Construction_Performance_Bond.pdf
PDF 118 KB Posted
- Solicitation number
- 2025-ITB-002
- Issued by
- Doña Ana County, New Mexico
About this file
This document is a Construction Performance Bond for the Gallup Municipal Airport project, issued by the City of Gallup, New Mexico, with an Airport Improvement Project (AIP) number 3-35-0019-031-2024. The bond serves as a financial guarantee for the completion of airport runway rehabilitation work, specifically involving crack seal and seal coat services for Runway 6/24. The bond outlines the legal obligations and responsibilities of the contractor and surety in the event of default, including provisions for completing the contract, correcting defects, and managing potential performance issues within one year after final project acceptance.
The bond does not specify the exact contract amount or detailed pricing terms, but it establishes a comprehensive framework for protecting the owner's interests by ensuring project completion and quality. The surety (bonding company) agrees to take specific actions if the contractor fails to perform, such as arranging for contract completion, undertaking the work directly, or obtaining bids from alternative contractors. The bond also includes provisions for handling additional costs, legal expenses, and potential damages resulting from contractor default, with a two-year limitation period for any legal proceedings related to the contract performance.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Contract Documents PER-1 247024 Gallup Municipal Airport
CONSTRUCTION PERFORMANCE BOND
Any singular reference to Contractor, Surety, Owner or other party shall be considered plural where applicable.
CONTRACTOR (Name and Address): SURETY (Name and Principal Place of Business)
OWNER (Name and Address):
City of Gallup 110 West Aztec Avenue Gallup, New Mexico 87301
CONSTRUCTION CONTRACT
Date: ____________________ Amount: $ Description (Name and Location):
Gallup Municipal Airport Gallup, New Mexico AIP No. 3-35-0019-031-2024
BOND
Date (Not earlier than Construction Contract Date): ___________________________ Amount: $ Modifications to this Bond Form:
CONTRACTOR AS PRINCIPAL SURETY
Company: Company: _________________________ (Corp. Seal) (Corp. Seal)
Signature: ___________________________________ Signature: __________________________ Name and Title: _______________________________ Name and Title: ______________________
Contract Documents PER-2 247024 Gallup Municipal Airport
1. The Contractor and the Surety, jointly and severally, bind themselves, their heirs, executors, administrators, successors and assigns to the Owner for the performance of the Construction Contract, including all related Construction Documents and modifications thereto, which is incorporated herein by reference.
2. If the Contractor completes the Contract and corrects all defects that appear within one year after final acceptance of all the work required under the Contract Documents, the Surety and the Contractor shall have no obligation under this bond, except to participate in conferences as provided in Subparagraph 3.1.
3. The Surety's obligations under this Bond shall arise after:
3.1 The Owner has notified the Contractor and the Surety at its address described in Paragraph 10 below, that the Owner is considering declaring a Contractor Default and has requested and attempted to arrange a conference with the Contractor and the Surety to be held not later than fifteen days after receipt of such notice to discuss methods of performing the Contract, or for correcting defects in workmanship or material that have appeared within one year after final acceptance of the work. If the Owner, the Contractor and the Surety agree, the Contractor shall be allowed a reasonable time to perform the Contract, or to correct said defects in workmanship or material, but such an agreement shall not waive the Owner's right, if any, subsequently to declare a Contractor Default; and
3.2 The Owner has declared a Contractor Default and formally terminated the Contractor's right to complete the Contract or to correct said defects. Such Contractor Default shall not be declared earlier than twenty days after the Contractor and the Surety have received notice as provided in Subparagraph 3.1; and
3.3 The Owner has agreed to pay the Balance of the Contract Price to the Surety in accordance with the terms of the Contract or to a contractor selected to perform the Contract, or to correct said defects in accordance with the terms of the Contract with the Owner.
4. When the Owner has satisfied the conditions of Paragraph 3, the Surety shall promptly and at the Surety's expense take one of the following actions:
4.1 Arrange for the Contractor, with consent of the Owner to perform and complete the Contract, or to correct said defects in workmanship or material; or
4.2 Undertake to perform and complete the Contract, or to correct said defects in workmanship or material itself, through its agents or through independent contractors; or
4.3 Obtain bids or negotiated proposals from qualified contractors acceptable to the Owner for a contract to (a) perform and complete the Contract or correct said defects in workmanship or materials; (b) arrange for a Contract to be prepared for execution by the Owner and the Contractor selected with the Owner's concurrence, to be secured with performance and payment bonds executed by a qualified surety equivalent to the bonds issued on the Contract and (c) pay to the Owner the amount of damages as described in Paragraph 6 in excess of the Balance of the Contract Price incurred by the Owner resulting from the Contractor's default; or
4.4 Waive its right to perform and complete, arrange for completion or obtain a new contractor and with reasonable promptness under the circumstances:
1. After investigation, determine the amount for which it may be liable to the Owner and as soon as practicable after the amount is determined, tender payment therefore to the Owner; or
2. Deny liability in whole or in part and notify the Owner citing reasons therefore.
5. If the Surety does not proceed as provided in Paragraph 4 with reasonable promptness, the Surety shall be deemed to be in default on this Bond fifteen days after receipt of an additional written notice from the Owner to the Surety demanding that the Surety perform its obligations under this Bond and the Owner shall be entitled to enforce any remedy available to the Owner if the Surety proceeds as provided in Subparagraph 4.4 and the Owner refuses the payment tendered or the Surety has denied liability, in whole or in part, without further notice the Owner shall be entitled to enforce any remedy available to the Owner.
6. After the Owner has terminated the Contractor's right to complete the Contract, or to correct said defects in workmanship or materials and if the Surety elects to act under Subparagraphs 4.1, 4.2 or 4.3 above, then the responsibilities of the Surety to the Owner shall not be greater than those of the Contractor under the Contract and related Construction Documents and the responsibilities of the Owner to the Surety shall not be greater than those of the Owner under the Contract and Construction Documents. To the limit of the amount of this Bond, but subject to commitment by the Owner to pay the Balance of the Contract Price to mitigation of costs and damages of the Contract, the Surety is obligated without duplication for:
6.1 The responsibilities of the Contractor for completion of the Contract and correction of any defects that appear within one year following final acceptance of all the work required under the Construction Contract and related Documents;
6.2 Additional legal, design professional and delay costs resulting from the Contractor's Default, or resulting from the actions or failure to act of the Surety under Paragraph 4; and
6.3 Liquidated damages, or if no liquidated damages are specified in the Contract, actual damages caused by delayed performance or nonperformance of the Contractor.
7. The Surety shall not be liable to the Owner or others for obligations of the Contractor that are unrelated to the Contract and the Balance of the Contract Price shall not be reduced or set off on account of any such unrelated obligations. No right of action shall accrue on this bond to any person or entity other than the Owner or its heirs, executors, administrators, or successors.
8. The Surety hereby waives notice of any change, including changes of time and changes in the work required under the Contract or related subcontracts, purchase orders and other obligations.
9. Any proceeding, legal or equitable, under this Bond may be instituted in any court of competent jurisdiction in the location in which the work or part of the work is located and shall be instituted within two years after Owner became aware, or reasonably should have become aware of Contractor Default or within two years after the Surety refuses or fails to perform its obligations under this Bond; whichever occurs first. If the provisions of this Paragraph are void or prohibited by law, the minimum period for limitation available to sureties as a defense in the jurisdiction of the suit shall be applicable.
10. Notice to the Surety, the Owner or the Contractor shall be mailed or delivered to the address shown on the signature page.
11. When this bond has been furnished to comply with a statutory or other legal requirement in the location where the construction was to be performed, any provision in this Bond conflicting with said statutory or legal requirement shall be deemed deleted hereon and provisions conforming to such statutory or other legal requirement shall be deemed incorporated herein. The intent is that this Bond shall be construed as a statutory bond and not as a common-law bond.
12. Definitions:
12.1 Balance of the Contract Price: The total amount payable by the Owner to the Contractor under the Contract after all proper adjustments have been made, including allowance to the Contractor of any amount received or to be received by the Owner in settlement of insurance or other claims for damages to which the Contractor is entitled, reduced by all valid and proper payments made to or on behalf of the Contractor under the Contract.
12.2 Contract: The agreement between the Owner and the Contractor identified on the signature page, including all Contract Documents and changes thereto.
12.3 Contractor Default: Failure of the Contractor, which has neither been remedied nor waived, to perform or otherwise to comply with the terms of the Contract.
12.4 Owner Default: Failure of the Owner, which has neither been remedied nor waived, to pay the Contractor as required by the Construction Contract or to perform and complete or comply with the other terms thereof.