This is a bid document introduction for a construction project involving History Colorado and the Georgetown Loop Railroad in Clear Creek County. The project involves constructing a water storage facility at the Devil's Gate Visitor's Center to augment potable water supply from an existing well and meet water rights augmentation requirements on Clear Creek. The scope of work includes constructing a new storage building with consistent architecture to the existing Visitor's Center that will house two 2,000-gallon storage cisterns, a self-priming centrifugal pump, flow meters, and related plumbing and electrical work. Additionally, contractors must install two parallel 4-inch diameter PVC pipes running from the new structure to a new headwall near Clear Creek, perform tree removal, implement sediment and erosion control measures, and complete site restoration. A mandatory site walk-through is scheduled for November 14, 2018, at 10:00 AM at Devil's Gate Station in Georgetown. Questions must be submitted by 4:00 PM on November 26, 2018, with answers posted by 4:00 PM on November 28, 2018. Bids are due by 2:00 PM on December 12, 2018, with project completion required by May 2019.
Contractors must demonstrate expertise in building, electrical, and environmental codes; building foundations; concrete forming; stamped and colored concrete; PVC piping; flow measurement meters; rock wall demolition; steel fencing; large tank installation; roofing; and erosion and sediment control. No pricing information, set-asides, incumbency details, or funding sources are specified in this introduction document.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SC6.21 CONTRACTORS AGREEMENT- DBB A .docx | DOCX document | |
| SC6.23DBB GENERAL CONDITONS.docx | DOCX document | |
| Electrical Stamped Drawings GLRR Cistern_Part1.pdf | ||
| Structural_18001 Devils Gate Cistern 2018-08-10r.pdf | ||
| SC622PerfBond.docx | DOCX document | |
| Civil_Georgetown Loop 8-13-18 a_Part1.pdf | ||
| NOTICE.docx | DOCX document | |
| 17.193 Georgetown Loop Visitor's Center Addition Report 12.08.17 (reduced file size).pdf | ||
| Electrical Stamped Drawings GLRR Cistern_Part2.pdf | ||
| Devil's Gate Cistern Bid Sheet_Oct 2018.pdf | ||
| Architectural_2018 0711 Devil's Gate Cistern_Part1.pdf | ||
| sbp-612_0 Information for Bidders.doc | DOC document | |
| SC6221LMBond.docx | DOCX document | |
| Devil's Gate Station Cistern Q and A.pdf | ||
| sbp-614 Bid Bond.docx | DOCX document | |
| sbp-613 BID.docx | DOCX document | |
| Civil_Georgetown Loop 8-13-18 a_Part2.pdf | ||
| Architectural_2018 0711 Devil's Gate Cistern_Part2.pdf |
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
2015-026P14/Devil's Gate Station Cistern Bid Document Intro
November 2018
History & Purpose History Colorado has operated the Georgetown Loop Railroad as a historic property since the 1970s. The property is a tourist attraction for Clear Creek County, and brings in visitors from all over that generate County-wide revenue. Water needs at the property include potable water use at the Devil’s Gate Visitor’s Center on the Georgetown side of the railroad. History Colorado uses an existing well to provide water for the restroom at the Visitor’s Center, and is in need of augmenting that use at certain times of year to prevent injury to other water rights on Clear Creek. Storage is needed at the Devil’s Gate Visitor’s Center to meet augmentation needs.
History Colorado plans to construct a storage cistern adjacent to the existing Visitor’s Center that will include two (2) 2,000 gallon storage cisterns in a new storage building to be constructed with architecture that is consistent with the existing Visitor’s Center building. The new structure will also house a self-priming centrifugal pump, flow meters, and related plumbing and electrical work. In addition, two parallel 4-inch diameter PVC pipes will run from the new structure to the new headwall located near Clear Creek. Contractor will be responsible for tree removal, sediment and erosion control, and site restoration.
There is a MANDATORY site walk through on Wednesday, November 14, 2018 at 10:00AM.
The meeting location is at Devil’s Gate Station/Georgetown Loop Railroad in Georgetown.
Questions regarding this solicitation must be submitted by 4:00 PM November 26, 2018.
Answers will be posted to Colorado Bids/VSS by 4:00 PM November 28, 2018.
Bids are due by 2:00 PM December 12, 2018.
Project needs to be completed by May 2019.
Required Contractor Skills
• Building, electrical and environmental codes; compliance with Colorado Office of State Architect’s building codes
• Building foundations
• Concrete forming
• Stamped and colored concrete
• PVC Piping
• Flow Measurement meters
• Rock wall demolition
• Steel fencing
• Large tank installation
• Roofing
• Erosion and sediment control