About this file
This is a Task Assignment Notification Form (Task Assignment No. 03) issued by the Florida Department of Environmental Protection (FDEP) under the professional services agreement with APTIM Environmental & Infrastructure, LLC for the St. Lucie Inlet Preserve State Park Buoy Reestablishment Project. The contract is executed under FDEP Contract No. CN327, with project management oversight by FDEP's Bureau of Design and Construction located in Tallahassee, Florida. APTIM, represented by Douglas W. Mann, P.E., D.C.E., serves as the consulting firm responsible for project delivery under the direction of FDEP Contract Manager Jeffrey Whitfield.
The scope of services encompasses design and necessary permits to allow for buoy replacement and boundary limit establishment within the park, with work to be advertised for competitive bidding. The project is structured into six subtasks: Subtask 1 (Bathymetric and Sub-bottom Survey) at $24,712.92; Subtask 2 (optional Benthic Survey) at $16,260.12; Subtask 3 (Engineering) at $7,022.68; Subtask 4 (State and Federal Permitting) at $13,368.36; Subtask 5 (Final Plans and Specifications) at $4,199.00; and Subtask 6 (Project Meeting) at $1,291.68. The total contract value is $66,854.76 on a fixed-price basis with no reimbursable costs, with payment contingent upon FDEP approval of deliverables for each subtask. The project period runs from November 18, 2021, to November 18, 2022, with individual subtasks ranging from 30 to 270 calendar days in duration.
View the file
Other files
Show all 31
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT NOTIFICATION FORM
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Owner’s Name: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description of Task:
Project Manager:
Schedule Start Date: Fixed Price Cost:
Completion Date: Cost Reimbursement not to exceed:
Total Task Amount:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 digit FLAIR Code: Total:
CN327 03 APTIM Environmental &Inf. 61394C
St. Lucie Inlet State Park Buoy Replacements
APTIM Environmental & Infrastructure, LLC
Douglas W. Mann 561-361-3148 douglas.mann@APTIM.com
Jeff Whitfield 850-245-2630 jeffreywhitfield@floridadep.gov
Provide design and necessary permits to allow for Buoy replacement and boundary limits within the Park. Scope will allow for project to be advertised for Bid. See attache dated 11/18/21.
Jim McGuire
November 18,2021 $ 66,854.76 November 18, 2022
$ 66,854.76
Greg Turral Gregory Turral Digitally signed by Gregory Turral Date: 2022.01.05 16:44:57 -05'00'
Jim McGuire James McGuire Digitally signed by James McGuire Date: 2022.01.06 09:02:42 -05'00'
Jeffrey Whitfield Jeffrey Whitfield Digitally signed by Jeffrey Whitfield Date: 2022.02.02 09:23:38 -05'00'
Douglas Mann Douglas W Mann Digitally signed by Douglas W Mann Date: 2022.02.02 13:41:00 -05'00'
Michael W. Foster Jr., P.E. Michael W. Foster Jr.
Digitally signed by Michael W.
Foster Jr.
Date: 2022.02.08 09:06:59 -05'00'
61394C 37505000070 080039/22 423001 U3200 131500 QK $ 66,854.76
$ 0.00
Douglas Mann, P.E., D.CE.
Lead Coastal Engineer
Coastal Restoration Team
APTIM
2481 NW Boca Raton Blvd
Boca Raton FL 33431 Tel: +1 561 361 3148 Fax: +1 561 391 9116
Douglas.Mann@aptim.com
November 18, 2021
Jim McGuire Florida Department of Environmental Protection Bureau of Design and Construction 3800 Commonwealth Boulevard Tallahassee, FL 32399
RE: Contract No. CN327 TA03 St. Lucie Inlet Preserve State Park Buoy Reestablishment Project
Dear Mr. McGuire:
Aptim Environmental & Infrastructure, LLC (APTIM) is submitting this proposal in response to your request for coastal engineering, surveying, and regulatory services to reestablish boundary buoys and mooring buoys in the Atlantic Ocean offshore of St. Lucie Inlet Preserve State Park (Park). A scope of services with cost breakdown is included in Appendix A.
The proposed subtasks identified herein will be performed under and governed by the terms and conditions of the Professional Services Agreement between APTIM and the Florida Department of Environmental Protection (FDEP), titled DEP CN327 for a lump sum total of $66,854.76. A cost breakdown is included in Appendix A. Please authorize us to begin by executing a Task Assignment to perform the requested services in the name of our licensed contracting entity Aptim Environmental & Infrastructure, LLC.
If you have any questions, please call me.
Very truly yours, Douglas W. Mann, P.E., D.CE.
Lead Coastal Engineer Aptim Environmental & Infrastructure, LLC
Appendix A.
Scope of Services and Cost Breakdown St Lucie Inlet Preserve State Park Buoy Reestablishment
Introduction
The Park has previously established boundary buoys within the Atlantic Ocean to demark the limits of the park and a set of mooring buoys within the park boundary. The Park has provided a list of coordinates of the intended locations. At present there is no known source of information regarding the ocean bottom conditions (physical or biological) at each buoy location that is required to support design efforts and regulatory approvals. Preliminary discussions with the FDEP Southeast District Office and the USACE Cocoa Beach regulatory office were accomplished in preparing this proposal. The following subtasks are proposed:
Subtask 1:
Description: Subtask 1 Bathymetric and Sub-bottom survey. A bathymetric survey of the specific coordinate areas (24 sites) will be performed. An approximate 100 by 100 foot area will be surveyed.
If there is nearshore hardbottom at any location, an equivalent location nearby may be adopted in the field such that impacts from the installation or operation of the buoys will not impact nearshore hardbottom resources (See additional discussions under Subtasks 2,and 4).
All survey and hydrographic work shall be conducted under the direct supervision of a Florida Professional Surveyor and Mapper as well as an American Congress of Surveying and Mapping Certified Hydrographer and will be in accordance with Chapter 5J-17 Florida Administrative Code (F.A.C.)
pursuant to Chapter 472 of the Florida Statutes (FS).
Prior to the start of the survey, reconnaissance of published National Geodetic Survey (NGS) and/or FDEP survey control monuments will be conducted using Global Navigation Satellite System (GNSS) receivers relative to the Florida Permanent Reference Network (FPRN). GNSS and/or Static GNSS techniques will be used to locate and confirm survey control for this project. Static GNSS methods will be utilized to establish temporary benchmarks (TBMs) if the existing survey control is disturbed or insufficient to cover the entire survey area. Horizontal and vertical positioning checks will be conducted at the beginning and end of each survey day. All positions will be collected in US survey feet relative to the North American Datum of 1983/2011 (NAD 83/11). All vertical data will be collected in US survey feet relative to the North American Vertical Datum of 1988 (NAVD 88), Geoid 18.
At each site, a jet probe will be performed to determine the depth of sand at each location. This will be performed by APTIM field crews while scuba diving. All diving will follow AAUS safety standards.
Survey services will include:
1. Bathymetric data will be collected within the boundary/exclusion buoy corridor to establish general bathymetric condition.
2. Bathymetric data will be collected within approximately 150 of each mooring buoy proposed coordinates
3. A jet probe at each proposed buoy location will be performed by APTIM scuba divers.
Survey Methods:
All data will be collected using GNSS receivers relative to the Florida Permanent Reference Network (FPRN) If hydrographic (sounding data) is required, data will be collected along transects using an Odom E20 sounder with digitizer on APTIM's 24-foot survey vessel or equivalent, with a centrally located hull-mounted transducer.
Upon completion of the field work, data will be processed using APTIM’s internal software programs, Trimble Business Center, and HYPACK. The offshore data will be processed using HYPACK and an ASCII XYZ file will be created and exported for plan view map and planning purposes.
Deliverable: The final deliverable will include a bathymetric survey map, certified by a registered Florida Surveyor and Mapper, digital data files (XYZ and AutoCAD (.dwg)) and field notes as deliverables for the surveying efforts.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 1
Firm Name Position Classification Hourly Rate
Hours Total Fixed Price Cost
APTIM Professional Surveyor & Mapper
$138.48 40 $5,539.20
APTIM Surveyor $79.95 76 $6,076.20 APTIM Survey Technician $68.31 96 $6,557.76 APTIM CAD Operator $98.07 12 $1,176.84 APTIM Marine Biologist I $90.00 56 5,040.00 APTIM Sr. Coastal Engineer $161.46 2 $322.92
Fixed Price Cost: $24,712.92
Reimbursable Cost: $0.00
Total for Subtask 1: (Fixed Price Cost + Reimbursable) $24,712.92
Subtask 2 (optional):
Description: Subtask 2 (optional). Benthic Survey If required by State or Federal regulatory agencies, APTIM biologists will conduct a benthic resource investigation to identify any benthic resources (i.e., hardbottom) that may be present at each boundary buoy and mooring buoy coordinate, including a 50 ft. buffer around each coordinate. Qualitative benthic data will be collected to characterize the resources observed at each site. If hardbottom is observed, the edge adjacent to the site shall be delineated. Representative photographs and/or video will be collected to supplement the data. This survey is not meant to provide the level of data required for mitigation planning as it is assumed that any areas of hardbottom resources will be avoided in the buoy installation design.
Deliverable: The final deliverables will include an observation report (in pdf) with map overlaid on recent aerial imagery. If benthic resources are documented during the assessment, the report will provide the location/delineation of those resources with a qualitative description and representative photographs.
Digital shapefiles of any hardbottom resources documented during the survey will also be provided.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 2
Firm Name Position Classification Hourly Rate
Hours Total Fixed Price Cost
APTIM Survey Technician $68.31 72 $4,918.32 APTIM Sr. Marine Biologist $132.48 56 $7,418.88 APTIM Marine Biologist I $90.00 40 $3,600.00 APTIM Sr. Coastal Engineer $161.46 2 $322.92
Fixed Price Cost: $16260.12
Total for Subtask 2: (Fixed Price Cost + Reimbursable) $16,260.12
Subtask 3:
Description: Subtask 3 Engineering. An APTIM coastal engineer will design appropriate buoy and anchoring systems for the boundary and mooring systems. An inspection of the materials stored within the Park facilities will be performed for documentation, and quantification. This inspection will determine the suitability of these existing materials.
Deliverable: 30 % plans will be produced in pdf format
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 3
Firm Name Position Classification Hourly Rate
Hours Total Fixed Price Cost
APTIM Coastal Engineer II
$130.00 40
$5,200.00
APTIM Sr. Coastal Engineer $161.46 4 $645.84
APTIM CAD Operator $98.07 12 $1,176.84 Fixed Price Cost: $7,022.68
Reimbursable Cost: $0.00
Total for Subtask 3: (Fixed Price Cost + Reimbursable) $7,022.68
Subtask 4:
Description: Subtask 4 State and Federal Permitting. APTIM will develop permit applications for the reestablishment of the boundary and mooring buoys. Preapplication phone calls with the FDEP and the USACE suggested that the buoys could be permitted with either FDEP exemptions, FDEP general permits, and USACE Nationwide permits. The expected effort is based on these types of permits.
The USACE suggested that consultation under the Endangered Species Act with the federal resource agencies may be required which will extend the federal permitting time frames. We will address questions of the federal resource agencies based on existing information. The USACE also indicated that installing anchors directly into hardbottom may not permittable under a Nationwide Permit. Locating an area nearby may be required. If either the FDEP, USACE, or federal resource agencies require additional field data (subtask 2), we will notify the FDEP BDC.
Deliverable: Permit applications with permit sketches will be provided to FDEP as a deliverable (pdf format). Copies of correspondence will be provided in pdf format.
Performance Measure: Deliverables will be reviewed by FDEP to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 4
Firm Name Position Classification Hourly Rate
Hours Total Fixed
APTIM Sr. Coastal Engineer
$161.46 8 $1,291.68
APTIM Coastal Engineer III $130.00 72 $9360.00 APTIM GIS Operator $120.00 4 $ 480.00 APTIM CAD Operator $98.07 12 $1,176.84 APTIM Sr. Marine Biologist $132.48 8 $1,059.84
Fixed Price Cost: $13,368.36
Reimbursable Cost: $0.00
Total for Subtask 4 (Fixed Price Cost + Reimbursable) $13,368.36
Subtask 5:
Description: Subtask 5 Final plans and Specifications. Final plans and technical specifications will be produced suitable for bidding the work.
Deliverable: 100 % plans and technical specifications will be provided in pdf format.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 5
Firm Name Position Classification Hourly Rate
Hours Total Fixed
$161.46 8 $1,291.68
APTIM Coastal Engineer III $130.00 8 $1,040.00 APTIM CAD Operator $98.07 16 $1,569.12 APTIM Clerical $74.55 4 $298.20
Fixed Price Cost: $4,199.00
Total for Subtask 5: (Fixed Price Cost + Reimbursable) $4,199.00
Subtask 6:
Description: Subtask 6. Meeting. APTIM will attend one meeting with Park and District staff to discuss the development of the project. The meeting will be informal and no formal presentation will be made.
The meeting will be at the Park or District office.
Deliverable: Meeting minutes will be provided in pdf format.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 6
Firm Name Position Classification Hourly Rate
Hours Total Fixed
$161.46 8 $1291.68
Fixed Price Cost: $1,291.68
Reimbursable Cost: $0.00
Total for Subtask 6: (Fixed Price Cost + Reimbursable) $1,291.68
Project Schedule:
Activity Duration (Calendar Days) Dates Subtask 1: 45 days from Notice to
Proceed To be scheduled
Subtask 2:
120 days from Notice to Proceed
To be scheduled
Subtask 3: 75 days from Notice to Proceed
To be scheduled
Subtask 4: 270 days from Notice to Proceed
To be scheduled
Subtask 5: 30 days from Notice to Proceed
To be scheduled
Subtask 6: 270 days from receipt of comments
To be scheduled
Summary of Fees:
Subtask Subtask Fixed Price Cost Subtask Reimbursable Subtask 1: $24,712.92 $ 0.00
Subtask 2: $16,260.12 $ 0.00
Subtask 3: $ 7,022.68 $ 0.00
Subtask 4: $ 13,368.36 $ 0.00
Subtask 5: $ 4,199.00
$ 0.00
Subtask 6: $ 1,291.68 $ 0.00
Total Fixed Price Cost: $66,854.76 Total Reimbursable Cost: $ 0.00
Overall Total Cost: $66,854.76
Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified. (Please do not alter this language)
| CN327 TA3.pdf |