This document is a sources sought notice for a hospital modernization project at Misawa Air Base in Japan. The Air Force is seeking industry input to determine availability of potential sources that can fulfill project requirements, which include modernizing existing facilities and constructing new buildings. Responses to the notice will be used to develop an acquisition strategy and will not result in contract awards. The draft specifications and drawings provided are for informational purposes only. Interested parties are encouraged but not required to submit input by [no response date given]. The Government will not reimburse any costs associated with responding.

View the file

Other files for this federal contract opportunity

Other files attached to Sources Sought - Hospital Modernization Misawa Air Base, Japan, newest first.
File Type Posted
Sources Sought - Misawa Hospital Modernization_3Feb2021.docx DOCX document
Sources Sought - Misawa Hospital Modernization.docx DOCX document
DRAFT_Drawing 04 MABH-Architecture.pdf PDF
DRAFT_Drawing 07 MABH-FireProtection.pdf PDF
DRAFT_Drawing 02 MABH-Civil.pdf PDF
DRAFT_Drawing 01 MABH-General.pdf PDF
DRAFT_Drawing 08 MABH-Plumbing.pdf PDF
DRAFT_Drawing 05 MABH-Interiors.pdf PDF
DRAFT_Drawing 09 MABH-Mechanical.pdf PDF
DRAFT_Drawing 03 MABH-Structural.pdf PDF
DRAFT_Drawing 06 MABH-Equipment.pdf PDF
DRAFT_Drawing 10 MABH-Electrical.pdf PDF
DRAFT_Specifications_Volume 1.pdf PDF
Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FY19 HOSPITAL MODERNIZATION

MISAWA AIR BASE, JAPAN

Contract No. FA 8903-15-D-0004 Task Order 18-F-0072 Legacy project # QKKA188003, Opportunity 1090686

PROJECT SPECIFICATIONS

Volume 2 of 2 Divisions 21 -33

ISSUED FOR CONSTRUCTION

23 December 2019

Hospital Modernization, Misawa AB Japan Issued for Construction Legacy Project #QKKA188003, Opportunity 1090686 December 23, 2019

SPECIFICATIONS TABLE OF CONTENTS Page 1

SPECIFICATIONS TABLE OF CONTENTS

VOLUME 1: DIVISIONS 01 - 13

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 SUMMARY OF WORK

ATTACHMENT: CONSTRUCTION SIGN

01 33 00 SUBMITTAL PROCEDURES

01 42 00.00 33 JIS ACCEPTABLE ALTERNATIVES

ATTACHMENT: JAPANESE PROFESSIONAL EXPERIENCE AND

REGISRATION EQUIVALENCIES

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 42 15 METRIC MEASUREMENTS

01 45 00.00 10 QUALITY CONTROL

01 45 35 SPECIAL INSPECTIONS

ATTACHMENT 1: STATEMENT OF SPECIAL INSPECTIONS

ATTACHMENT 2: SCHEDULE OF SPECIAL INSPECTIONS

01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS

01 57 20.00 10 ENVIRONMENTAL PROTECTION

ATTACHMENT: MISAWA AB INFECTION PROGRAM (1 of 2) ATTACHMENT: MISAWA AF INFECTION PROGRAM (2 of 2)

01 73 19 INSTALLATION OF GOVERNMENT-FURNISHED MEDICAL EQUIPMENT

01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT

01 78 00 CLOSEOUT SUBMITTALS

01 78 23 OPERATION AND MAINTENANCE DATA

01 91 00.15 TOTAL BUILDING COMMISSIONING

DIVISION 02 – EXISTING CONDITIONS

02 41 00 DEMOLITION AND DECONSTRUCTION

ATTACHMENT: DLA DISPOSITION SERVICES TURN-IN SMARTBOOK

02 82 00 ASBESTOS REMEDIATION

ATTACHMENTS: ASBESTOS LAB RESULTS

02 83 00 LEAD REMEDIATION

ATTACHMENT: LEAD PAINT LAB RESULTS

02 84 33 REMOVAL AND DISPOSAL OF POLYCHLORINATED BIPHENYLS (PCBs)

DIVISION 03 - CONCRETE

03 30 00 CAST-IN-PLACE CONCRETE

DIVISION 05 - METALS

05 12 00 STRUCTURAL STEEL

05 30 00 STEEL DECKS

05 40 00 COLD-FORMED METAL FRAMING

05 50 13 MISCELLANEOUS METAL FABRICATIONS

ATTACHMENT: BUILDING ENVELOPE INSPECTION CHECKLIST

DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES

06 10 00 ROUGH CARPENTRY

06 20 00 FINISH CARPENTRY

06 61 16 SOLID SURFACING FABRICATIONS

SPECIFICATIONS TABLE OF CONTENTS Page 2

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 13 53 ELASTOMERIC SHEET WATERPROOFING

ATTACHMENT: BUILDING ENVELOPE INSPECTION CHECKLIST

07 21 13 BOARD AND BLOCK INSULATION

07 21 16 MINERAL FIBER BLANKET INSULATION

ATTACHMENT: BUILDING ENVELOPE INSPECTION CHECKLIST

07 22 00 ROOF AND DECK INSULATION

ATTACHMENT: BUILDING ENVELOPE INSPECTION CHECKLIST

07 27 26 FLUID-APPLIED MEMBRANE AIR BARRIERS

07 41 13 METAL ROOF PANELS

ATTACHMENT: BUILDING ENVELOPE INSPECTION CHECKLIST

07 42 13 METAL WALL PANELS

ATTACHMENT: BUILDING ENVELOPE INSPECTION CHECKLIST

07 54 19 POLYVINYL-CHLORIDE ROOFING

ATTACHMENT: BUILDING ENVELOPE INSPECTION CHECKLIST

07 60 00 FLASHING AND SHEET METAL

ATTACHMENT: BUILDING ENVELOPE INSPECTION CHECKLIST

07 81 00 SPRAY-APPLIED FIREPROOFING

07 84 00 FIRESTOPPING

07 92 00 JOINT SEALANTS

ATTACHMENT: BUILDING ENVELOPE INSPECTION CHECKLIST

DIVISION 08 - OPENINGS

08 11 13 STEEL DOORS AND FRAMES

ATTACHMENT: BUILDING ENVELOPE INSPECTION CHECKLIST

08 14 00 WOOD DOORS

08 31 00 ACCESS DOORS AND PANELS

08 41 13 ALUMINUM-FRAMED ENTRANCES AND STOREFRONTS

ATTACHMENT: BUILDING ENVELOPE INSPECTION CHECKLIST

08 71 00 DOOR HARDWARE

08 81 00 GLAZING

ATTACHMENT: BUILDING ENVELOPE INSPECTION CHECKLIST

08 91 00 METAL WALL LOUVERS

ATTACHMENT: BUILDING ENVELOPE INSPECTION CHECKLIST

DIVISION 09 - FINISHES

09 06 00 SCHEDULES FOR FINISHES

09 22 00 SUPPORTS FOR PLASTER AND GYPSUM BOARD

09 24 23 CEMENT STUCCO

ATTACHMENT: BUILDING ENVELOPE INSPECTION CHECKLIST

09 29 00 GYPSUM BOARD

09 30 10 CERAMIC, QUARRY, AND GLASS TILING

09 51 00 ACOUSTICAL CEILINGS

09 65 00 RESILIENT FLOORING

09 67 23.13 STANDARD RESINOUS FLOORING

09 68 00 CARPETING

09 72 00 DIGITALLY PRINTED WALL COVERING MURAL

09 90 00 PAINTS AND COATINGS

09 96 00 HIGH-PERFORMANCE COATINGS

SPECIFICATIONS TABLE OF CONTENTS Page 3

DIVISION 10 - SPECIALTIES

10 14 00.10 EXTERIOR SIGNAGE

10 14 00.20 INTERIOR SIGNAGE

10 26 00 WALL AND DOOR PROTECTION

10 28 13 TOILET ACCESSORIES

10 44 16 FIRE EXTINGUISHERS

DIVISION 11 - EQUIPMENT

11 70 00 GENERAL REQUIREMENTS FOR MEDICAL AND DENTAL EQUIPMENT

11 71 00 WARMING CABINETS, STERILIZERS, AND ASSOCIATED EQUIPMENT

11 72 13 MEDICAL EQUIPMENT, MISCELLANEOUS

11 74 00 DENTAL EQUIPMENT

DIVISION 12 - FURNISHINGS

12 24 13 ROLLER WINDOW SHADES

12 35 70 HEALTHCARE CASEWORK

12 36 00 COUNTERTOPS

12 48 13 ENTRANCE FLOOR MATS AND FRAMES

DIVISION 13 - SPECIAL CONSTRUCTION

13 48 00 SEISMIC BRACING FOR MISCELLANEOUS EQUIPMENT

13 49 10 X-RAY SHIELDING

ATTACHMENTs: PHYSICIST REPORTS (3)

VOLUME 2: DIVISIONS 21 – 33

DIVISION 21 - FIRE SUPPRESSION

21 13 18.00 10 PREACTION AND DELUGE SPRINKLER SYSTEMS, FIRE PROTECTION

21 30 00 AUTOMATIC TRANSFER SWITCHES FOR FIRE PUMP CONTROL

DIVISION 22 - PLUMBING

22 00 70 PLUMBING, HEALTHCARE FACILITIES

ATTACHMENT A: DOMESTIC WATER PUMP PREFUNCTIONAL CHECKLIST

ATTACHMENT B: DOMESTIC WATER BOOSTER PUMP FUNCTIONAL

PERFORMANCE TEST

ATTACHMENT C: DOMESTIC WATER CIRCULATING PUMP PREFUNCTIONAL

CHECKLIST

22 31 00 WATER SOFTENERS, CATION-EXCHANGE (SODIUM CYCLE)

ATTACHMENT A: WATER SOFTENER PREFUNCTIONAL CHECKLIST

22 60 70 GAS AND VACUUM SYSTEMS FOR HEALTHCARE FACILITIES

DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)

23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS

ATTACHMENT A: MODULAR AIR-HANDLING UNIT PREFUNCTIONAL

CHECKLIST

ATTACHMENT B: MODULAR INDOOR CENTRAL STATION AIR HANDLING

UNIT FUNCTIONAL PERFORMANCE TEST

ATTACHMENT C: TERMINAL UNIT – HOT WATER HEAT PREFUNCTIONAL

CHECKLIST

ATTACHMENT D: VAV WITH REHEAT FUNCTIONAL PERFORMANCE TEST

ATTACHMENT E: EXHAUST FAN PREFUNCTIONAL CHECKLIST

SPECIFICATIONS TABLE OF CONTENTS Page 4

ATTACHMENT F: EXHAUST FAN FUNCTIONAL PERFORMANCE TEST

23 05 15 COMMON PIPING FOR HVAC

23 05 48.19 BRACING FOR HVAC AND PLUMBING

23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC

ATTACHMENT A: TESTING, ADJUSTING AND BALANCING PREFUNCTIONAL

CHECKLIST

23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS

23 09 00 INSTRUMENTATION AND CONTROL FOR HVAC

ATTACHMENT A: BUILDING AUTOMATION SYSTEM FUNCTIONAL

PERFORMANCE TEST

23 09 13 INSTRUMENTATION AND CONTROL DEVICES FOR HVAC

23 09 23.02 BACNET DIRECT DIGITAL CONTROL FOR HVAC AND OTHER BUILDING

CONTROL SYSTEMS

23 11 25 FACILITY GAS PIPING

23 21 13.00 20 LOW TEMPERATURE WATER (LTW) HEATING SYSTEM

23 22 26.00 20 STEAM SYSTEM AND TERMINAL UNITS

23 64 26 CHILLED, CHILLED-HOT, AND CONDENSER WATER PIPING SYSTEMS

VOLUME 3: DIVISIONS 26 – 33

DIVISION 26 - ELECTRICAL

26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS

26 05 48.00 10 SEISMIC PROTECTION FOR ELECTRICAL EQUIPMENT

26 20 00 INTERIOR DISTRIBUTION SYSTEM

26 29 23 VARIABLE FREQUENCY DRIVE SYSTEMS UNDER 600 VOLTS

26 51 00 INTERIOR LIGHTING

ATTACHMENT A: PREFUNCATIONAL CHECKLIST

ATTACHMENT B: FUNCTIONAL PERFORMANCE TEST

26 53 00.00 40 EXIT SIGNS

DIVISION 27 - COMMUNICATIONS

27 05 14.00 10 CABLE TELEVISION PREMISES DISTRIBUTION SYSTEM

27 05 28.36 40 CABLE TRAYS FOR COMMUNICATIONS SYSTEMS

27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM

27 13 23.00 40 COMMUNICATIONS OPTICAL BACKBONE CABLING

27 21 00.00 20 INTERCOMMUNICATION SYSTEM

27 51 16 PUBLIC ADDRESS AND SOUND MASKING SYSTEMS

27 52 24 NURSE CALL SYSTEM

DIVISION 28 - ELECTRONIC SAFETY AND SECURITY

28 05 26.00 40 GROUNDING AND BONDING FOR ELECTRONIC SAFETY AND SECURITY

28 08 10 ELECTRONIC SECURITY SYSTEM ACCEPTANCE TESTING

28 10 05 ELECTRONIC SECURITY SYSTEMS (ESS)

28 31 76 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM

DIVISION 31 - EARTHWORK

31 00 00 EARTHWORK

ATTACHMENT: GEOTECHNICAL REPORT

DIVISION 32 - EXTERIOR IMPROVEMENTS

32 16 19 CONCRETE CURBS, GUTTERS AND SIDEWALKS

32 92 19 SEEDING

SPECIFICATIONS TABLE OF CONTENTS Page 5

DIVISION 33 - UTILITIES

33 46 16 SUBDRAINAGE PIPING

33 71 01.00 40 OVERHEAD TRANSMISSION AND DISTRIBUTION

33 71 02 UNDERGROUND ELECTRICAL DISTRUBITION

-- End of Project Table of Contents --

FY 19 Hospital Modernization, Misawa AB, Japan Issued for Construction

SECTION 21 13 18.00 10

PREACTION AND DELUGE SPRINKLER SYSTEMS, FIRE PROTECTION

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

Refer to Specification Section 01 42 00.00 33 JIS ACCEPTABLE ALTERNATIVES for a listing of Japanese standards which are considered acceptable alternatives to the listed US standards. Japanese standards not included in this list or not referenced elsewhere in these specifications as being acceptable alternatives to US standards may be submitted to the Contracting Officer's Representative for approval as acceptable alternatives. Prior to the use of such Japanese standards, written approval by the Contracting Officer's Representative is required. See part 2.2 Mandatory U.S. Products in Specification Section 01 42 00.00 33 JIS ACCEPTABLE ALTERNATIVES for a list of products and materials that must meet US standards and be procured from the U.S.

ASME INTERNATIONAL (ASME)

ASME B16.1 (2015) Gray Iron Pipe Flanges and Flanged Fittings Classes 25, 125, and 250

ASME B16.11 (2016) Forged Fittings, Socket-Welding and Threaded

ASME B16.21 (2016) Nonmetallic Flat Gaskets for Pipe Flanges

ASME B16.3 (2016) Malleable Iron Threaded Fittings, Classes 150 and 300

ASME B16.4 (2011) Standard for Gray Iron Threaded Fittings; Classes 125 and 250

ASME B16.9 (2018) Factory-Made Wrought Steel Buttwelding Fittings

ASME B18.2.2 (2015) Nuts for General Applications:

Machine Screw Nuts, Hex, Square, Hex Flange, and Coupling Nuts (Inch Series)

ASTM INTERNATIONAL (ASTM)

ASTM A135/A135M (2009; R2014) Standard Specification for Electric-Resistance-Welded Steel Pipe

ASTM A183 (2014) Standard Specification for Carbon Steel Track Bolts and Nuts

SECTION 21 13 18.00 10 Page 1

ASTM A449 (2014) Standard Specification for Hex Cap Screws, Bolts, and Studs, Steel, Heat Treated, 120/105/90 ksi Minimum Tensile Strength, General Use

ASTM A47/A47M (1999; R 2018; E 2018) Standard Specification for Ferritic Malleable Iron Castings

ASTM A53/A53M (2018) Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded and Seamless

ASTM A536 (1984; R 2014) Standard Specification for Ductile Iron Castings

ASTM A795/A795M (2013) Standard Specification for Black and Hot-Dipped Zinc-Coated (Galvanized) Welded and Seamless Steel Pipe for Fire Protection Use

ASTM F436M (2011) Hardened Steel Washers (Metric)

FM GLOBAL (FM)

FM APP GUIDE (updated on-line) Approval Guide http://www.approvalguide.com/

INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE)

IEEE C62.41.1 (2002; R 2008) Guide on the Surges Environment in Low-Voltage (1000 V and Less) AC Power Circuits

IEEE C62.41.2 (2002) Recommended Practice on Characterization of Surges in Low-Voltage (1000 V and Less) AC Power Circuits

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 101 (2018; TIA 18-1; TIA 18-2; TIA 18-3) Life Safety Code

NFPA 13 (2016; TIA 16-1; TIA 16-2; TIA 16-3 2016;

Errata 17-1; Errata 17-2) Standard for the Installation of Sprinkler Systems

NFPA 13D (2016) Standard for the Installation of Sprinkler Systems in One- and Two-Family Dwellings and Manufactured Homes

NFPA 13R (2013) Standard for the Installation of Sprinkler Systems in Residential Occupancies Up to and Including Four Stories in Height

NFPA 24 (2016; ERTA 2016) Standard for the Installation of Private Fire Service Mains and Their Appurtenances

SECTION 21 13 18.00 10 Page 2

NFPA 70 (2017; ERTA 1-2 2017; TIA 17-1; TIA 17-2;

TIA 17-3; TIA 17-4; TIA 17-5; TIA 17-6;

TIA 17-7; TIA 17-8; TIA 17-9; TIA 17-10;

TIA 17-11; TIA 17-12; TIA 17-13; TIA

17-14; TIA 17-15; TIA 17-16; TIA 17-17 )

National Electrical Code

NFPA 72 (2016; Errata 1 2018) National Fire Alarm and Signaling Code

NATIONAL INSTITUTE FOR CERTIFICATION IN ENGINEERING TECHNOLOGIES

(NICET)

NICET 1014-7 (2012) Program Detail Manual for Certification in the Field of Fire Protection Engineering Technology (Field Code 003) Subfield of Automatic Sprinkler System Layout

U.S. DEPARTMENT OF DEFENSE (DOD)

UFC 3-310-04 (2013; with Change 1) Seismic Design of Buildings

UNDERWRITERS LABORATORIES (UL)

UL Fire Prot Dir (2012) Fire Protection Equipment Directory

1.2 SYSTEM DESCRIPTION

a. Furnish piping offsets, fittings, and any other accessories as required to provide a complete installation and to eliminate interference with other construction. Install sprinkler over and under ducts, piping and platforms when such equipment can negatively affect or disrupt the sprinkler discharge pattern and coverage.

b. Modify preaction sprinkler system(s) in areas indicated on the drawings .

The sprinkler system shall provide fire sprinkler protection for the entire area. Except as modified herein, the system shall meet the requirements of NFPA 13 and NFPA 72 .

c. Design any portions of the sprinkler system that are not indicated on the drawings or are not specified herein, including locating sprinklers, piping, and equipment, and size piping and equipment.

Determine pipe sizes which are not indicated on the drawings by hydraulic calculations.

1.2.1 Hydraulic Design

Hydraulically design the system to discharge a minimum density of 0.20 over the hydraulically most demanding of floor area. The minimum pipe size for branch lines in gridded systems shall be 32 mm. Hydraulic calculations shall be in accordance with the Area/Density Method of NFPA 13 .

Water velocity in the piping shall not exceed 6 m/s.

1.2.1.1 Basis for Calculations

Obtain a new fire pump test performed per NFPA 20 and 25 and base design of

SECTION 21 13 18.00 10 Page 3 the sprinkler system on the water supply provided at the discharge flange of the fire pump. Base hydraulic calculations upon the Hazen-Williams formula with a "C" value of 120 for all new steel piping, 140 for new cement-lined ductile-iron piping, and 100 for existing underground piping.

a. Outline hydraulic calculations as in NFPA 13 , except that calculations shall be performed by computer using software intended specifically for fire protection system design using the design data shown on the drawings. Submit hydraulic calculations, including a drawing showing hydraulic reference points and pipe segments. Software that uses k-factors for typical branch lines is not acceptable. Calculations shall substantiate that the design area used in the calculations is the most demanding hydraulically.

b. Plot water supply curves and system requirements on semi-logarithmic graph paper so as to present a summary of the complete hydraulic calculation. Provide a summary sheet listing sprinklers in the design area and their respective hydraulic reference points, elevations, actual discharge pressures and actual flows. Indicate elevations of hydraulic reference points (nodes). Documentation shall identify each pipe individually and the nodes connected thereto. Indicate for each pipe the diameter, length, flow, velocity, friction loss, number and type fittings, total friction loss in the pipe, equivalent pipe length and Hazen-Williams coefficient.

c. For gridded systems, calculations shall show peaking of demand area friction loss to verify that the hydraulically most demanding area is being used. Also for gridded systems, include a flow diagram indicating the quantity and direction of flows. A drawing showing hydraulic reference points (nodes) and pipe designations used in the calculations shall be included and shall be independent of shop drawings.

1.2.2 Sprinkler Coverage

Uniformly space sprinklers on branch lines. In buildings protected by automatic sprinklers, provide coverage throughout 100 percent of the building. This includes, but is not limited to, telephone rooms, electrical equipment rooms, boiler rooms, switchgear rooms, transformer rooms, and other electrical and mechanical spaces. Coverage per sprinkler shall be in accordance with NFPA 13 , but shall not exceed 9 square m for extra hazard occupancies, 12 square m for ordinary hazard occupancies, and 21 square m for light hazard occupancies. Exceptions are as follows:

a. Facilities that are designed in accordance with NFPA 13R and NFPA 13D.

b. Sprinklers may be omitted from small rooms which are exempted for specific occupancies in accordance with NFPA 101 .

1.2.3 Control System

The control system shall meet the requirements of NFPA 72 . The control panel shall be listed in UL Fire Prot Dir or FM APP GUIDE for "Releasing Device Service". The control panel and the solenoid valve that activates the water control valves shall be compatible with each other.

Compatibility shall be in accordance with specific UL listing or FM approval of the control equipment.

SECTION 21 13 18.00 10 Page 4

1.2.3.1 Power Supply

Provide the primary operating power from two single-phase 120 VAC circuits. Transfer from normal to backup power and restoration from backup to normal power shall be fully automatic and shall not initiate a false alarm. Loss of primary power shall not prevent actuation of the respective automatic water control valve upon activation of any alarm initiating device. Provide backup power through use of rechargeable, sealed, lead calcium storage batteries.

1.2.3.2 Circuit Requirements

Connect alarm initiating devices to initiating device circuits (IDC), Style D or to signal line circuits (SLC), Style 6 , in accordance with NFPA 72 .

Alarm notification or indicating appliances shall be connected to indicating appliance circuit (IAC), Style W in accordance with NFPA 72 .

Provide a separate circuit for actuation of each individual automatic water control valve. Fully supervise the circuits that actuate the water control valves so that the occurrence of a single open or a single ground fault condition in the interconnecting conductors will be indicated at the control panel.

1.2.4 System Operational Features

Include in the system a heat detection system, manual actuation stations, supervisory and alarm switches, alarm notification appliances, control panel and associated equipment. Provide preaction sprinkler system piping with supervisory air pressure not to exceed 210 kPa.

1.2.4.1 System Actuation

Activation of any single heat detector or a single manual actuation station shall actuate alarm zone circuits of the control panel that, in turn, shall actuate the corresponding automatic water control valve. Actuation of the automatic water control valve shall cause water to fill the preaction system piping and be discharged from fused sprinklers .

1.2.4.2 Alarm Functions

Activation of any heat detector or sprinkler pressure alarm switch or manual actuation station shall cause the illumination of the respective zone annunciator, and transmission of the alarm to the base-wide fire reporting system. Valve tamper alarm shall be monitored by the system control panel and transmitted to the building fire alarm system as a trouble alarm.

1.2.4.3 Supervisory Functions

The reduction of supervisory air pressure within the sprinkler system piping to less than 70 kPa or the occurrence of a single open or a single ground fault in any alarm initiating device circuit, in the automatic water control valve actuation circuit, in any alarm indicating appliance circuit or in other electrically supervised circuit shall cause the individually labelled control panel trouble light to be illuminated, the audible trouble alarm to be activated, and a trouble alarm to be transmitted to the building fire alarm control panel and to base-wide fire reporting system.

SECTION 21 13 18.00 10 Page 5

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00

SUBMITTAL PROCEDURES:

SD-02 Shop Drawings

Shop Drawings; G

As-Built Drawings

SD-03 Product Data

Fire Protection Specialist; G

Installer Qualifications

List of Submittals

Materials and Equipment; G

Spare Parts

OnSite Training; G

SD-05 Design Data

Sway Bracing; G

Hydraulic Calculations; G

Storage Batteries; G

SD-06 Test Reports

Preliminary Tests; G

Final Acceptance Tests

SD-07 Certificates

Inspection by Fire Protection Specialist; G

SD-10 Operation and Maintenance Data

Operating and Maintenance Instructions; G

1.4 QUALITY ASSURANCE

Compliance with referenced NFPA standards is mandatory. Applicable material and installation standards referenced in Appendix A of NFPA 13 and NFPA 24 shall be considered mandatory the same as if such referenced standards were specifically listed in this specification. In the event of a conflict between specific provisions of this specification and applicable NFPA standards, this specification governs. Incorporate all requirements that exceed the minimum requirements of NFPA 13 into the design. Interpret reference to "authority having jurisdiction" to mean the Contracting

SECTION 21 13 18.00 10 Page 6

Officer.

1.4.1 Fire Protection Specialist

Perform the work specified in this section under the supervision of and certified by the Fire Protection Specialist (FPS) who is a registered professional engineer and a Full Member of the Society of Fire Protection Engineers or who is certified as a Level III Technician by National Institute for Certification in Engineering Technologies (NICET) in the Automatic Sprinkler System Layout subfield of Fire Protection Engineering Technology in accordance with NICET 1014-7 . Submit the name and documentation of certification of the proposed FPS, no later than 14 days after the Notice to Proceed and prior to the submittal of the sprinkler system shop drawings and hydraulic calculations. The FPS shall prepare and submit a list of submittals, related to fire protection, from the Contract Submittal Register that relate to the successful installation of the sprinkler systems(s), no later than 7 days after the approval of the FPS.

The submittals identified on this list shall be accompanied by a letter of approval signed and dated by the FPS when submitted to the Government. The FPS shall be regularly engaged in the design and installation of the type and complexity of system specified in the Contract documents, and shall have served in a similar capacity for at least three systems that have performed in the manner intended for a period of not less than 6 months.

1.4.2 Installer Qualifications

Work specified in this section shall be performed by the Sprinkler System Installer. Submit the name and documentation of certification of the proposed Sprinkler System Installer, concurrent with submittal of the FPS Qualifications. The Installer shall be regularly engaged in the installation of the type and complexity of system specified in the Contract documents, and shall have served in a similar capacity for at least three systems that have performed in the manner intended for a period of not less than 6 months.

1.4.3 Shop Drawings

Submit 3 copies of the Sprinkler System Drawings, on reproducible full-size mylar film, no later than 21 days prior to the start of sprinkler system installation. The drawings shall conform to the requirements established for working plans as prescribed in NFPA 13 . Drawings shall include plan and elevation views demonstrating that the equipment will fit the allotted spaces with clearance for installation and maintenance. Update the Shop Drawings to reflect as-built conditions after all related work is completed. Each set of drawings shall include the following:

a. Descriptive index of drawings in the submittal with drawings listed in sequence by drawing number. A legend identifying device symbols, nomenclature, and conventions used.

b. Floor plans drawn to a scale not less than 1:100 which clearly show locations of sprinklers, risers, pipe hangers, seismic separation assemblies, sway bracing, inspector's test connections, drains, and other applicable details necessary to clearly describe the proposed arrangement. Indicate each type of fitting used and the locations of bushings, reducing couplings, and welded joints.

c. Actual center-to-center dimensions between sprinklers on branch lines and between branch lines; from end sprinklers to adjacent walls; from

SECTION 21 13 18.00 10 Page 7 walls to branch lines; from sprinkler feed mains, cross-mains and branch lines to finished floor and roof or ceiling. A detail shall show the dimension from the sprinkler and sprinkler deflector to the ceiling in finished areas.

d. Longitudinal and transverse building sections showing typical branch line and cross-main pipe routing as well as elevation of each typical sprinkler above finished floor.

e. Details of each type of riser assembly; pipe hanger; sway bracing for earthquake protection, and restraint of underground water main at point-of-entry into the building, and electrical devices and interconnecting wiring.

f. Complete point-to-point wiring diagram of the detection and control system. Indicate the detailed interconnection of control panel modules to the devices, the number and size of conductors in each conduit, and size of conduit. Connection points shall be indicated and coordinated with the terminal identification marked on the devices. Provide complete internal wiring schematic of the control panel and each electrical device. Detailed description of the functions of the control panel and each module shall be provided.

1.5 DELIVERY, STORAGE, AND HANDLING

All equipment delivered and placed in storage shall be housed in a manner to preclude any damage from the weather, humidity and temperature variations, dirt and dust, or other contaminants. Additionally, all pipes shall either be capped or plugged until installed.

1.6 EXTRA MATERIALS

Submit spare parts data for each different item of material and equipment specified. The data shall include a complete list of parts and supplies, with current unit prices and source of supply, and a list of parts recommended by the manufacturer to be replaced after 1 year and 3 years of service. Include alist of special tools and test equipment required for maintenance and testing of the products supplied.

PART 2 PRODUCTS

2.1 STANDARD PRODUCTS

Provide materials and equipment which are standard products of a manufacturer regularly engaged in the manufacture of such products and that essentially duplicate items that have been in satisfactory use for at least 2 years prior to bid opening. Submit manufacturer's catalog data included with the Sprinkler System Drawings for all items specified herein.

Highlight the data to show model, size, options, etc., that are intended for consideration. Data shall be adequate to demonstrate compliance with all contract requirements. In addition, provide a complete equipment list that includes equipment description, model number and quantity.

2.2 NAMEPLATES

All equipment shall have a nameplate that identifies the manufacturer's name, address, type or style, model or serial number, and catalog number.

SECTION 21 13 18.00 10 Page 8

2.3 REQUIREMENTS FOR FIRE PROTECTION SERVICE

Materials and equipment shall have been tested by Underwriters Laboratories, Inc. and listed in UL Fire Prot Dir or approved by Factory Mutual and listed in FM APP GUIDE. Where the terms "listed" or "approved" appear in this specification, such shall mean listed in UL Fire Prot Dir or

FM APP GUIDE.

2.4 ABOVEGROUND PIPING COMPONENTS

2.4.1 Steel Pipe

Except as modified herein, steel pipe shall be black as permitted by NFPA 13 and shall conform to applicable provisions of ASTM A795/A795M , ASTM A53/A53M, or ASTM A135/A135M . Pipe in which threads or grooves are cut or rolled formed shall be Schedule 40 or shall be listed by Underwriters' Laboratories to have a corrosion resistance ratio (CRR) of

1.0 or greater after threads or grooves are cut or rolled formed. Pipe shall be marked with the name of the manufacturer, kind of pipe, and ASTM designation.

2.4.2 Fittings for Non-Grooved Steel Pipe

Fittings shall be cast iron conforming to ASME B16.4 , steel conforming to ASME B16.9 or ASME B16.11 , or malleable iron conforming to ASME B16.3 .

Fittings into which sprinklers, drop nipples or riser nipples (sprigs) are screwed shall be threaded type. Plain-end fittings with mechanical couplings, fittings that use steel gripping devices to bite into the pipe and segmented welded fittings shall not be used.

2.4.3 Grooved Mechanical Joints and Fittings

Joints and fittings shall be designed for not less than 1200 kPa service and shall be the product of the same manufacturer; segmented welded fittings shall not be used. Fitting and coupling houses shall be malleable iron conforming to ASTM A47/A47M, Grade 32510; ductile iron conforming to ASTM A536, Grade 65-45-12. Gaskets shall be of silicon compound and approved for dry fire protection systems. Gasket shall be the flush type that fills the entire cavity between the fitting and the pipe. Nuts and bolts shall be heat-treated steel conforming to ASTM A183 and shall be cadmium plated or zinc electroplated.

2.4.4 Flanges

Flanges shall conform to NFPA 13 and ASME B16.1 . Gaskets shall be non-asbestos compressed material in accordance with ASME B16.21 , 1.6 mm thick, and full face or self-centering flat ring type.

2.4.4.1 Bolts

Bolts shall be ASTM A449, Type 1. Bolts shall extend no less than three full threads beyond the nut with bolts tightened to the required torque.

2.4.4.2 Nuts

Nuts shall be hexagon type conforming to ASME B18.2.2 .

SECTION 21 13 18.00 10 Page 9

2.4.4.3 Washers

Washers shall meet the requirements of ASTM F436M. Flat circular washers shall be provided under all bolt heads and nuts.

2.4.5 Pipe Hangers

Hangers shall be listed in UL Fire Prot Dir or FM APP GUIDE and of the type suitable for the application, construction, and pipe type and size to be supported.

2.5 SPRINKLERS

Sprinklers for preaction systems shall be automatic, fusible solder or glass bulb type; sprinklers for deluge systems shall be open type without the fusible element. Sprinklers with internal O-rings shall not be used.

Sprinklers shall be used in accordance with their listed coverage limitations. Temperature classification shall be ordinary . Sprinklers in high heat areas including attic spaces or in close proximity to unit heaters shall have temperature classification in accordance with NFPA 13 .

Extended coverage sprinklers shall not be used.

2.5.1 Pendent Sprinkler

Pendent sprinkler shall be of the fusible strut or glass bulb type, recessed quick-response type with nominal 13 mm orifice. Pendent sprinklers shall have a polished chrome finish.

2.5.2 Upright Sprinkler

Upright sprinkler shall be brass quick-response type and shall have a nominal 13 mm orifice.

2.5.3 Corrosion Resistant Sprinkler

Corrosion resistant sprinkler shall be in locations as indicated.

Corrosion resistant coatings shall be factory-applied by the sprinkler manufacturer.

2.6 ACCESSORIES

2.6.1 Sprinkler Cabinet

Spare sprinklers shall be provided in accordance with NFPA 13 and shall be packed in a suitable metal or plastic cabinet. Spare sprinklers shall be representative of, and in proportion to, the number of each type and temperature rating of the sprinklers installed. At least one wrench of each type required shall be provided.

2.6.2 Pendent Sprinkler Escutcheon

Escutcheon shall be one-piece metallic type with a depth of less than 19 mm and suitable for installation on pendent sprinklers. The escutcheon shall have a factory finish that matches the pendent sprinkler heads.

2.6.3 Pipe Escutcheon

Escutcheon shall be polished chromium-plated zinc alloy, or polished chromium-plated copper alloy. Escutcheons shall be either one-piece or

SECTION 21 13 18.00 10 Page 10 split-pattern, held in place by internal spring tension or set screw.

2.6.4 Sprinkler Guard

Guard shall be a steel wire cage designed to encase the sprinkler and protect it from mechanical damage. Guards shall be provided on sprinklers located as indicated.

2.6.5 Identification Sign

Valve identification sign shall be minimum 150 mm wide by 50 mm high with enamel baked finish on minimum 1.214 mm steel or 0.6 mm aluminum with red letters on a white background or white letters on red background. Wording of sign shall include, but not be limited to "main drain," "auxiliary drain," "inspector's test," "alarm test," "alarm line," and similar wording as required to identify operational components.

2.7 CONTROL PANEL

Panel shall be UL listed or FM approved for "Releasing Device Service" or shall have modules approved for this purpose. Panel shall contain all components and equipment required to provide the specified operational and supervisory functions of the system. House components in a surface -mounted steel cabinet with hinged door and cylinder lock. Control panel shall be a clean, uncluttered, and orderly factory assembled and wired unit. Panel shall include integral "power on," "alarm," and "trouble" lamps with annunciation of each alarm, supervisory and trouble signal. The panel shall have prominent rigid plastic or metal identification plates for lamps, zones, controls, meters, fuses, and switches. Nameplates for fuses shall also include ampere rating. Control panel switches shall be within the locked cabinet. Provide a suitable means for testing the working condition and accuracy of the control panel visual indicating devices (meter and lamps). Meters and lamps shall be plainly visible when the cabinet door is closed. Signals shall be provided to indicate by zone any alarm, supervisory or trouble condition on the system. Upon restoration of power, startup shall be automatic, and shall not require any manual operation. The loss of primary power or the sequence of applying primary or emergency power shall not affect the transmission of alarm, supervisory or trouble signals.

2.7.1 Zone Annunciator

Provide a separate alarm and trouble lamp for each active and spare zone located on exterior of cabinet door or visible through the cabinet door. A minimum of two spare alarm zones that are fully operational shall be provided. Each lamp shall provide specific identification of the zone by means of a permanently attached rigid plastic or metal sign with either raised or engraved letters. Zone identification shall consist of a unique zone number as well as a word description of the zone.

2.7.2 Primary Power Supply

Primary power and trouble alarm power to the Control Panel shall be supplied from two 120 VAC circuits. Power to the control panel shall be as indicated.

2.7.3 Emergency Power Supply

Emergency power shall be provided for system operation in the event of

SECTION 21 13 18.00 10 Page 11 failure of the primary power supply and shall consist of rechargeable storage battery system. Transfer from normal to emergency power or restoration from emergency to normal power shall be automatic and shall not cause transmission of a false alarm.

2.7.3.1 Storage Batteries

Storage Batteries shall be sealed, lead-calcium type requiring no additional water. Submit calculations to substantiate the total requirements for supervisory and alarm power. Include ampere-hour requirements for each system component and each control panel component or module, under both normal and alarm conditions. The battery recharging period shall be included with the calculations. The batteries shall have ample capacity, with primary power disconnected, to operate the system for a period of 90 hours. Following this period of operation via batteries, the batteries shall have ample capacity to operate all alarm indicating devices in the alarm mode for a minimum period of 15 minutes. Battery cabinet shall be a separate compartment at the bottom of the control panel .

The battery cabinet shall have adequate space for spare duplicate storage batteries. Batteries shall be mounted on a noncorrosive and nonconductive base or pad.

2.7.3.2 Battery Charger

Battery charger shall be completely automatic, with high/low charging rate, capable of restoring the batteries from full discharge to full charge within 12 hours using the high charging rate. A separate ammeter shall be provided for indicating rate of charge. A separate voltmeter shall be provided to indicate the state of the battery charge. A pilot light indicating when batteries are manually placed on a high rate of charge shall be provided as part of the unit assembly. The charger shall be located in control panel cabinet.

2.8 ALARM INITIATING DEVICES

2.8.1 Heat Detectors

Detectors located in areas subject to moisture, exterior atmospheric conditions or hazardous locations as defined in NFPA 70 shall be approved for such locations. Detectors shall be listed or approved for 15 m spacing between detectors. The detector shall be equipped with an alarm indicating light in its base that lights when the detector is in an alarm condition.

Five spare detectors of each type and temperature rating shall be provided.

2.8.1.1 Rate Compensation Detector

Detector shall be of the vertical spot type with a temperature classification rating of ordinary as defined by NFPA 72 . Detectors listed or approved as "rate anticipation" type will be accepted. Detector shall automatically reset when temperature drops below detector temperature rating. Detector shall be hermetically sealed.

2.8.1.2 Fixed-Temperature and Rate-of-Rise Heat Detector

Detector shall consist of two independently operated thermal elements. The rate-of-rise portion of the detector shall consist of an air chamber, flexible metal diaphragm and a moisture-proof calibrated vent which will respond to a temperature rise exceeding 8 degrees C per minute. This portion of the detector shall be self-restoring after actuation. The fixed

SECTION 21 13 18.00 10 Page 12 temperature portion of the detector shall consist of a fusible alloy that will melt and cause an alarm when the surrounding air rises above the temperature rating of the detector. The detector shall provide an external indication when the fixed temperature portion of the detector actuates.

Detector shall have a temperature classification rating of ordinary as defined by NFPA 72 .

2.8.1.3 Fixed-Temperature Heat Detector

Detector shall have a fusible alloy that will melt and cause an alarm when the surrounding air rises above the temperature rating of the detector.

The detector shall provide an external indication upon actuation of the detector. Detector shall provide a temperature classification rating of ordinary as defined by NFPA 72 .

2.8.2 Sprinkler Pressure Alarm Switch

Pressure switch shall include a metal housing with a neoprene diaphragm, SPDT snap action switches. The switch shall have a service pressure rating of 1200 kPa. There shall be two SPDT (Form C) contacts factory adjusted to operate at 30 to 60 kPa. The switch shall be capable of being mounted in any position in the alarm line trim piping of the alarm check valve.

2.8.3 Waterflow Alarm

Electrically operated, exterior-mounted, waterflow alarm bell shall be provided and installed in accordance with NFPA 13 . Waterflow alarm bell shall be rated 24 VDC and shall be connected to the Fire Alarm Control Panel (FACP) in accordance with Section 28 31 76 INTERIOR FIRE ALARM AND

MASS NOTIFICATION SYSTEM.

2.8.4 Valve Supervisory (Tamper) Switch

Switch shall be suitable for mounting to the type of control valve to be supervised open. The switch shall be tamper resistant and contain one set of SPDT (Form C) contacts arranged to transfer upon removal of the housing cover or closure of the valve of more than two rotations of the valve stem.

2.9 NOTIFICATION APPLIANCES

Notification appliances shall be suitable for connection to supervised alarm indicating circuits. Appliance shall have a separate screw terminal for each conductor. The surface of the appliance shall be red in color.

2.9.1 Alarm Bell

Bell shall be 250 mm diameter, surface-mounted vibrating type with matching back box. Sound output shall be a minimum of 85 DBA at 3000 mm. Bell shall operate on nominal 24 VDC. Bells shall have screw terminals for in-out wiring connection. Bells used in exterior locations shall be specifically listed or approved for outdoor use and be provided with metal housing and protective grilles.

2.9.2 Alarm Horn

Horn shall be surface mounted, with the matching mounting back box surface mounted vibrating type suitable for use in an electrically supervised circuit. Horns shall operate on nominal 24 VDC and have screw terminals for in-out wiring connection. Sound output shall be a minimum of 85 DBA at

SECTION 21 13 18.00 10 Page 13

3000 mm. Horns used in exterior locations shall be specifically listed or approved for outdoor use and be provided with metal housing and protective grills.

2.10 WIRING

Wiring for alternating current (AC) circuits shall be 12 AWG minimum.

Wiring for low voltage direct current (DC) circuits shall be No. 16 AWG minimum. Power wiring (over 28 volts) and control wiring shall be isolated. Wiring shall conform to NFPA 70 . System field wiring shall be solid copper and installed in electrical metallic tubing or in metallic conduit, except rigid plastic conduit may be used under slab-on-grade.

Conductors shall be color coded. Conductors used for the same function shall be similarly color coded. Wiring color code shall remain uniform throughout the circuit. Pigtail or T-tap connections to alarm initiating, alarm indicating, supervisory, and actuation circuits are prohibited.

PART 3 EXECUTION

3.1 EXAMINATION

After becoming familiar with all details of the work, verify all dimensions in the field, and advise the Contracting Officer of any discrepancy before performing the work.

3.2 INSPECTION BY FIRE PROTECTION SPECIALIST

The Fire Protection Specialist shall inspect the sprinkler system periodically during the installation to assure that the sprinkler system installed in accordance with the contract requirements. The Fire Protection Specialist shall witness the preliminary and final tests, and shall sign the test results. The Fire Protection Specialist, after completion of the system inspections and a successful final test, shall certify in writing that the system has been installed in accordance with the contract requirements, including signed approval of the Preliminary, Detection and Control Systems, and Final Acceptance Test Reports. Any discrepancy shall be brought to the attention of the Contracting Officer in writing, no later than three working days after the discrepancy is discovered.

3.3 ABOVEGROUND PIPING INSTALLATION

3.3.1 Protection of Piping Against Earthquake Damage

Building is classified as Seismic Design Category "D".

For piping in the Dental Clinic area: Seismically protect the system piping against damage from earthquakes. This requirement is not subject to determination under NFPA 13 . Install the seismic protection of the system piping, including sway bracing as required, in accordance with UFC 3-310-04 , NFPA 13 and Annex A; submit load calculations for sizing of sway bracing for systems that are required to be protected against damage from earthquakes. Include the required features identified therein that are applicable to the specific piping system.

For any new piping in renovation areas outside the Dental Clinic area:

Match existing bracing.

SECTION 21 13 18.00 10 Page 14

3.3.2 Piping in Exposed Areas

Exposed piping shall be installed so as not diminish exit access widths, corridors, or equipment access. Exposed horizontal piping, including drain piping, shall be installed to provide maximum headroom.

3.3.3 Piping in Finished Areas

In areas with suspended or dropped ceilings and in areas with concealed spaces above the ceiling, piping shall be concealed above ceilings. Piping shall be inspected, tested and approved before being concealed. Risers and similar vertical runs of piping in finished areas shall be concealed.

3.3.4 Pendent Sprinklers Locations

Sprinklers installed in the pendent position shall be of the listed dry pendent type, unless otherwise indicated. Dry pendent sprinklers shall be of the required length to permit the sprinkler to be threaded directly into a branch line tee. Hangers shall be provided on arm-overs to drop nipples supplying pendent sprinklers when the arm-over exceeds 300 mm for steel pipe or 150 mm for copper tubing. Dry pendent sprinkler assemblies shall be such that sprinkler ceiling plates or escutcheons are of the uniform depth throughout the finished space. Pendent sprinklers in suspended ceilings shall be a minimum of 150 mm from ceiling grid. Recessed pendent sprinklers shall be installed such that the distance from the sprinkler deflector to the underside of the ceiling shall not exceed the manufacturer's listed range and shall be of uniform depth throughout the finished area.

3.3.5 Upright Sprinklers

Riser nipples or "sprigs" to upright sprinklers shall contain no fittings between the branch line tee and the reducing coupling at the sprinkler.

Riser nipples exceeding 750 mm in length shall be individually supported.

3.3.6 Pendent Sprinklers Locations

Sprinklers installed in the pendent position shall be of the listed dry pendent type, unless otherwise indicated. Dry pendent sprinklers shall be of the required length to permit the sprinkler to be threaded directly into a branch line tee. Hangers shall be provided on arm-overs exceeding 300 mm in length. Dry pendent sprinkler assemblies shall be such that sprinkler ceiling plates or escutcheons are of the uniform depth throughout the finished space. Pendent sprinklers in suspended ceilings shall be a minimum of 150 mm from ceiling grid. Recessed pendent sprinklers shall be installed such that the distance from the sprinkler deflector to the underside of the ceiling shall not exceed the manufacturer's listed range and shall be of uniform depth throughout the finished area.

3.3.7 Pipe Joints

Pipe joints shall conform to NFPA 13 , except as modified herein. Not more than four threads shall show after joint is made up. Welded joints will be permitted, only if welding operations are performed as required by NFPA 13 at the Contractor's fabrication shop, not at the project construction site. Flanged joints shall be provided where indicated or required by NFPA 13 . Grooved pipe and fittings shall be prepared in accordance with the manufacturer's latest published specification according to pipe material, wall thickness and size. Grooved couplings and fittings shall be

SECTION 21 13 18.00 10 Page 15 from the same manufacturer. Grooved joints shall not be used in concealed locations, such as behind solid walls or ceilings, unless an access panel is shown on the drawings for servicing or adjusting the joint.

3.3.8 Reducers

Reductions in pipe sizes shall be made with one-piece tapered reducing fittings. The use of grooved-end or rubber-gasketed reducing couplings will not be permitted. When standard fittings of the required size are not manufactured, single bushings of the face type will be permitted. Where used, face bushings shall be installed with the outer face flush with the face of the fitting opening being reduced. Bushings shall not be used in elbow fittings, in more than one outlet of a tee, in more than two outlets of a cross, or where the reduction in size is less than 13 mm.

3.3.9 Pipe Penetrations

Cutting structural members for passage of pipes or for pipe-hanger fastenings will not be permitted. Pipes that must penetrate concrete or masonry walls or concrete floors shall be core-drilled and provided with pipe sleeves. Each sleeve shall be Schedule 40 galvanized steel, ductile iron or cast iron pipe and shall extend through its respective wall or floor and be cut flush with each wall surface. Sleeves shall provide required clearance between the pipe and the sleeve in accordance with NFPA 13 . The space between the sleeve and the pipe shall be firmly packed with mineral wool insulation. Where pipes penetrate fire walls, fire partitions, or floors, pipes shall be fire stopped in accordance with Section 07 84 00 FIRESTOPPING. In penetrations that are not fire-rated or not a floor penetration, the space between the sleeve and the pipe shall be sealed at both ends with plastic waterproof cement that will dry to a firm but pliable mass or with a mechanically adjustable segmented elastomer seal.

3.3.10 Escutcheons

Escutcheons shall be provided for pipe penetration of ceilings and walls.

Escutcheons shall be securely fastened to the pipe at surfaces through which piping passes.

3.3.11 Inspector's Test Connection

Unless otherwise indicated, test connection shall consist of 25 mm pipe connected to the remote branch line ; a test valve located approximately 2 m above the floor; a smooth bore brass outlet equivalent to the smallest orifice sprinkler used in the system; and a painted metal identification sign affixed to the valve with the words "Inspector's Test." The discharge orifice shall be located outside the building wall directed so as not to cause damage to adjacent construction or landscaping during full flow discharge.

3.3.12 Drains

Provide main drain piping to discharge at a safe point outside the building .

Auxiliary drains shall be provided as indicated and as required by NFPA 13 .

When the capacity of trapped sections of pipe is less than 11 L, the auxiliary drain shall consist of a valve not smaller than 13 mm and a plug or nipple and cap. When the capacity of trapped sections of piping is more than 11 L, the auxiliary drain shall consist of two 25 mm valves and one 50 x 300 mm condensate nipple or equivalent, located in an accessible location. Tie-in drains shall be provided for multiple adjacent trapped

SECTION 21 13 18.00 10 Page 16 branch pipes and shall be a minimum of 25 mm in diameter. Tie-in drain lines shall be pitched a minimum of13 mm per 3 m.

3.3.13 Identification Signs

Signs shall be affixed to each control valve, inspector test valve, main drain, auxiliary drain, test valve, and similar valves as appropriate or as required by NFPA 13 . Hydraulic design data nameplates shall be permanently affixed to each sprinkler riser as specified in NFPA 13 .

3.4 ELECTRICAL WORK

Unless otherwise specified herein, power supply equipment and wiring shall be in accordance with Section 26 20 00 INTERIOR DISTRIBUTION SYSTEM.

3.4.1 Overcurrent and Surge Protection

All equipment connected to alternating current circuits shall be protected from surges in accordance with IEEE C62.41.1 , IEEE C62.41.2 and NFPA 70 .

Cables and conductors that serve as communications links, except fiber optics, shall have surge protection circuits…