This is a Pre-Bid Questions and Answers document from Applegate Group, Inc., the project engineer, for the Devil's Gate Station Cistern project (Solicitation #2019000094) in Clear Creek County, Colorado. The project involves construction of a water storage cistern system for water augmentation purposes at Devil's Gate Station. Key project parameters include a substantial completion deadline of May 1, 2019, with contract duration measured in calendar days at the contractor's discretion. Liquidated damages are assessed at $56 per day. The owner has already obtained the Flood Plain Development Permit and Driveway Permit from Clear Creek County, and no Army Corps of Engineers permit is required. The project includes installation of storage tanks with specific tie-down specifications (crossed ratchet straps with 15,000-pound minimum load rating connected to eye bolts and concrete anchors), construction of a new wire fence and gate matching existing site fencing, excavation and backfill work with Class 6 road base, pipe bedding requirements, electrical installation with owner-provided electrical drop and meter, and a custom wood door with specified hardware. The warranty period is one year after substantial completion, and prevailing wages do not apply to this project.

The document confirms that the contractor is responsible for soils and concrete testing, dewatering permits if required, tree removal and disposal, and provision of temporary restrooms for workers. The owner will provide survey control on site prior to construction. Excess excavation may be disposed of east of the existing parking lot at a location to be directed by the owner. No fire sprinkler system is required based on the structure's classification as Group U occupancy. The project includes specifications for a Class 2-A fire extinguisher and surface-mount cabinet. A bid bond is required with submission. All state building bid package documents, including the performance bond, labor and material bond, and general conditions, were provided as part of the addendum.

View the file

Other files

Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Water Resource Advisors for the West www.applegategroup.com Denver • Glenwood Springs • Hotchkiss (303) 452-6611

Memorandum

Date: November 28, 2018 AG Job No.: 14-135

To: Contractors From: Applegate Group, Inc.

RE: Responses for Devil’s Gate Cistern Project Pre-Bid Questions

Questions – Devil’s Gate Station Cistern Sol. # 2019000094

Please see the corresponding answer below each question in Italics.

1. Please provide bid bond form.

Bid bond form is attached.

2. What are the liquidated damages?

Liquidated damages are $56/day.

3. What is the warranty period?

One year after substantial completion.

4. Please confirm the Flood Plain Development Permit and the Driveway Permit have been obtained by the owner from Clear Creek County.

Correct these have been obtained by the owner.

5. Please confirm no permit is required from the Corps. of Engineers.

Correct, no permit is required from the Army Corps of Engineers as the project will not disturb area below the ordinary high-water mark which will be flagged by Applegate Group during the pre-construction meeting.

6. Please confirm water for the storage tanks is to be considered storage water and not potable water.

Correct, the water will solely be used to store water for water augmentation back to the river.

7. Please confirm no additional fire mitigation is required.

No additional fire mitigation is required on site as the main fire mitigation focus in this area is defensible space near property. No new flammable landscaping will be added.

8. Please confirm the new “electrical drop” will be provided by the owner.

Correct, the owner will provide the new electrical drop.

9. Please confirm the existing electrical panel will be used or upgraded by the owner.

Correct, the owner will oversee upgrading the electrical panel if necessary.

10. Please confirm if a new electrical meter is required it will be provided by the owner.

www.applegategroup.com 1490 West 121st Avenue, Suite 100

Denver, CO 80234

(303) 452-6611

Correct, a new electrical meter will be installed by HRA prior to contractor mobilization.

11. Is an Erosion Control Permit required from Clear Creek County?

The Driveway Permit, required by Clear Creek County, is the equivalent of an Erosion Control

Permit.

12. Please provide a detail/description for the storage tank tie downs.

The storage tank tie downs will consist of two crossed rachet straps with a minimum load rating of

15,000 pounds. The straps shall be connected to four eye bolts and anchored to the concrete. The swivel eye bold shall be attached to a steel plate capable of 6,000 pounds of loading. The concrete tensile strength needs to be considered as this is the weak factor in this set up. Here is an example of the swivel eye bolt:

13. Please confirm owner will provide survey control on the site for the contractor to utilize.

Correct, owner will provide survey control on site prior to construction.

14. Please confirm new fence will match the existing fence off the bridge and one gate is required.

Confirmed, a new fence and gate are required. The fence should be similar to the existing wire fence along the bank, and does not need to match the metal fence on the bridge.

15. Please confirm soils and concrete testing will be provided by the contractor.

Correct the soils and concrete testing will be provided by the contractor.

16. Please confirm prevailing wages do not apply.

Confirmed, prevailing wages do not apply.

17. How many contract days are allowed and will they be work days or calendar days?

(Advertisement has May 2018 completion and drawing 2 states April 20, 2018.)

Calendar days, dependent on contractor schedule. Substantial completion is required by May 1, 2019.

18. Is a dewatering permit required?

If required, a dewatering permit will be contractor’s responsibility.

19. Please confirm excess excavation can be disposed of “East” of the existing parking lot.

Confirmed, a location east of the parking lot to be directed by Owner/Operator.

(303) 452-6611

20. Please confirm we are to assume existing material can be excavated with a mid-sized excavator, and if undiggable rock is encountered it will be addressed with a change order.

Confirmed.

21. Please confirm CL. 6 Road base or other approved select backfill will be used to backfill below the new floor slab.

Correct, Class 6 road base or engineer-approved equivalent backfill shall be used below the new floor slab.

22. Please confirm pipe bedding is required.

Pipe bedding is required when encountering rock, hard pan, boulders or other materials that could damage the pipe. A minimum of 4’’ of squeegee bedding which consists of evenly graded, free flowing, granular material which is 3/8 inch minus in diameter shall be used.

23. Please confirm removed trees can be cut in lengths and left at the disposal site “East” of the parking lot. Can tops and limbs also be left at this site?

Confirmed, trees shall be cut in max 4 foot lengths, and disposed of by Contractor at a location east of the parking lot to be directed by Owner/Operator.

24. Please confirm existing restrooms on site can be used by the contractors’ workers.

No, Contractor shall provide their own restrooms.

25. Please provide state buildings bid package including bid bond form, information for bidders, agreement, Performance Bond, Labor and Material Bond and the General

Conditions.

State bid documents are attached to this addendum.

26. Please confirm a fire sprinkler system is not required.

According to the 2015 International Building Codes, Chapter 9 Section 3 – Fire Protection Systems, item 903.2.11 claims that “ in all occupancies other than Group U, an automatic sprinkler system shall be installed for building design or hazards…”. If this building is classified as Group U – Utility and Miscellaneous as this structure is not classified in any specific occupancy but note conform to the requires of this code commensurate with the fire and life hazard incidental to their occupancy. An incidental group is Storage Group S-2 enclosed parking garages, which calls for an automatic sprinkler system when the fire area of the enclosed parking garage exceeds 12,000 square feet or the enclosed parking garage is located beneath other groups, both of which are no applicable.

27. Electrical drawing E501 is blank – is this correct?

Electrical drawing E501 is the Fault Current calculations. This sheet is attached again for reference.

28. Please provide a specification for the wood door and door hardware.

The door is custom per details on A-301 and spec Devision 08 14 00

Hardware to be:

(303) 452-6611

• Cal-Royal pul203, solid bar round pull, ¾’’ diameter, 8’’ Ctc with 2-1/4’’ projection. US1OB

Antique Bronze Oiled Finish.

• Schlage B660613 Single Cylinder Deadbolt. US1OB Oil Rubbed Bronze finish.

• Ives Residential b453tb10b12 Steel 12” UL surface bolt (top and bottom). US10B Oil

Rubbed Bronze finish.

• Cal-Royal Bb-5200 4 ½” x 4 ½” full mortise, heavy weight, ball-bearing hinges. US10B

Antique Bronze oiled finish.

29. See Sheet E600, “typical disconnect name plate”: Is there a welder or is this just used as an example?

No, there is no welder, this is just an example.

30. See Sheet A-201, (4) west Elevation: Is the fire extinguisher cabinet included in this project? If so, please provide specifications.

Yes, specifications include:

• Uline Class 2-A Fire extinguisher. S-9873, 5lbs capacity.

• Uline Fire Extinguisher Cabinet. H-4871 surface mount cabinet.