This is a Task Assignment Notification Form and Scope of Work issued by the Florida Department of Environmental Protection (FDEP) under the Resilient Florida Program. The task assignment (Contract No. CN327, Task Assignment No. 9) engages Aptim Environmental & Infrastructure, Inc. as the consultant, with Samantha Danchuk serving as the consultant representative and Ralph Perkins as the FDEP Contract Manager. The project, titled "Florida Adaptation Planning Guidebook Support," is designated as Project No. FLAPG2 and falls under the FDEP-RCP (Resilient Coastal Planning) owner entity.

The contract requires Aptim to complete three primary tasks: facilitate a virtual workshop to gather stakeholder input on local high tide flooding thresholds (due October 31, 2024, valued at $10,680.00); perform maintenance and updates to the Florida Adaptation Planning Guidebook including the workshop outcomes (due December 13, 2024, valued at $10,680.00); and conduct a live webinar to present guidebook updates to stakeholders with a recorded PowerPoint presentation for public posting (due February 28, 2025, valued at $8,720.00). The total fixed-price task assignment is $30,080.00, with a start date upon execution and completion by February 28, 2025. Payment is contingent upon written acceptance of deliverables by FDEP's Contract Manager within ten business days, with penalties of $50.00 per day assessed for late deliverables. Interim payments are not accepted, and the vendor must submit invoices only after task completion and formal acceptance.

View the file

Other files

File Type Posted
CN-370000-CN327-CMC1.pdf PDF
CN-370000-CN327-CMC3.pdf PDF
CN-370000-CN327-CMC4.pdf PDF
CN-370000-CN327-T1CO1.pdf PDF
CN-370000-CN327-T1CO3.pdf PDF
CN-370000-CN327-T4CO3.pdf PDF
CN-370000-CN327-CMC2.pdf PDF
CN-370000-CN327-T1.pdf PDF
CN-370000-CN327-T1CO2.pdf PDF
CN-370000-CN327-T1CO4.pdf PDF
CN-370000-CN327-T2CO1.pdf PDF
CN-370000-CN327-T3.pdf PDF
CN-370000-CN327-T3CO1.pdf PDF
CN-370000-CN327-T3CO2.pdf PDF
CN-370000-CN327-T4CO1.pdf.crdownload CRDOWNLOAD file
CN-370000-CN327-T4CO2.pdf PDF
CN-370000-CN327-T8.pdf PDF
CN-370000-CN327-A1.pdf PDF
CN-370000-CN327-A2.pdf PDF
CN-370000-CN327-CMC5.pdf PDF
CN-370000-CN327-T5CO2.pdf PDF
CN-370000-CN327-T6.pdf PDF
CN-370000-CN327-T7.pdf PDF
CN-370000-CN327.pdf PDF
CN-370000-CN327-T2.pdf PDF
CN-370000-CN327-T4.pdf PDF
CN-370000-CN327-T4CO1.pdf PDF
CN-370000-CN327-T5.pdf PDF
CN-370000-CN327-T5CO1.pdf PDF
CN-370000-CN327-T9CO1.pdf PDF
CN-370000-CN327-T9CO2.pdf PDF
Show all 31

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Florida Department of Environmental Protection

TASK ASSIGNMENT NOTIFICATION FORM

Required Signatures: Adobe Signature

FDEP Contract No.: Task Assignment No.: Owner’s Name: Project No.:

Project Location: Project Name:

Consultant Name:

Consultant Representative: Phone: Email:

FDEP Contract Manager: Phone: Email:

Description of Task:

Project Manager:

Schedule Start Date: Fixed Price Cost:

Completion Date: Cost Reimbursement not to exceed:

Total Task Amount:

Approval Signatures:

Budget Representative, FDEP Signature Date

Project Manager, FDEP Signature Date

Contract Manager, FDEP Signature Date

Consultant Signature Date

Contract Authority, FDEP Signature Date

Project # Grant # Org Code Cat/Year Fund Module Object Code EOEO Amount

2929 digit FLAIR Code: Total:

CN327 9 FDEP-RCP FLAPG2

FDEP-RCP Florida Adaptation Planning Guidebook Support

Aptim Environmental & Infrastructure, Inc.

Samantha Danchuk 561-361-3199 Samantha.Danchuk@Aptim.com

Ralph Perkins oror successor 850-245-2460 ralph.perkins@floridadep.gov

The contractor will hold a public workshop toto gather data for local high tide flooding thresholds toto bebe included inin the

Florida Adaptation Planning Guidebook (FLAPG), hold anan additional webinar toto update stakeholders onon changes made toto the FLAPG, provide the Program with a recorded PowerPoint video, and update the FLAPG asas directed.

Krista Slyter

Upon Execution $ 30,080.00 February 28, 2025

$ 30,080.00

Ashley Larson

Krista Slyter

Ralph Perkins

Samantha Danchuk, Aptim

Eddy Bouza 8/27/2024

FLAPG2 37538010010 100777/00 055010 U1672 131353 3E3E $ 30,080.00

$ 30,080.0037202055010375004000010077700

Digitally signed by: Ashley Larson

DN: CN = Ashley Larson email = Ashley.M.

Larson@Floridadep.gov C = AD

Date: 2024.08.22 08:55:53 -04'00' Ashley Larson

Digitally signed by: Krista Slyter

DN: CN = Krista Slyter email = krista.slyter@floridadep.gov C =

US O = FL Dept. of Environmental Protection OU = Resilient

Florida - Planning and Policy

Date: 2024.08.23 10:11:31 -04'00'

Krista Slyter

Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2024.08.23 11:48:24 -04'00'

Danchuk, Samantha Digitally signed by Danchuk, Samantha Date: 2024.08.26 18:07:42 -04'00'

Digitally signed by Eddy Bouza Date: 2024.08.27 12:49:05 -04'00'

SCOPE OF WORK

RESILIENT FLORIDA PROGRAM

FLORIDA ADAPTATION PLANNING GUIDEBOOK SUPPORT

PURPOSE: This task assignment is work with the Resilient Florida Program (Program) to facilitate and

<BFG 0 N=EGM0? OBE>F<BC GB ;0G<4E FG0>4<B?34E =ACMG 5BE F4KA; ?B20? <=;< H34 9BB3=A; G<E4F<B?3F O<=2<

F<0?? G<4A 14 =A2BECBE0G43 =A 0 E4N=F43 %?BE=30 "30CG0HBA 0A3 *?0AA=A; &M=341BB>U ,<4 .4A3BE O=?? 0?FB

<BFG 0 ?=N4 O41=A0E 5BE FG0>4<B?34EF O<=2< F<0?? BMG?=A4 G<4 2<0A;4F @034 GB G<4 %?BE=30 "30CG0HBA

*?0AA=A; &M=341BB> Y%("*&Z 0A3 CEBN=34 G<4 *EB;E0@ 0 E42BE343 *BO4E*B=AG CE4F4AG0HBA O<=2< O=?? 14

CBFG43 5BE FG0>4<B?34E MF4 BA G<4 *EB;E0@VF O41F=G4U ,<4 .4A3BE O=?? 0?FB MC30G4 G<4 %?BE=30 "30CG0HBA

(6+ &4(66260 $<2+,)773 (: (<;1792A,+ )@ &9709(5 :;(.C

Task 1: Future High Tide Flooding Threshold Workshop

Descrip on: "CH@ O=?? 502=?=G0G4 BA4 Y]Z N=EGM0? OBE>F<BC GB E424=N4 FG0>4<B?34E =ACMG BA A443F 0A3

0CCEB02< 5BE F4KA; G<4 G<E4F<B?3 5BE 5MGME4 <=;< H34 9BB3=A; 0F 34F2E=143 =AT 0A3 5BE G<4 CMECBF4 B5

@44HA; G<4 =AG4AG B5T FU _b\U\c_Y_ZY3ZY^ZY0ZT %U+U "*,') O=?? 2BA3M2G ?=G4E0GME4 E4N=4O 0A3 =AG4EN=4O MC

GB 7N4 YaZ FG0>4<B?34EF =A 03N0A24 B5 G<4 OBE>F<BC GB BMG?=A4 2MEE4AG CE02H24T 0;4A2Q C4EFC42HN4F 0A3

0N0=?01?4 30G0F4GF E4?0G43 GB <=;< H34 9BB3=A; G<E4F<B?3F =A %?BE=30U ,<4 *EB;E0@ O=?? CEBN=34 0A =A=H0?

?=FG B5 FG0>4<B?34EF GB BCHBA0??Q 4A;0;4U ,<4 OBE>F<BC O=?? 14 502=?=G0G43 GB B1G0=A 2BAF4AFMF BA BA4 BE

579, (**,8;()4, 5,;17+:C " 87:; >793:178 :<9=,@ >244 ), 5(26;(26,+ -79 ;129;@ EHGF +(@: ;7 *76/95 ;1, proposed methodology(ies) and/or suite of metrics is applicable to use cases across the state. The email

3=FGE=1MHBA ?=FG 5BE FG0>4<B?34E =ACMG OBE>F<BC 3ME=A; G<4 34N4?BC@4AG B5 G<4 %("*& O=?? 14 MF43 5BE

@44HA; BMGE402<T E4@=A34EFT N=EGM0? <BFHA;T 0;4A30 34N4?BC@4AG 0A3 BG<4E @0E>4HA; @0G4E=0?FU

'AN=G0HBAF GB G<4 O41=A0E O=?? 14 3=FGE=1MG43 0G ?40FG G<=EGQ Y_\Z 30QF CE=BE GB G<4 @44HA; 0A3 O=G<=A BA4

Y]Z O44> B5 4P42MHBA B5 G<=F G0F> 0FF=;A@4AGU ,<4 %("*& O=?? 14 MC30G43 GB =A2?M34 G<4 BMG2B@4 B5 G<4

OBE>F<BC 0A3 @4GE=2 5BE G<4 G<E4F<B?3 H30? 9BB3=A;U

Deliverables:

� 1.1: /BE>F<BC 0;4A30 GB =A2?M34 ?B20HBAT 30G4 0A3 H@4 B5 @44HA;U

� 1.2: )44HA; F=;AX=A F<44GF BE 0J4A30A24 E42BE3F O=G< 0J4A344 A0@4F 0A3 08?=0HBAU

� 1.3: " 2BCQ B5 G<4 CE4F4AG0HBAYFZ 0A3 0AQ @0G4E=0?F 2E40G43 5BE 3=FGE=1MHBAU

� 1.4: A summary of the input received during interviews and workshop and outcomes to include

A0@4T HG?4T 0A3 08?=0HBA B5 =AG4EN=4O44FU

Due Date: October 31, 2024

Task 2: Maintenance of Florida Adapta on Planning Guidebook

Descrip on: APTIM will complete maintenance tasks for the FLAPG to include adding the outcomes of

,0F> ]T 0A3 033=HBA0??QT O<4A BG<4EO=F4 0MG<BE=R43 1Q G<4 *EB;E0@VF FG06 FB ?BA; 0F FM2< @0=AG4A0A24

=F O=G<=A G<4 ,0F> 1M3;4GU ,0F>F @0Q =A2?M34 E4N=F=A; G4PG 0A3 ;E0C<=2FT OE=HA; 0A3 FM1@=KA;

2BA54E4A24 01FGE02GF GB CEB@BG4 MF4 B5 ;M=341BB>T 0A3 34N4?BC=A; CE4F4AG0HBA @0G4E=0?F GB 0FF=FG =A the use of the guidebook.

Deliverables:

� 2.1: %=A0? E4N=F43 %("*& =A2?M3=A; F42HBA E4;0E3=A; 5MGME4 <=;< H34 9BB3=A;

G<E4F<B?3FW@4G<B3B?B;QY=4FZU *M1?=20HBA 5BE@0KA; @MFG 14 FM=G01?4 5BE bUaP]] BE "`

CM1?=20HBA F=R4U

� 2.2: Copies of all materials developed to promote use of the FLAPG.

Due Date: December 13, 2024

Task 3: Adapta on Planning Guidebook Update Webinar

Descrip on: APTIM will facilitate one (1) live virtual webinar to highlight the updates made to the guidebook, explain the prompts for updates and review the approach included in the guidebook for

030CG0HBA C?0AA=A;U ,<4 4@0=? 3=FGE=1MHBA ?=FG MF43 5BE FG0>4<B?34E =ACMG OBE>F<BC 3ME=A; G<4

;M=341BB> 34N4?BC@4AG O=?? 14 MF43 5BE @44HA; BMGE402<T E4@=A34EFT N=EGM0? <BFHA;T 0;4A30

34N4?BC@4AG 0A3 BG<4E @0E>4HA; @0G4E=0?FU 'AN=G0HBAF GB G<4 O41=A0E O=?? 14 3=FGE=1MG43 0G ?40FG G<=EGQ

Y_\Z 30QF CE=BE GB G<4 @44HA;U "*,') O=?? E42BE3 0 *BO4E*B=AG *E4F4AG0HBA 2BN4E=A; G<4 F0@4 2BAG4AG as the live webinar for the Program to post on its website and make publicly available for all Grantees.

Deliverables:

� 3.1: /41=A0E 0;4A30 GB =A2?M34 ?B20HBAT 30G4 0A3 H@4 B5 @44HA;U

� 3.2: )44HA; 0J4A30A24 E42BE3F O=G< 0J4A344 A0@4F 0A3 08?=0HBA Y=5 0N0=?01?4 34C4A3=A; BA

G<4 FB:O0E4WE4;=FGE0HBA CEB24FFZU

� 3.3: " 2BCQ B5 G<4 CE4F4AG0HBAYFZ 0A3 0AQ @0G4E=0?F 2E40G43 5BE 3=FGE=1MHBA 0G G<4 @44HA;T 0F applicable.

� 3.4: " ?=FG B5 DM4FHBAF 0A3 2B@@4AGF E424=N43 3ME=A; G<4 FG0>4<B?34E @44HA;U

� 3.5: A summary of the input received and outcomes.

� 3.6: " E42BE343 *BO4E*B=AG CE4F4AG0HBA 2BN4E=A; F0@4 2BAG4AG 0F G<4 ?=N4 O41=A0EU

Due Date: February 28, 2025

PERFORMANCE STANDARD: The Vendor will submit all deliverables for each task to the Program’s

Contract Manager on or before the deliverable due date listed within the task. The Program’s Contract

Manager and Project Manager will review the deliverable(s) to verify that they meet all required

FC42=720HBAFU ,<4 *EB;E0@VF #BAGE02G )0A0;4E O=?? CEBN=34 OE=J4A 0224CG0A24 BE 34A=0? B5 G<4

34?=N4E01?4YFZ GB G<4 .4A3BE O=G<=A G4A Y]\Z 1MF=A4FF 30QF MA?4FF E4FCBAF4 H@4 =F FC42=743 BG<4EO=F4 =A this scope of work.

CONSEQUENCES FOR NON-PERFORMANCE: For each task deliverable not received by the Department

0G BA4 <MA3E43 C4E24AG Y]\\fZ 2B@C?4HBA 0A3 1Q G<4 FC42=743 3M4 30G4 ?=FG43T G<4 $4C0EG@4AG O=??

reduce the Vendor’s invoice by $50.00 for each day the deliverable is not received.

PAYMENT REQUEST SCHEDULE: %B??BO=A; G<4 2B@C?4HBA B5 0 G0F>VF 34?=N4E01?4YFZ 0A3 OE=J4A

(**,8;(6*, )@ ;1, &9709(5D: #76;9(*; %(6(0,9B ',6+79 5(@ :<)52; (6 26=72*, (; ;1, /?,+ 9(;, -79 ;1, deliverable(s) as shown in the Project Timeline and Budget Detail table. Interim payments will not be

0224CG43U -CBA G<4 $4C0EG@4AGVF E424=CG B5 G<4 05BE4@4AHBA43 3B2M@4AGF 0A3 FMCCBEHA; 7F20?

3B2M@4AG0HBAT G<4 *EB;E0@VF #BAGE02G )0A0;4E O=?? <0N4 G4A Y]\Z OBE>=A; 30QF GB E4N=4O 0A3 0CCEBN4 or deny the payment request.

Project Timeline and Budget Detail:

Task Task Title Due Date Fixed-Price Cost

1 Future High Tide Flooding Threshold Workshop October 31, 2024 $10,680.00

2 )0=AG4A0A24 B5 %?BE=30 "30CG0HBA *?0AA=A;

Guidebook

December 13, 2024 $10,680.00

3 "30CG0HBA *?0AA=A; &M=341BB> Update

Webinar

February 28, 2025 $8,720.00

Total Task Assignment: $30,080.00