This solicitation is for a phased boiler replacement project at Timberline Lodge on Mount Hood National Forest. The project includes removing abandoned equipment, installing new hot water boilers and associated piping and controls, replacing room radiators, and integrating new controls systems. Work will be conducted in phases over multiple years with optional items that can be awarded separately. Phase 1 involves preparatory work and is estimated at $10 million. Subsequent phases will replace additional steam boilers and controls. A pre-proposal conference is scheduled for May 4 and offers are due May 25. The selected contractor must be registered in SAM.gov and comply with prevailing wage requirements.

View the file

Other files

File Type Posted
AmendmentA0009.pdf PDF
AmendmentA0008.pdf PDF
AmendmentA0007.pdf PDF
AmendmentA0006.pdf PDF
Amendment0005.pdf PDF
Interested Vendors.pdf PDF
AmendmentA0004.pdf PDF
TimberlineBoilersErrataAmendment4-20210514.pdf PDF
260000A-ElectricalBasicRequirements-Testing-20210517.pdf PDF
AmendmentA0003.pdf PDF
AmendmentA0002.pdf PDF
AmendmentA0001.pdf PDF
MainAndWyEastDayLodge-Drawings-20210426.pdf PDF
MainAndWyEastDayLodgeSpecs-20210426.pdf PDF
Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

1240BH21R0014

2. TYPE OF SOLICITATION

SEALED BID (IFB)

NEGOTIATED (RFP)

3. DATE ISSUED

26 April

PAGE OF PAGES

IMPORTANT - The “offer” section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

5. REQUISITION/PURCHASE REQUEST NO.

1031957

6. PROJECT NO.

7. ISSUED BY CODE 8. ADDRESS OFFER TO

PROCUREMENT AND PROPERTY SERVICES, NORTHWEST

ZONE, CSA 6

3200 SW JEFFERSON WAY

CORVALLIS, OREGON 97331

Email or Fax Submission Only Note: Due to COVID-19 all proposal documents must be emailed to sm.fs.conwest@usda.gov or faxed to 866.230.8120.

9. FOR INFORMATION

CALL:

A. NAME

CONTRACTING OFFICE

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

(541) 750-7116

SOLICITATION

NOTE: In sealed bid solicitations “offer” and “offeror” mean “bid” and “bidder.”

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date):

RFP 1240BH21R0014

GAOA TIMBERLINE BOILER

MOUNT HOOD NATIONAL FOREST

Price Range The Government's estimate is over $10,000,000 (including option items).

THIS IS A SMALL BUSINESS SET-ASIDE PROJECT. OFFERS RECEIVED FROM OTHER THAN

SMALL BUSINESSES WILL BE REJECTED.

11. The Contractor shall begin performance within 10 calendar days and complete it within See F-2 calendar days after receiving award, notice to proceed. This performance period is mandatory, negotiable. (See F-2.)

12A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If “YES,” indicate within how many calendar days after award in Item 12B.)

NO

12B. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and -0- copies to perform the work required are due at the place specified in Item 8 by 4:00 PM local time 05/25/21 . If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror’s name and address, the solicitation number, and the date and time offers are due.

B. An offer guarantee is, is not required.

C. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than _60 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Computer Generated Prescribed by GSA FAR (48 CFR) 53.236-1(e) mailto:sm.fs.conwest@usda.gov

OFFER (Must be fully completed by offeror)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)

15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than Item 14)

CODE FACILITY CODE

17. The offeror agrees to perform the work at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government within calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER

(Type or print)

20B. SIGNATURE

20C. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT

23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c)( )

26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return ____ copies to issuing office.) Contractor agrees to furnish and deliver all items or perform all work, requirements identified on this form and any continuation sheets for the consideration stated in this contract.

The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications or incorporated by reference in or attached to this contract.

29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED

TO SIGN (Type or print)

31A. NAME OF CONTRACTING OFFICER (Type or print)

30B. SIGNATURE

30C. DATE

31B. UNITED STATES OF AMERICA

BY

31C. AWARD DATE

Computer Generated STANDARD FORM 1442 BACK (REV. 4-85)

GAOA TIMBERLINE LODGE

MOUNT HOOD NATIONAL FOREST

ZIG ZAG RANGER DISTRICT

MULTNOMAH COUNTY, OR

PART I—THE SCHEDULE

SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS

BID SCHEDULE

ITEM NO. DESCRIPTION MOM UNIT

ESTIMATED

QUANTITY UNIT PRICE TOTAL

BASE ITEMS – PHASE 1

REMOVE ABANDONED

GENERATOR LSQ LS 1 n/a $

INSTALL BOILER AND

CIRCULATION PUMP

INSTALL PANEL CH-1

AND ALL ELECTRICAL

ELEMENTS REQUIRED

FOR PHASE I LSQ LS 1 n/a $

INSTALL HOT WATER

PIPING AND

RADIATORS LSQ LS 1 n/a $

DESIGN DDC CONTROL

SYSTEM FOR PHASES 1-

4 AND INSTALL PHASE

1 DDC CONTROL

SYSTEM TO

INTERGRATE WITH

EXISTING HONEYWELL

SYSTEM LSQ LS 1 n/a $

DESIGN AND INSTALL

SECURITY SYSTEM FOR

ENTIRE DDC CONTROL

SYSTEM LSQ LS 1 n/a $

SUBTOTAL BASE

ITEMS-PHASE 1 $

OPTIONAL ITEMS 1 –

PHASE 2

REMOVE STEAM

BOILER LSQ LS 1 n/a $

INSTALL BOILER AND

CIRCULATION PUMP LSQ LS 1 n/a $

1240BH21R0014

REPLACE WEST SIDE

ROOM RADIATORS LSQ LS 1 n/a $

1004 INSTALL CONTROLS LSQ LS 1 n/a $

CONNECT CS PRICE

HEATING TO NEW HOT

WATER SYSTEM LSQ LS 1 n/a $

SUBTOTAL OPTIONAL

ITEMS 1-PHASE 2 $

ITEM NO. DESCRIPTION MOM UNIT

ESTIMATED

QUANTITY UNIT PRICE TOTAL

OPTIONAL ITEMS 2 –

PHASE 3

REPLACE STEAM

BOILER LSQ LS 1 n/a $

REPLACE ROOM

RADIATORS LSQ LS 1 n/a $

CONNECT NEW HOT

WATER SYSTEM LSQ LS 1 n/a $

2004 INSTALL CONTROLS LSQ LS 1 n/a $

INSTALL SWIMMING

POOL AND SPA

HEATING SYSTEMS LSQ LS 1 n/a $

ITEMS 2-PHASE 3 $

OPTIONAL ITEMS 3 –

PHASE 4

3001 REPLACE TWO BOILERS LSQ LS 1 n/a $

3002 INSTALL CONTROLS LSQ LS 1 n/a $

ITEMS 3-PHASE 4 $

GRAND TOTAL $

Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed-Price Construction Contracts, shall not be in addition to the contract price.

DUNS Number________________________

EMAIL ______________________________

NOTE: prospective awardee shall be registered and active in the System for Award Management (SAM) data base when submitting an offer, and shall continue to be registered until time of award, during performance, and through final payment of a contract resulting from this solicitation. Information on registration may be obtained via the internet at: http://www.sam.gov. All contractors and vendors must complete the electronic version of the Representations and Certifications in the SAM system. If at the time of receipt of offers, an Offeror is not actively and successfully registered in the SAM database, the Offeror will not be considered for award.

C-1 SCOPE OF CONTRACT

The work of this Contract includes all labor, equipment and materials required to do the following work at the Timberline Lodge, Zig Zag Ranger District, Mount Hood National Forest.

This project is set up to be phased. The following is a description of Phase 1, which are the Base items.

1.Bid Item 001: Remove abandoned generator in the boiler room.

2. Bid Item 002: Install a 2,000 MBH hot water boiler and a 15 HP circulation pump. The existing steam boilers will remain.

3. Bid Item 002: Replace 2 existing fuel oil pumps and piping to new boiler and 2 existing boilers.

4. Install new panel CH-1 with capacity to serve the needs of phase I-IV, Options 1-3 in the Lodge and all necessary circuits, wiring, devices and controls for Phase I operational needs.

5. Bid Item 003: Install new main hot water piping in the boiler room. Provide hot water to patio, front Lodge entry and CS Price snow melt systems. Keep snow melt heating pipe, pump and accessories intact and connect to new hot water boiler. Integrate with existing control system to render the system operational.

6. Bid Item 004: Design complete DDC Control system for Main Lodge and Day lodge for phases 1-4.

See section 23 09 00 Instrumentation and Controls Performance Specification, 26 09 00 Controls and Instrumentation, 27 00 00 Telecommunications Wiring System, 27 00 01 Network Security for connection details. The Controls will be installed per phase.

7. Bid Item 004: Integrate new control system with the existing Honeywell DDC control system capable of serving the entire project, phases 1-4, and provide software, infrastructure, and equipment necessary to render the systems installed in Phase I operational. System will include control system hardware, wiring, and software programs.

8. Bid item 005: Design the control system to provide for security from Malware, hacking and other threats. System should include a firewall system and wiring changes to isolate the existing DDC system network connections from the existing building network. See section 27 00 01 for Network Security design criteria.

***Items 1-6 need to be completed before consistently freezing temperatures and snow occur (typically late October) in order to minimize impacts to Lodge operations and prevent freeze damage to existing water piping. ***

9. Bid Item 003: Install new main hot water piping from boiler room to attic spaces, stub off isolation valves for connection to individual room radiators of all phases; replace/install approximately 34 finned tube room radiators in existing and newly constructed historically accurate cabinets. This work will need to be coordinated with Lodge operations to minimize impacts to the operation of the Lodge.

Phase 1 will have a period of performance of 150 days starting July 2021.

Option No.1: Phase 2 of the Boiler Replacement project consists of the following:

1. Remove one (1) steam boiler.

2. Install new 5,000 MBH boiler and a 15 HP circulation pump, and all associated electrical work, control system additions and modifications needed to render the installation fully functional.

3. Replace/install approximately 94 Finned tube room radiators in existing and newly constructed historically accurate cabinets, on west side of building and connect heating and fan coil units at the common spaces. This work will need to be coordinated with Lodge operations to minimize impacts to the operation of the Lodge.

4. Expand existing electrical service, existing controls infrastructure and equipment to make the system replacements/additions fully functional.

5. Connect CS Price Heating to new hot water system

Phase 2 will have a period of performance of 150 days starting no later than May 2022.

Option No. 2: Phase 3 of the Boiler Replacement project consists of the following:

1. Replace second steam boiler and install new, third, 5,000 MBH boiler, and all associated electrical work, control system additions and modifications needed to render the installation fully functional.

2. Replace/install approximately 93 Finned tube room radiators in existing and newly constructed historically accurate cabinets, in the remaining areas of building and connect heating and fan coil units at the common spaces. This work will need to be coordinated with Lodge operations to minimize impacts to the operation of the Lodge.

3. Connect kitchen, domestic hot water, pool and spa to the new hot water system.

4. Expand existing electrical service, controls infrastructure and equipment to make the system replacements/additions fully functional.

5. Install Swimming Pool and Spa Heating Systems

Phase 3 will have a period of performance of 150 days starting no later than May 2023.

Option No. 3: Phase 4 of the Boiler Replacement project consists of the following:

1. Replace 2 hot water boilers with two new 4,000 MBH hot water boilers, pumps, and all associated electrical work, control system additions and modifications needed to render the installation fully functional.

2. Expand existing electrical service, controls infrastructure and equipment to make the system replacements/additions fully functional.

Phase 4 will have a period of performance of 120 days starting no later than May 2023.

C-2 PROJECT LOCATION

Timberline Lodge, Zigzag Ranger Distrcit, Mt Hood National Forest 27500 E Timberline Road, Government Camp, OR 97028

C-3 MAGNITUDE OF CONSTRUCTION PROJECT

The Government's estimate is over $10,000,000 (including options).

C-4 APPLICABLE SPECIFICATIONS (CSI PROJECTS)

The specifications shown in the specification listing contained in the attachments are applicable to this contract. All specifications not included in the specification listing but referenced by listed specifications, are applicable. The specifications shown on the specification list are physically attached.

C-5 ATTACHMENTS TO STATEMENT OF WORK/SPECIFICATIONS - AGAR

452.211-73 (FEB 1988)

The attachments to the Statement of Work/Specifications listed in Section J are hereby made part of this solicitation and any resultant contract.

C-6 STATEMENT OF WORK/SPECIFICATIONS (452.211-72) (FEB 1988)

The Contractor shall furnish the necessary personnel, material, equipment, services and facilities (except as otherwise specified), to perform the Statement of Work/Specifications referenced in Section J.

C-7 BIO-PREFERRED PROGRAM REQUIREMENTS

The Contractor must comply with Section 9002 of the Farm Security and Rural Investment Act of 2002 (FSRIA), Executive Order (EO) 13423, “Strengthening Federal Environmental, Energy, and Transportation Management,” and the Federal Acquisition Regulation to provide biobased products.

The Contractor shall utilize products and material made from biobased materials (e.g., insulating foam, composite panels, and concrete and asphalt release fluids) to the maximum extent possible without jeopardizing the intended end use or detracting from the overall quality delivered to the end user. All supplies and materials shall be of a type and quality that conform to applicable Federal specifications and standards. All supplies and materials to be used in the performance of work described herein are subject to the approval of the Contracting Officer Representative (COR).

The following is an example list of products that may be used in this contract for minor construction for which biobased products are available. The list is not all inclusive. It is desirable that vendors be able to supply the greatest number of biobased products meeting the health and environmental specifications.

Operations and Maintenance Penetrating Lubricants Greases Gear Lubricants Pneumatic Equipment Lubricants Fuel Conditioners Gasoline Fuel Additives Hydraulic Fluids Safety Equipment (Protective Helmets)

Construction Dust Suppressants Concrete/Asphalt Release Fluids Asphalt Restorers Asphalt/Tar Removers Traffic/Zone Marking Paints Erosion Control

Biobased products that are designated for preferred procurement under USDA’s BioPreferred program must meet the required minimum biobased content as stated in the USDA Final Rule available at www.biopreferred.gov.

In addition to the biobased products designated by the U.S. Department of Agriculture in the BioPreferred Program, the Contractor is encouraged to use other commercially available biobased products.

The Contractor shall comply with the provision at FAR 52.223-1, Biobased Product Certification.

The Contractor shall comply with the clause at FAR 52.223-2, Affirmative Procurement of Biobased Products Under Service and Construction Contracts.

SECTION D--PACKAGING AND MARKING

{For this Solicitation, there are NO clauses in this Section}

SECTION E--INSPECTION AND ACCEPTANCE

E-1 CLAUSES INCORPORATED BY REFERENCE (FAR 52.252-2)(FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.arnet.gov/far/

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

52.246-12 Inspection of Construction (AUG 1996)

E-2 INSPECTION AND ACCEPTANCE (AGAR 452.246-70) (FEB 1988)

(a) The Contracting Officer or the Contracting Officer's duly authorized representative will inspect and accept the supplies and/or services to be provided under this contract.

(b) Inspection and acceptance will be performed at the project location.

(End of clause)

E-3 INSPECTION AND TESTING PERFORMED BY GOVERNMENT

The Government will perform sampling, testing and inspection of work in progress where these responsibilities are not expressly assigned to the Contractor by the Forest Service specifications or by the Supplemental Specifications.

E-4 CONFORMITY WITH DRAWINGS AND SPECIFICATIONS

Unless working tolerances are specified, all work performed and materials furnished shall be in reasonably close conformity with lines, grades, cross sections, dimensions, and material requirements shown on the Drawings, indicated in the specifications, or designated on the ground. "Reasonably close conformity" is in compliance with reasonable and customary manufacturing and construction tolerances.

http://www.arnet.gov/far/

SECTION F--DELIVERIES OR PERFORMANCE

F-1 CLAUSES INCORPORATED BY REFERENCE (FAR 52.252-2)(FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.arnet.gov/far/

52.211-18 Variation in Estimated Quantity (APR 1984) 52.236-15 Schedules for Construction Contracts (APR 1984) 52.242-14 Suspension of Work (APR 1984)

F-2 FAR 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF

WORK (APR 1984) ALTERNATE I (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than see C-1. The time stated for completion shall include final cleanup of the premises.

Estimated start work date for the base items is 15 July 2021.

This contract is funded by Great American Outdoor Act funding. At this time, it is unknown when or if funding may be received by the Forest Service for Phases 2 through 4 (optional items 1-3).

Therefore, if the performance period for the base items ends, and funding for Phase 2 (option 1) has not yet been received, the contract will remain open, in order to allow for Phase 2 (option 1) to be exercised. Likewise, if the performance period for Phase 2 (option 1) has elapsed before funding for Phases 3 (option 2) and 4 (option 3) is received, the contract will remain open to allow for those phases to be exercised.

F-3 SUSPENSIONS OF WORK FOR OTHER THAN GOVERNMENT'S

CONVENIENCE

The Contracting Officer may issue orders to suspend the work wholly or in part for such period of time as deemed necessary because of:

(1) Weather or ground conditions when further prosecution of the work might cause environmental or resource damage to the project, access roads to the project or adjacent property. Such action would include but not be limited to instances such as siltation of streams, damage to access roads, rutting of project roads which causes otherwise suitable soils to be muddy or unsuitable; or

(2) Failure of the Contractor to comply with specifications such as but not limited to placement of frozen material in fills, placing of asphalts at temperatures lower than those specified, performing work prior to prerequisite approvals, operating equipment not meeting fire requirements or when

1240BH21R0014

http://www.arnet.gov/far/ conditions exist which do not meet safety requirements. Whether or not a suspend work notice is issued, the Contractor shall be responsible for correcting any damage caused by its operation, whether inside or outside project limits, at no cost to the Government. Such suspensions shall not be considered as suspensions for the Convenience of the Government under FAR 52.242-14, Suspension of Work, and shall not qualify for an equitable adjustment.

SECTION G--CONTRACT ADMINISTRATION DATA

G-1 POST AWARD CONFERENCE (AGAR 452.215-73)(NOV 1996)

A post award conference with the successful offeror is required. It will be scheduled and held within 7 days after the date of contract award. The conference will be held via phone or Microsoft TEAMS or a mutually agreed upon location.

G-2 DESIGNATION OF CONTRACTNG OFFICER’S REPRESENTATIVE

The Contracting Officer’s Representative (COR) is responsible for administering the performance of work under this contract. In no event, however, will any understanding, agreement, modification, change order or other matter deviating from the terms of this contract be effective or binding upon the government unless formalized by proper contractual documents executed by the Contracting Officer prior to completion of the contract. The Contracting Officer should be informed as soon as possible or any actions, or inactions, by the Contractor, or the Government, which will change the required delivery or completion times stated in the contract, and the contract will be modified accordingly.

(This does not apply to individual assignments which were issued by the COR provided they do not affect the delivery schedule or the performance period stated in the contract.)

On all matters that pertain to the contract terms, the Contractor must communicate with the Contracting Officer. Whenever, in the opinion of the Contractor, the COR requests effort outside the scope of the contract, the Contractor should so advise the COR. If the COR persists and there still exists a disagreement as to proper contractual coverage, the Contracting Officer should be notified immediately, preferably in writing, if time permits. Proceeding with work without proper contractual coverage could result in nonpayment or necessitate submittal of a contract claim.

SECTION H--SPECIAL CONTRACT REQUIREMENTS

H-1 KEY PERSONNEL (AGAR 452.237-74)(FEB 1988)

(a) The Contractor shall assign to this contract the following key personnel:

Project Manager Site Superintendent Quality Control Manager Electrical Contractor Licensed in the State of Oregon.

(b) During the first ninety (90) days of performance, the Contractor shall make no substitutions of key personnel unless the substitution is necessitated by illness, death, or termination of employment. The Contractor shall notify the Contracting Officer within 15 calendar days after the occurrence of any of these events and provide the information required by paragraph (c) below. After the initial 90-day period, the Contractor shall submit the information required by paragraph (c) to the Contracting Officer at least 15 days prior to making any permanent substitutions.

(c) The Contractor shall provide a detailed explanation of the circumstances necessitating the proposed substitutions, complete resumes for the proposed substitutes, and any additional information requested by the Contracting Officer. Proposed substitutes should have comparable qualifications to those of the persons being replaced. The Contracting Officer will notify the Contractor within 15 calendar days after receipt of all required information of the decision on substitutions. The contract will be modified to reflect any approved changes of key personnel.

H-2 POTENTIAL SAFETY HAZARDS

(a) Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor. This list shall not be deemed to be all-inclusive. The Contractor shall bear the sole responsibility for taking all appropriate actions necessary to prevent accidents and injuries to individuals at the worksite.

(b) The following checked activities have been identified by the Government as potential safety hazards.

[ ] Confined space entry.

[ ] Temporary excavation/deep trenching/slope stability.

[ ] Tree falling.

[X ] Fall hazard from work heights exceeding six feet.

[ ] Blasting.

[ ] Traffic control on high-volume and/or high-speed and/or limited visibility roads.

[X ] Heavy equipment operation.

[ ] Tree climbing and/or tower climbing.

[ ] Fire hazards.

[X ] Hazardous materials handling.

[X ] Electrical hazard.

[X ] Hydraulic and/or pneumatic and/or other high pressure hazards.

[X ] Mechanical hazards such as pulleys, springs, etc.

[ ] Other __________________________________

H-3 SALVAGE RIGHTS

No Contractor salvage rights exist under the contract unless specifically provided elsewhere herein.

H-4 SUBMITTALS, SHOP DRAWINGS, MATERIAL CERTIFICATIONS AND TESTING

REPORTS

The following shall be submitted on this project:

Title Referenced by

Specification No.

Time of Government

Approval After Submittal

SEE SPECIFICATIONS

H-5 PRODUCT SUBSTITUTION

Any modification of items, designs, materials, products or equipment (including Government-Furnished property), made necessary because of a substitution, will be the responsibility of the Contractor without adjustment in contract price or time. The Contracting Officer's approval of any substitute will not affect the Contractor's responsibility for such modification. Any and all substitutions will be requested by the Contractor after award of the contract has been made.

No approvals will be made prior to award.

H-6 PROSECUTION OF WORK

(a) Construction activity shall be limited to the hours between 0900 a.m. and 0600 p.m., Monday through Friday, unless other hours are approved in writing by the Contracting Officer. The Contractor shall conduct activities so that interference with the public shall be kept at a minimum. The project site shall be open to public access and free of hazards on weekends. Any activities requiring closure to the public shall be scheduled with the COR at least 14 days in advance.

(b) The Contractor shall use measures and precautions necessary to warn and protect the public and Government personnel during work at the project site. Such actions include, but are not limited to, furnishing and maintaining barricades and signs around the work site and roping off the area.

H-7 PROTECTION OF CULTURAL RESOURCES

Location of known historic or prehistoric sites, buildings, objects, and properties related to American history, architecture, archaeology and culture, such as settler or Indian artifacts, protected by American Antiquities Act of 1906 (16 U.S.C. 431-433), National Historic Preservation Act of 1966 (16 U.S.C.

470) and the Archaeological Resources Protection Act of 1979 (PL 96-95 and 36 CFR 261.9(e)) shall be identified on the ground by Forest Service. Forest Service may unilaterally modify or cancel this contract to protect an area, object of antiquity, artifact, or similar object which is or may be entitled to protection under these Acts regardless of when the area, object or artifact is discovered or identified.

Discovery of such areas or objects by either party shall be promptly reported to the other party.

Contractor shall protect all known and identified historic or prehistoric sites, buildings, objects and properties related to American history, architecture, archaeology and culture against destruction, obliteration, removal or damage during Contractor's Operations. In accordance with 36 CFR 296.14(c), Contractor shall bear costs of restoration, provided that such payment shall not relieve Contractor from civil or criminal remedies otherwise provided by law.

H-8 METHODS OF MEASUREMENT

One of the following methods of measurement for determining final payment is DESIGNATED on the SCHEDULE OF ITEMS for each pay item:

(a) Designed Quantities (DQ). These quantities denote the final number or units to be paid for under the terms of the contract. They are based upon the original design data available prior to advertising the project. Original design data include the preliminary survey information, design assumptions, calculations, drawings, and the presentation in the contract. Changes in the number of units SHOWN in the SCHEDULE OF ITEMS may be authorized under any of the following conditions:

(1) As a result of changes in the work authorized by the Contracting Officer.

(2) As a result of the Contracting Officer determining that errors exist in the original design that cause a pay item quantity to change by 15 percent or more.

(3) As a result of the Contractor submitting to the Contracting Officer a written request showing evidence of errors in the original design that cause a pay item quantity to change by 15 percent or more.

The evidence must be verifiable and consist of calculations, drawings, or other data that show how the designed quantity is believed to be in error.

(b) Lump Sum Quantities (LSQ). These quantities denote one complete unit of work as required by or described in the contract including necessary materials, equipment, and labor to complete the job.

They will not be measured.

H-9 STATE ELECTRICAL INSPECTION AND COUNTY BUILDING PERMITS

The Contractor shall arrange for and provide the State Electrical inspection. When requesting the inspection inform the Building Permit Department of the federal limitation described below. The Contractor shall not obtain any building permits or inspections other than the State Electrical inspection.

NOTE: This project requires electrical contractor / electricians to be licensed in the state of Oregon.

Obtaining an electrical permit and electrical inspection of the work by the Authority Having Jurisdiction is required. Submit proof of State of Oregon contractor’s electrical license at time of proposal submission.

Federal law validated by the State Attorney General, Oregon Department of Justice verify that the Federal Government and its Contractors may be exempted from State/Local Building Permits and Fees for projects located on Federal Installations. Contractor State Licenses will not be jeopardized by following this requirement to avoid the State/County permit system. This applies to the prime Contractor and all subcontractors.

PART II--CONTRACT CLAUSES

SECTION I--CONTRACT CLAUSES

I-1 FAR 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

Federal Acquisition Regulation (FAR) Clauses: https://www.acquisition.gov/browse/index/far (FAR clauses begin with 52) Department of Agriculture Acquisition Regulation (AGAR) Clauses: https://www.acquisition.gov/agar (AGAR clauses begin with 452) Deviations to clauses may be viewed at:

https://www.dm.usda.gov/procurement/policy/FARClassDeviations.htm

52.202-1 Definitions (JUN 2020) 52.203-3 Gratuities (APR 1984) 52.203-5 Covenant Against Contingent Fees (MAY 2014) 52.203-6 Restrictions on Subcontractor Sales to the Government (JUN 2020) 52.203-7 Anti-Kickback Procedures (JUN 2020) 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity (MAY 2014) 52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (MAY 2014) 52.203-12 Limitation on Payments to Influence Certain Federal Transactions (JUN 2020) 52.203-13 Contractor Code of Business Ethics and Conduct (JUN 2020) 52.203-14 Display of Hotline Poster(s) (JUN 2020) 52.203-17 Contractor Employee Whistleblower Rights and Requirement To Inform Employees of

Whistleblower Rights (JUN 2020) 52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements

(JAN 2017)

52.204-4 Printed or Copied Double-Sided on Recycled Paper (MAY 2011) 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards (JUN 2020) 52.204-13 System for Award Management Maintenance (OCT 2018) 52.204-14 Service Contract Reporting Requirements (OCT 2016) 52.204-18 Commercial and Government Entity Code Maintenance (AUG 2020) 52.204-19 Incorporation by Reference of Representations and Certifications (DEC 2014) 52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab and Other Covered Entities (JUL 2018) 52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance

Services or Equipment (AUG 2020) 52.209-6 Protecting the Government's Interest when Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (JUN 2020) 52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters (OCT

2018) 52.209-10 Prohibition on Contracting With Inverted Domestic Corporations (NOV 2015)

1240BH21R0014

https://www.acquisition.gov/browse/index/far https://www.acquisition.gov/agar https://www.dm.usda.gov/procurement/policy/FARClassDeviations.htm

52.210-1 Market Research (JUN 2020) 52.215-2 Audit and Records -- Negotiation (JUN 2020) 52.219-6 Notice of Total Small Business Set-Aside (MAR 2020) 52.219-8 Utilization of Small Business Concerns (OCT 2018) 52.219-14 Limitations on Subcontracting (MAR 2020)

[Contracting Officer check as appropriate.] X☐By the end of the base term of the contract and then by the end of each subsequent option period; or ☐By the end of the performance period for each order issued under the contract.

52.219-28 Post Award Small Business Program Rerepresentation (NOV 2020) 52.222-3 Convict Labor (JUN 2003) 52.222-4 Contract Work Hours and Safety Standards Act -- Overtime Compensation (MAY

2018) 52.222-6 Construction Wage Rate Requirements (AUG 2018) 52.222-7 Withholding of Funds (MAY 2014) 52.222-8 Payrolls and Basic Records (AUG 2018) 52.222-9 Apprentices and Trainees (JUL 2005) 52.222-10 Compliance with Copeland Act Requirements (FEB 1988) 52.222-11 Subcontracts (Labor Standards) (MAY 2014) 52.222-12 Contract Termination - Debarment (MAY 2012) 52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations

(MAY 2014)

52.222-14 Disputes Concerning Labor Standards (FEB 1988) 52.222-15 Certification of Eligibility (MAY 2014) 52.222-21 Prohibition of Segregated Facilities (APR 2015) 52.222-26 Equal Opportunity (SEP 2016) 52.222-27 Affirmative Action Compliance Requirements for Construction (APR 2015) 52.222-30 Construction Wage Rate Requirements-Price Adjustment (None or Separately Specified

Pricing Method) (AUG 2018) 52.222-35 Equal Opportunity for Veterans (JUN 2020) 52.222-36 Equal Opportunity for Workers with Disabilities (JUN 2020) 52.222-37 Employment Reports on Veterans (JUN 2020) 52.222-40 Notification of Employee Rights Under National Labor Relations Act (DEC 2010) 52.222-50 Combating Trafficking in Persons (OCT 2020) 52.222-54 Employment Eligibility Verification (OCT 2015) 52.222-55 Minimum Wages under Executive Order 13658 (NOV 2020) 52.222-62 Paid Sick Leave Under Executive Order 13706 (JAN 2017) 52.223-2 Affirmative Procurement of Biobased Products under Service and Construction

Contracts (SEP 2013) 52.223-3 Hazardous Material Identification and Material Safety Data Alt 1 (FEB 2021) 52.223-5 Pollution Prevention and Right-to-Know Information (MAY 2011) 52.223-6 Drug-Free Workplace (MAY 2001) 52.223-15 Energy Efficiency in Energy Consuming Products (MAY 2020) 52.223-17 Affirmative Procurement of EPA-Designated Items in Service and Construction

Contracts (AUG 2018) 52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving (JUN 2020) 52.223-20 Aerosols (JUN 2016) 52.223-21 Foams. (JUN 2016)

52.225-13 Restrictions on Certain Foreign Purchases (FEB 2021) 52.227-1 Authorization and Consent (JUN 2020) 52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement (JUN 2020) 52.227-4 Patent Indemnity -- Construction Contracts (DEC 2007) 52.228-2 Additional Bond Security (OCT 1997) 52.228-5 Insurance - Work on a Government Installation (JUN 1997) 52.228-12 Prospective Subcontractor Requests for Bonds (MAY 2014) 52.228-14 Irrevocable Letter of Credit (NOV 2014) 52.229-3 Federal, State, and Local Taxes (FEB 2013) 52.232-5 Payments Under Fixed-Price Construction Contracts (MAY 2014) 52.232-17 Interest (MAY 2014) 52.232-23 Assignment of Claims (MAY 2014) 52.232-27 Prompt Payment for Construction Contracts (JAN 2017) 52.232-33 Payment by Electronic Funds Transfer – System for Award Management (OCT 2018) 52.232-39 Unenforceability of Unauthorized Obligations (JUN 2013) 52.233-1 Disputes (MAY 2014) 52.233-3 Protest After Award (AUG 1996) 52.233-4 Applicable Law for Breach of Contract Claim (OCT 2004) 52.236-2 Differing Site Conditions (APR 1984) 52.236-3 Site Investigation and Conditions Affecting the Work (APR 1984) 52.236-5 Material and Workmanship (APR 1984) 52.236-6 Superintendence by the Contractor (APR 1984) 52.236-7 Permits and Responsibilities (NOV 1991) 52.236-8 Other Contracts (APR 1984) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and

Improvements (APR 1984) 52.236-9 Operations and Storage Areas (APR 1984) 52.236-10 Use and Possession Prior to Completion (APR 1984) 52.236-11 Cleaning Up (APR 1984) 52.236-13 Accident Prevention (NOV 1991) Alternate I (NOV 1991) 52.236-14 Availability and Use of Utility Services (APR 1984) 52.236-16 Quantity Surveys (APR 1984) 52.236-17 Layout of Work (APR 1984) 52.236-21 Specifications and Drawings for Construction (FEB 1997) 52.236-26 Preconstruction Conference (FEB 1995) 52.242-13 Bankruptcy (JUL 1995) 52.243-4 Changes (JUN 2007) 52.244-6 Subcontracts for Commercial Items (NOV 2020)(DEVIATION APR 2020) 52.246-21 Warranty of Construction (MAR 1994) 52.248-3 Value Engineering – Construction (OCT 2020) 52.249-2 Termination for Convenience of the Government (Fixed-Price) (APR 2012)--

Alternate I (SEP 1996) 52.249-10 Default (Fixed-Price Construction) (APR 1984) 52.253-1 Computer Generated Forms (JAN 1991)

AGRICULTURE ACQUISITION REGULATION (48 CFR CHAPTER 4) CLAUSES

452.232-70 Reimbursement for Bond Premiums – Fixed-Price Construction Contracts (NOV

1996) 452.236-71 Prohibition Against the Use of Lead-Paint (NOV 1996) 452.236-72 Use of Premises (NOV 1996) 452.236-73 Archeological or Historic Sites (FEB 1988) 452.236-74 Control of Erosion, Sedimentation and Pollution (NOV 1996) 452.236-76 Samples and Certificates (FEB 1988) 452.236-77 Emergency Response (NOV 1996)

I-2 OPTION FOR INCREASED QUANTITY – SEPARATELY PRICED LINE ITEM

(FAR 52.217-7)(MAR 1989)

The Government may require the delivery of the numbered line item, identified in the Schedule as an option item, in the quantity and at the price stated in the Schedule. The Contracting Officer may exercise the option by written notice to the Contractor:

Option 1 (Phase 2): within one year of base contract award Option 2 (Phase 3): within one year of option item 1 award Option 3 (Phase 4): within one year of option item 1 award

I-3 FAR 52.225-11 BUY AMERICAN ACT-CONSTRUCTION MATERIALS UNDER

TRADE AGREEMENTS (JAN 2021)(DEVIATION JUL 2020)

(a) Definitions. As used in this clause-

Caribbean Basin country construction material means a construction material that–

(1) Is wholly the growth, product, or manufacture of a Caribbean Basin country; or

(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in a Caribbean Basin country into a new and different construction material distinct from the materials from which it was transformed.

Commercially available off-the-shelf (COTS) item-

(1) Means any item of supply (including construction material) that is-

(i) A commercial item (as defined in paragraph (1) of the definition at Federal Acquisition Regulation (FAR) 2.101);

(ii) Sold in substantial quantities in the commercial marketplace; and

(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and

(2) Does not include bulk cargo, as defined in 46 U.S.C.40102(4), such as agricultural products and petroleum products.

Component means an article, material, or supply incorporated directly into a construction material.

Construction material means an article, material, or supply brought to the construction site by the Contractor or subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.

Cost of components means-

(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or

(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.

Designated country means any of the following countries:

(1) A World Trade Organization Government Procurement Agreement (WTO GPA) country (Armenia, Aruba, Australia, Austria, Belgium, Bulgaria, Canada, Croatia, Cyprus, Czech Republic, Denmark, Estonia, Finland, France, Germany, Greece, Hong Kong, Hungary, Iceland, Ireland, Israel, Italy, Japan, Korea (Republic of), Latvia, Liechtenstein, Lithuania, Luxembourg, Malta, Moldova, Montenegro, Netherlands, New Zealand, Norway, Poland, Portugal, Romania, Singapore, Slovak Republic, Slovenia, Spain, Sweden, Switzerland, Taiwan, Ukraine, or United Kingdom);

(2) A Free Trade Agreement (FTA) country (Australia, Bahrain, Canada, Chile, Colombia, Costa Rica, Dominican Republic, El Salvador, Guatemala, Honduras, Korea (Republic of), Mexico, Morocco, Nicaragua, Oman, Panama, Peru, or Singapore);

(3) A least developed country (Afghanistan, Angola, Bangladesh, Benin, Bhutan, Burkina Faso, Burundi, Cambodia, Central African Republic, Chad, Comoros, Democratic Republic of Congo, Djibouti, Equatorial Guinea, Eritrea, Ethiopia, Gambia, Guinea, Guinea-Bissau, Haiti, Kiribati, Laos, Lesotho, Liberia, Madagascar, Malawi, Mali, Mauritania, Mozambique, Nepal, Niger, Rwanda, Samoa, Sao Tome and Principe, Senegal, Sierra Leone, Solomon Islands, Somalia, South Sudan, Tanzania, Timor-Leste, Togo, Tuvalu, Uganda, Vanuatu, Yemen, or Zambia); or

(4) A Caribbean Basin country (Antigua and Barbuda, Aruba, Bahamas, Barbados, Belize, Bonaire, British Virgin Islands, Curacao, Dominica, Grenada, Guyana, Haiti, Jamaica, Montserrat, Saba, St. Kitts and Nevis, St. Lucia, St. Vincent and the Grenadines, Sint Eustatius, Sint Maarten, or Trinidad and Tobago).

"Designated country construction material" means a construction material that is a WTO GPA country construction material, an FTA country construction material, a least developed country construction material, or a Caribbean Basin country construction material.

Domestic construction material means-

(1) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both-

(i) An unmanufactured construction material mined or produced in the United States; or

(ii) A construction material manufactured in the United States, if-

(A) The cost of its components mined, produced, or manufactured in the United States exceeds 55 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic. Components of unknown origin are treated as foreign; or

(B) The construction material is a COTS item; or

(2) For construction material that consists wholly or predominantly of iron or steel or a combination of both, a construction material manufactured in the United States if the cost of foreign iron and steel constitutes less than 5 percent of the cost of all components used in such construction material. The cost of foreign iron and steel includes but is not limited to the cost of foreign iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the construction material and a good faith estimate of the cost of all foreign iron or steel components excluding COTS fasteners. Iron or steel components of unknown origin are treated as foreign. If the construction material contains multiple components, the cost of all the materials used in such construction material is calculated in accordance with the definition of "cost of components".

Fastener means a hardware device that mechanically joins or affixes two or more objects together. Examples of fasteners are nuts, bolts, pins, rivets, nails, clips, and screws.

Foreign construction material means a construction material other than a domestic construction material.

Foreign iron and steel means iron or steel products not produced in the United States. Produced in the United States means that all manufacturing processes of the iron or steel must take place in the United States, from the initial melting stage through the application of coatings, except metallurgical processes involving refinement of steel additives. The origin of the elements of the iron or steel is not relevant to the determination of whether it is domestic or foreign.

Free Trade Agreement country construction material means a construction material that-

(1) Is wholly the growth, product, or manufacture of a Free Trade Agreement (FTA) country; or

(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in a FTA country into a new and different construction material distinct from the materials from which it was transformed.

Least developed country construction material means a construction material that-

(1) Is wholly the growth, product, or manufacture of a least developed country; or

(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in a least developed country into a new and different construction material distinct from the materials from which it was transformed.

Predominantly of iron or steel or a combination of both means that the cost of the iron and steel content exceeds 50 percent of the total cost of all its components. The cost of iron and steel is the cost of the iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the product and a good faith estimate of the cost of iron or steel components excluding COTS fasteners.

Steel means an alloy that includes at least 50 percent iron, between 0.02 and 2 percent carbon, and may include other elements.

United States means the 50 States, the District of Columbia, and outlying areas.

WTO GPA country construction material means a construction material that-

(1) Is wholly the growth, product, or manufacture of a WTO GPA country; or

(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in a WTO GPA country into a new and different construction material distinct from the materials from which it was transformed.

(b) Construction materials. (1) This clause implements 41 U.S.C.chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C.1907, the domestic content test of the Buy American statute is waived for construction material that is a COTS item, except that for construction material that consists wholly or predominantly of iron or steel or a combination of both, the domestic content test is applied only to the iron and steel content of the construction material, excluding COTS fasteners. (See FAR 12.505(a)(2)). In addition, the Contracting Officer has determined that the WTO GPA and Free Trade Agreements (FTAs) apply to this acquisition. Therefore, the Buy American restrictions are waived for designated country construction materials.

(2) The Contractor shall use only domestic or designated country construction material in performing this contract, except as provided in paragraphs (b)(3) and (b)(4) of this clause.

(3) The requirement in paragraph (b)(2) of this clause does not apply to information technology that is a commercial item or to the construction materials or components listed by the Government as follows:

"none"

(4) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(3) of this clause if the Government determines that-

(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the restrictions of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent;

(ii) The application of the restriction of the Buy American Act to a particular construction material would be impracticable or inconsistent with the public interest; or

(iii) The construction material is not mined, produced, or manufactured…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .