Copy_of_County_LD_Schedule_(Purchasing_Review_Only).xlsx

XLSX spreadsheet 30 KB Posted

Attached to
FY2025-2027 COUNTYWIDE PAVEMENT PRESERVATION - REBID
Solicitation number
25-0791-ITB-C
Issued by
Pinellas County, Florida

About this file

The document is a Liquidated Damages Calculator spreadsheet for Pinellas County's Countywide Pavement Preservation - Rebid project (PID No. 25-0791), covering fiscal years 2025-2027. The project involves roadway improvements, including traffic control, milling, resurfacing, and potential road base reconstruction across designated existing roadways. The construction duration is set at 540 calendar days, with an engineer's estimated construction cost of $23,500,000. The project aims to improve roadway conditions while accommodating traffic flow, pedestrian safety, and local business operations during construction.

The liquidated damages for the project are calculated at $1,434.66 per day of delay, based on various factors including construction administration fees, project management costs, and potential indirect expenses. The calculation methodology considers elements such as construction administration fees, daily staffing rates, and potential indirect costs like temporary facility expenses or lost revenues. The document provides a detailed breakdown of how liquidated damages are determined, emphasizing the need for a reasonable and well-documented approach to calculating potential project delays' financial impacts.

View the file

Other files

File Type Posted
FY2025-2027_COUNTYWIDE_PAVEMENT_PRESERVATION_-_REBID.pdf PDF
Affdavit_of_Release_and_Guarantee_0791.pdf PDF
Pricing_Proposal-25-0791(reference_only).pdf PDF
APPENDIX_7_-_SBE_COMPLIANCE_FORM.pdf PDF
Sample_Agreement-0791.pdf PDF
Sample_Change_Order.pdf PDF
Appendix_1-Permits.pdf PDF
Appendix_6-_Sample_Projects_For_Group_B.pdf PDF
Sample_Application_for_Payment.pdf PDF
38TH_AVE_HAINES_TO_4TH_ST_N_JOB_005687A_S.K._(Signed).pdf PDF
006297A_LG_87_S.K._Plans_(Signed).pdf PDF
005683A_LG_130_S.K._Plans_(Signed).pdf PDF
006303A_LG_107_S.K._Plans_(Signed).pdf PDF
006579A_LG_123_S.K._Plans_(Signed).pdf PDF
APPENDIX_4-Special_Notices_.pdf PDF
SBE_Compliance_Form.pdf PDF
Florida_Trench_Safety_Form.pdf PDF
QUALIFICATION_SUBMITTAL_FORM_8-25.pdf PDF
006767A_LG_211_S.K._Plans_(Signed).pdf PDF
006770A_LG_215_S.K._Plans_(Signed).pdf PDF
Klosteman_Rd_JOB_006577A_S.K._Plans_(Signed)_.pdf PDF
006309A_LG_122_S.K._Plans_(Signed).pdf PDF
006307A_LG_119_S.K._Plans_(Signed).pdf PDF
Specifications.pdf PDF
QUALIFICATION_SUBMITTAL_FORM.pdf PDF
Non-Competitive_Oversight_Committee_Justification_Form.docx DOCX document
OpenGov_Fillable-_Final.pdf PDF
Airport_Security_Program.pdf PDF
Performance_and_Payment_Bonds.pdf PDF
Affdavit_of_Release_and_Guarantee.pdf PDF
Bid_Submittal_Form-JOC.pdf PDF
E-Verify_Affidavit.pdf PDF
Show all 32

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Table

LIQUIDATED DAMAGES CALCULATOR
Project Name: CW Pavement Preservation - Rebid
PID No.: 25-0791
Enter Design Consultant's total post design fee
Enter Construction Administrator's total FeeN/A
Duration of Construction (calendar days)540
Enter Total Project Enclosed Square Footage (if applicable)N/A
Enter Total Daily Department PM/APM Full time EquivalentsN/A
Engineer's Estimate of probable construction cost$ 23,500,000.00
Elements for Liquidated Damages Determination:
Design Consultant Fees$ - 0Total post design fee divided by construction duration *3%
Construction Administration/Inspection$ 1,356.00Daily combined burdened rate for CA staff + Consultant CEI
Project Manager/Assistant Project Manager$ 78.66(1 hour/day burdened rate)
Department Project OverheadLD Schedule
Agency Administrative Costs$ - 0
Temporary Heat/Cooling/Electric$ - 0
Temporary Storage of Owner Provided FFE$ - 0
Rental/Lease of Facilites for Staff, and/or Clients$ - 0
Lost revenues$ - 0
Lost grant revenues$ - 0
Interest$ - 0
Rental / moving expenses$ - 0
Cost for Insurance
Other
Total Liquidated Damages Amount per day$ 1,434.66
Prepared by:
Edit Highlighted Areas

Definitions

A. LIQUIDATED DAMAGES:
Liquidated damages are a specific sum (or a sum readily determinable) of money, stipulated by the contracting parties, as the amount to be recovered for each day of delay in delivery of the product.
Typically, the actual damage amount is unknown or difficult to estimate and is liquidated by the mutual agreement to the rate. Liquidated damages must be based on a reference to a definite standard, such as market value, established experience, or direct inference from known circumstances.
Liquidated damages can not be speculative or a penalty.
B. RATE DETERMINATION:
The amount of liquidated damages must be reasonable to ensure that the damages will not be held to be unenforceable. Therefore, the rate of liquidated damages, also, must be reasonable and is figured on a project-by-project basis.
On the other hand, you do not want to set the liquidated damages at too low an amount. Once liquidated damages are included in a contract, you will be unable to recover actual damages in excess of the specified amount.
C. HOW TO DETERMINE THE AMOUNT OF ANTICIPATED ACTUAL DAMAGES IN ORDER TO ESTABLISH AN APPROPRIATE AMOUNT FOR LIQUIDATED DAMAGES:
Examples of Elements of Rate Determination are listed below (All rates to be based on daily cost). The following list of criteria should be considered when determining anticipated damages that may be caused by a delay in the completion of a project.
Some of these are hard costs; others are based upon nonquantifiable factors.

*Design Consultant Fees – calculated as the construction administration portion of the consultant fee divided by the construction duration multiplied by 3% per year based on duration. If not known, use estimate.

*Construction Administration Fee - Generally calculated by the Construction Division; however, if Construction Division is not inspecting, cost can be based on the total cost for CA divided by the construction duration (multiplied by 3%/year).
FDOT grant funded projects will use the FDOT LD Schedule.
*Project Manager/Assistant Project Manager Time – Hourly burdened rate of PM or APM.
*DPW Project Overhead - based upon daily rate for DPW administrative overhead costs not recovered in PM billing rate.
*Agency Administrative Costs – based upon daily rate for agency personnel assigned to work on project or agency personnel required to spend a portion of their time should be included at that percentage of the daily rate.
*Temporary Heat/Cooling/Electric, Owner provided – Per S.F. of project area/day.
*Temporary Storage of Owner provided FFE – Costs for storage of Furniture, Fixtures, and Equipment, or other storage of products or materials caused by the delayed turn over of the facility.
*Rental/Lease of Facilities for Staff, and/or Clients – calculated in coordination with the agency representative based upon specific needs and available alternatives.
*Loss of revenue - Loss of potential revenue from a facility not opening as scheduled.
*Loss of grant - Loss of grant funding should the project not be completed on time.
*Interest (on borrowed funds) during unexcused delays in completion or periods of non-use.
*Rental/moving or other expenses for alternate space.
*Costs for insurance, utilities, or equipment.
D. HOW TO DOCUMENT THE MEANS BY WHICH LIQUIDATED DAMAGES ARE ESTABLISHED:
1. Determine your anticipated actual per diem damages using criteria such as those listed above.
2. Determine the appropriateness of the figure arrived at in Step 1. The anticipated figure may be used, or a percentage of that figure may be determined to be more appropriate for liquidated damages.
3. Create a typewritten document of the criteria, calculations, and judgments used above.
4. Place the documentation with the Contracts Unit project file for future reference. It is essential to keep all of the records used to determine the per diem liquidated damages amount.
This documentation is important to resolve possible future claims, for audit purposes, and for reference in developing future liquidated damages clauses.

Sheet3