DKGV 14-2085 Repair Electrical Distribution B.2 Area SOW.docx
DOCX document 30 KB Posted
- Attached to
- Repair Electrical Distribution System, B2 Area Federal contract opportunity
- Solicitation number
- FA441820R0008
About this file
This statement of work and federal contract opportunity outline requirements for a firm-fixed-price contract to repair an electrical distribution system at Joint Base Charleston - Weapons Station in Goose Creek, South Carolina. The contractor shall provide all labor, equipment, materials and supervision to complete project DKGV 14-2085, replacing overhead lines with new pad-mounted transformers and underground feeds, and upgrading facilities' internal wiring. Work shall follow provided design drawings and be scheduled to minimize operational impacts, with utility interruptions requiring three weeks' advance approval. The contractor must submit redlined and as-built drawings and progress schedules as specified. The performance period is 270 calendar days from notice to proceed. The pre-construction conference will be arranged through Civil Engineering, with John Gaudette serving as inspector and Lawrence Pearl as construction manager. The solicitation was issued by the Department of the Air Force Air Mobility Command, with responses due under solicitation FA441820R0008. A mandatory site visit is scheduled for May 6, 2020.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Proposal Submission Change Notice FA441820R0008 20200520.pdf | ||
| QA 2 B2 Area FA441820R0008 20200518.pdf | ||
| Questions - Electrical Distribution System B2 Area20200518.pdf | ||
| Questions from Grot 20200519.pdf | ||
| Q and A B2 Area FA441820R0008 20200513.pdf | ||
| FA441820R0008 Preproposal Site Visit Ktr Roster 20200506.pdf | ||
| DKGV 14-2085 Drawings.pdf | ||
| B1 and B2 Asbestos and Lead Based Paint Surveys.pdf | ||
| DKGV 14-2085 Submittal Register (AF Form 66).pdf | ||
| DKGV 142085 Green Procurement Form.pdf | ||
| SC20190022 Wage Determination.pdf | ||
| FA441820R0008 2020042803.pdf | ||
| DKGV 14-2085 B2 Specs 20200427.pdf |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
REPAIR ELECTRICAL DISTRIBUTION, B.2 AREA
Project: DKGV 14-2085
22 SEP 2019
1.0 INTRODUCTION/OVERVIEW
The scope of this project is to provide an overhead primary loop feeder through the area which will improve operational abilities for the facilities in this area. In addition, new pad-mounted transformers with underground primary feeds and new underground secondary services will remove a number of overhead primary and secondary runs and improve maintenance and safety on this portion of the system. Most of the small single-phase services will remain overhead and be fed from overhead single-phase transformers. Buildings with three-phase and single-phase services will be re-worked internally to eliminate the single-phase services. The amount of overhead secondary feeders will be significantly reduced.
2.0 REFERENCES
1. All current versions of references listed in the design documents shall apply.
2. Design drawings and specifications dated 22 August 2019 shall be provided by the government.
| 3.0 | REQUIREMENTS |
| 3.1 | TASKS |
1. All work shall follow detailed design drawings dated 22 Aug 2019.
2. Minor material and work not specifically mentioned herein, but necessary for the proper completion of the specified work, shall be furnished without additional cost to the government.
3. Unforeseen Major Repairs: Should deteriorated material of major nature be uncovered in the course of the work, it shall be brought to the attention of the Construction Manager. Repairs shall be made as directed by the Contracting Officer.
4. Scheduling of Work: Work shall be scheduled so as to cause minimum interference with the operations of the Government in the area involved. The Contractor shall notify the Government Construction Manager no less than one day in advance of the start work date and shall receive approval before proceeding. Normal work hours for this project are 0700-1600 hours. Weekend work will require written request and approval by the Government Construction Manager and the Contracting Officer.
5. Interruption of Utilities Service: Interruptions shall be kept to a minimum and shall be at such times and durations approved. No interruptions shall occur unless scheduled three weeks in advance with the Government Construction Manager. Planned interruptions shall normally occur outside regular working hours and require advance approval.
3.2 DELIVERABLES
1. Red-lined and as-built drawings shall be delivered at the end of the project as required in the specifications of the design documents. Red-lined drawings are design drawings that are maintained and updated with pen and ink changes throughout the duration of the contract. As-built drawings are a completely new set of drawings that reflect any and all pen and ink changes accumulated during the project.
2. Progress schedules shall be delivered as outlined in the specifications of the design documents.
3.3 SCHEDULE
1. The performance time for this project is 270 calendar days from notice to proceed.
4.0 MONITORING PROGRESS/COMPLIANCE
1. FINAL INSPECTION: Inspections shall be arranged through the Government Construction Manager at 843-794-7747 or Government Construction Inspector at 843-794-7726.
2. PRECONSTRUCTION CONFERENCE: Pre-con shall be arranged through the Civil Engineering CENMP Flight at 843-794-7747. John Gaudette is the Government Construction Inspector. Mr. Lawrence Pearl is the Government Construction Manager.
END OF STATEMENT
File details come from the government source that posted it. Updated .