Cooling_Towers_Checklist_&_Condition_Assesment.docx
DOCX document 20 KB Posted
- Attached to
- HVAC-Systems and Related Services
- Solicitation number
- 26-0009-RFP
- Issued by
- Pinellas County, Florida
About this file
This is a Cooling Towers Checklist and Condition Assessment form for Pinellas County, Florida's HVAC Systems and Related Services contract. The document serves as an annual preventive maintenance and inspection template that contractors must complete for each cooling tower asset under the contract. The form requires contractors to perform comprehensive inspections and maintenance tasks including assessment of interior and exterior surfaces, drift eliminators, spray nozzles, fill condition, sump strainers, ball float valve assemblies, bleed flow rates, operational soundness, water leaks, fan motor and bearing conditions, vibration analysis, and electrical testing. Contractors must measure and record motor voltage and amperage, perform Megger Insulation Tests per manufacturer specifications, and lubricate bearings and change gear box oil using manufacturer-specified lubricants. The form must be completed annually and submitted as part of the Annual Preventive Maintenance documentation package, with sign-off required by both the contractor and County representative.
The form explicitly excludes responsibility for equipment room conditions, overall system performance, water treatment, acid cleaning, corrosion or erosion damage to the water side of equipment, disconnect switches, circuit breakers, and complementary equipment such as cabinets, fixtures, and water supply or drain lines. The document includes a five-point condition rating scale—Very Good, Good, Fair, Poor, and Failed—to assess component status and guide future capital planning and replacement decisions. Start and finish values, notes, and dating requirements are documented on the form to create a record of work performed and equipment condition status for the County's asset management and lifecycle planning purposes.
View the file
Other files
Show all 44
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Page 2 of 2 Cooling Towers
INSTRUCTIONS FOR COMPLETING – CHECKLIST AND CONDITION ASSESSMENT The Contractor shall complete for each asset and its associated components covered under this contract. This form must be completed annually and submitted as part of the Annual Preventive Maintenance documentation package. Check off next to each completed task.
Location
Description
Inspect the condition/cleanliness of all interior and exterior surfaces.
Check the integrity of drift eliminators.
Check spray nozzles water distribution. Clean nozzles and remove debris.
Check fill for physical damage.
Remove sump strainer, clean and re-install.
Check condition and operation of ball float valve assembly (of electronic assembly). Reset to correct operational height allowing for pull down volume.
Coordinate with water treatment provider to check bleed flow rate and reset if required.
Check unit for unusual sound or vibration. Perform vibration analysis on tower fan.
Check for any water leaks.
Check fan motor, shaft and bearing operation.
Check vibration cut-out switch.
Lubricate bearings.
Change oil in gear box using manufacturer specified lubricant.
Perform Megger Insulation Test of motor per manufacturer’s specifications and schedule.
Notes
Start Value
Finish Value
Measure and record motor voltage and amperage and record the voltage and current imbalance. Compare amperage with rated amperage.
Notes
It is understood that the service and maintenance provided for herein DOES NOT include the following:
1) Responsibility for equipment room conditions or overall system performance.
2) Water treatment and acid cleaning.
3) Corrosion or erosion damage to the water side of equipment.
4) Disconnect switches and circuit breakers.
5) Complementary equipment (for example, but not confined to, the following: cabinets, fixtures, boxes, water supply lines, and drain lines).
Date:
Signature:
County Representative Signature:
Condition Rating Scale
Notes
| Scale |
| Description of Condition Rating Scale |
| Very Good |
| Component is in new or like-new condition with full performance capability. No corrective actions are required beyond routine preventive maintenance. |
| Good |
| Component is in acceptable operating condition, performing as intended, with no immediate corrective work required outside of scheduled preventive maintenance. |
| Fair |
| Component remains functional but is degraded or showing measurable wear. Increased monitoring and prioritization for future capital planning is required. |
| Poor |
| Component condition is unacceptable or nearing failure. Significant deterioration or recurring issues exist and near‑term replacement must be planned. |
| Failed |
| Component is nonfunctional, inoperable, or unsafe to operate. Immediate replacement or major corrective repair is required. |