Amendment 000002.pdf
PDF 134 KB Posted
- Attached to
- CONSTRUCTION: Hangar 08 & 09 Mechanical Upgrades at the Mike Monroney Aeronautical Center, Oklahoma City, OK
- Solicitation number
- DTFAAC-17-R-00023
About this file
Amendment 000002 (pdf)
View the file
Other files
Show 40 more
Latest 50 of 174 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
5. PROJECT NO. (If applicable)2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ.NO.
PAGE OF PAGES
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6)
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
CODE
9A. AMENDMENT OF SOLICITATION NO.
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
Items 8 and 15, and returning is extended, is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required.)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
(x) A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO THE AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14.
E. IMPORTANT: Contractor is not, is required to sign this document and return
ORDER NO. IN ITEM 10A.
1 3
000002 08/18/2017
AAQ-811 FAC. & AVIATION SAFETY ACQ
FAA AERONAUTICAL CENTER
PO BOX 25082
MPB ROOM 380
AAQ0811-AFN
OKLAHOMA CITY OK 73125
AAQ-811 FAC. & AVIATION SAFETY ACQ
FAA AERONAUTICAL CENTER
PO BOX 25082
MPB ROOM 380
AAQ811-AFN
OKLAHOMA CITY OK 73125
x
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
separate letter or telegram which includes a reference to the solicitation and amendment number. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT
THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By ___________ 1 x x
DTFAAC-17-R-00023
1 copies to the issuing office.
07/25/2017
(x)
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. CONTRACT AUTHORITY 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Cynthia L. Cooper
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
LIST OF CHANGES:
The purpose of this amendment is to revise page 45, revise Section L.3 Instructions for Preparation and Submission of Proposals, remove clause AC4540 and extend the closing date.
FIRST: Page 45, Section J, Addendum 2 added as Attachment 13, 16-044 Addendum #2 added as Attachment 14, Hangar 8 E Addendum 2 added as attachment 15, Hangar 9 E Addendum 2 added as Attachment 16, M2-01 - Hangar 9 Site Plan and First Floor Plan added as Attachment 17, M4-01 - Hangar 8 Details and Schedules added as Attachment 18, Section 232113 - Hydronic Piping added as Attachment 19, Section 237313 - Central-Station-Air- Handling Units added as Attachment 20, Section 237416.13 - Packaged, Large-Capacity, Rooftop-Air-Conditioning Units added as Attachment 21, and Title Sheet added as Attachment 22.
SECOND: Page 53, Section L.3 Instructions for Preparation and Submission of Proposals, Paragraph (i) Section II
- Technical Documentation, section (1) is hereby revised as follows:
FROM: (1) Offerors shall provide adequate past performance information on completed or current contracts (including Federal, State, local government, and private) considered most relevant in demonstrating the ability to perform the proposed work as identified within the Drawings and Specifications. Offerors are required to explain what aspects of each contract are deemed relevant to complexity and magnitude as related to the requirements of this solicitation and in accordance with Section M.
(a) The Offeror shall complete a minimum of three (3), but no more than five (5), "Past Performance Experience Information" forms, attached to the SIR (Section J, Attachment 9) in response to this factor. All blocks must be filled in and all data should be accurate, current and complete. All projects submitted must have been underway or completed within the last 7 years through the closing date identified on the SIR. Each project provided must be valued at or over $2,500,000. If the Offeror does not have prime contracts to cite, then the Offeror may cite instances on which it has served as a primary subcontractor.
(b) Offerors shall have current or past customers complete the attached Past Performance Survey (PPS) attached to the SIR (Section J, Attachment 10). A minimum of three (3) but no more than five (5) completed PPS's shall be submitted directly from the offeror's customer to the Contracting Officer no later than the SIR closing date. All PPS submitted must show the projects are underway or completed with the last 7 years through the closing date identified on the SIR. The Offeror's construction projects (or greater than) the complexity and breadth of the Hangar 08 and 09 Mechanical Upgrades Project.
The Offeror's ability to meet contract obligations in a timely manner is an area of particular importance. A proposal should demonstrate acceptable past performance on construction projects of same or similar scope, complexity, and magnitude as the Hangar 08 and 09 Mechanical Upgrades.
Each PPS submitted shall be for work that is valued at or over $2,500,000.
TO: (1) Offerors shall provide adequate past performance information on completed or current contracts (including Federal, State, local government, and private) considered most relevant in demonstrating the ability to perform the proposed work as identified within the Drawings and Specifications. Offerors are required to explain what aspects of each contract are deemed relevant to complexity and magnitude as related to the requirements of this solicitation and in accordance with Section M.
(a) The Offeror shall complete a minimum of three (3), but no more than five (5), "Past Performance Experience Information" forms, attached to the SIR (Section J, Attachment 9) in response to this factor. All blocks must be filled in and all data should be accurate, current and complete. All projects submitted must have been underway or completed within the last 7 years through the closing date identified on the SIR. Each project provided must be valued at or over $2,000,000. If the Offeror does not have prime contracts to cite, then the Offeror may cite instances on which it has served as a primary subcontractor.
(b) Offerors shall have current or past customers complete the attached Past Performance Survey (PPS) attached to the SIR (Section J, Attachment 10). A minimum of three (3) but no more than five (5) completed PPS's shall be submitted directly from the offeror's customer to the Contracting Officer no later than the SIR closing date. All PPS submitted must show the projects are underway or completed with the last 7 years through the closing date identified on the SIR. The Offeror's construction projects (or greater than) the complexity and breadth of the Hangar 08 and 09 Mechanical Upgrades Project.
*If a current or past customer will no longer be allowed to complete any type of past performance questionnaire for projects, then a final Construction Contractor Appraisal Support System (CCASS) / Contractor Performance Assessment Reports (CPARS) evaluation may be submitted.
The Offeror's ability to meet contract obligations in a timely manner is an area of particular importance. A proposal should demonstrate acceptable past performance on construction projects of same or similar scope, complexity, and magnitude as the Hangar 08 and 09 Mechanical Upgrades.
Each PPS submitted shall be for work that is valued at or over $2,000,000.
THIRD: Page 18, Clause AC4540, Agreement to Participate in Alternative Dispute, is no longer applicable and is hereby deleted.
FOURTH: The Proposal Due Date is hereby extended as follows:
FROM: Tuesday, August 22, 2017 at 2:00 p.m. CT TO: Thursday, August 24, 2017 at 2:00 p.m. CT
FIFTH: All other terms and conditions remain unchanged and in full force and effect.