECTION OF INSTALLED WORK

A. Protect installed work from damage by construction operations.

B. Provide special protection where specified in individual specification sections.

C. Provide temporary and removable protection for installed products. Control activity in immediate work area to prevent damage.

D. Provide protective coverings at walls, projections, jambs, sills, and soffits of openings.

E. Protect finished floors, stairs, and other surfaces from traffic, dirt, wear, damage, or movement of heavy objects, by protecting with durable sheet materials.

F. Prohibit traffic or storage upon waterproofed or roofed surfaces. If traffic or activity is necessary, obtain recommendations for protection from waterproofing or roofing material manufacturer.

G. Remove protective coverings when no longer needed; reuse or recycle coverings if possible.

3.09 SYSTEM STARTUP

A. Coordinate schedule for start-up of various equipment and systems.

B. Verify that each piece of equipment or system has been checked for proper lubrication, drive rotation, belt tension, control sequence, and for conditions that may cause damage.

C. Verify tests, meter readings, and specified electrical characteristics agree with those required by the equipment or system manufacturer.

D. Verify that wiring and support components for equipment are complete and tested.

E. Execute start-up under supervision of applicable Contractor personnel and manufacturer's representative in accordance with manufacturers' instructions.

01.70.00 - 5 EXECUTION AND CLOSEOUT

REQUIREMENTS

F. Submit a written report that equipment or system has been properly installed and is functioning correctly.

3.10 DEMONSTRATION AND INSTRUCTION

A. See Section 01.79.00 - Demonstration and Training.

3.11 ADJUSTING

A. Adjust operating products and equipment to ensure smooth and unhindered operation.

3.12 FINAL CLEANING

A. Power washing of any exterior surface will require a Cosmetic Cleaning Permit with the City of

Oklahoma City, per 57-190 of the OKC Municpial Code.

B. Storm drains must be protected from illicit discharges.

C. Use cleaning materials that are nonhazardous.

D. Clean interior and exterior glass, surfaces exposed to view; remove temporary labels, stains and foreign substances, polish transparent and glossy surfaces, vacuum carpeted and soft surfaces.

E. Remove all labels that are not permanent. Do not paint or otherwise cover fire test labels or nameplates on mechanical and electrical equipment.

F. Clean equipment and fixtures to a sanitary condition with cleaning materials appropriate to the surface and material being cleaned.

G. Clean filters of operating equipment.

H. Clean debris from [].

I. Clean site; sweep paved areas, rake clean landscaped surfaces.

J. Remove waste, surplus materials, trash/rubbish, and construction facilities from the site;

dispose of in legal manner; do not burn or bury.

3.13 CLOSEOUT PROCEDURES

A. Make submittals that are required by governing or other authorities.

1. Provide copies to Architect.

B. Accompany Project Coordinator on preliminary inspection to determine items to be listed for completion or correction in the Contractor's Correction Punch List for Contractor's Notice of Substantial Completion.

C. Notify Architect when work is considered ready for Architect's Substantial Completion inspection.

D. Submit written certification containing Contractor's Correction Punch List, that Contract Documents have been reviewed, work has been inspected, and that work is complete in accordance with Contract Documents and ready for Architect's Substantial Completion inspection.

E. Conduct Substantial Completion inspection and create Final Correction Punch List containing Architect's and Contractor's comprehensive list of items identified to be completed or corrected and submit to Architect.

F. Correct items of work listed in Final Correction Punch List and comply with requirements for access to Owner-occupied areas.

G. Notify Architect when work is considered finally complete and ready for Architect's Substantial Completion final inspection.

H. Complete items of work determined by Architect listed in executed Certificate of Substantial Completion.

3.14 MAINTENANCE

A. Provide service and maintenance of components indicated in specification sections.

01.70.00 - 6 EXECUTION AND CLOSEOUT

REQUIREMENTS

B. Maintenance Period: As indicated in specification sections or, if not indicated, not less than one year from the Date of Substantial Completion or the length of the specified warranty, whichever is longer.

C. Examine system components at a frequency consistent with reliable operation. Clean, adjust, and lubricate as required.

D. Include systematic examination, adjustment, and lubrication of components. Repair or replace parts whenever required. Use parts produced by the manufacturer of the original component.

E. Maintenance service shall not be assigned or transferred to any agent or subcontractor without prior written consent of the Owner.

01.74.19 - 1 CONSTRUCTION WASTE

MANAGEMENT AND DISPOSAL

SECTION 01.74.19

CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

PART 1 GENERAL

1.01 WASTE MANAGEMENT REQUIREMENTS

A. Owner requires that this project generate the least amount of trash and waste possible.

B. Employ processes that ensure the generation of as little waste as possible due to error, poor planning, breakage, mishandling, contamination, or other factors.

C. Required Recycling, Salvage, and Reuse: The following may not be disposed of in landfills or by incineration:

1. Mechanical and electrical equipment.

a. If during the demolition of the existing systems, mercury thermostats are removed for discard, these devices need to be collected in a bucket or other suitable container and provided to AMP-100 for proper recycling/disposal as hazardous waste.

2. Fluorescent lamps (light bulbs).

a. All lighting lamps and ballasts that are recovered during the demolition are treated as universal waste or potential universal waste. All UV lamps must be containerized in cartons for recycling and PCB ballasts collected in drums or other suitable container.

Coordinate activities with AMP-100. This project will be in excess of $100K;

therefore, the contractor will be responsible for providing all cartons, drums, and other containers for collecting ballast and lighting. Although AMP-100 is available for consultation and advice, it is the contractor's responsibility for containerization and removal of Universal Waste as well as reporting the disposition/recycling to AMP-400 and AMP-100.

3. Refrigerant.

a. The Contractor's refrigerant recovery contractor shall provide records to…