CN-370000-CN327-T3CO1.pdf
PDF 2 MB Posted
- Contract number
- CN327
- Issued by
- Florida
About this file
This is a Task Assignment Change Order Form (Change Order No. 1) issued by the Florida Department of Environmental Protection (FDEP) for Contract No. CN327, Task Assignment No. 3, Project No. 61394C. The contract is with APTIM Environmental & Infrastructure, LLC, represented by Douglas W. Mann, P.E., D.C.E. The project involves buoy replacements at St. Lucie Inlet State Park. The change order was approved by FDEP representatives including Budget Representative Tamika Bass, Project Manager Jim McGuire, and Contract Manager Ralph Perkins, with consultant signature dated November 9, 2022, and contract authority approval on November 10, 2022.
This change order authorizes a time-only extension with no modification to the fixed fee task amount of $66,854.76. The original task execution date was November 18, 2021, with an original completion date of November 18, 2022. The change order extends the task completion date by 102 days to February 28, 2023 to allow completion of construction administration services. The extension was requested due to permitting delays that extended processing timelines beyond initial expectations. The total task amount remains $66,854.76 with no net increase or decrease in compensation resulting from this change order.
View the file
Other files
Show all 31
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT CHANGE ORDER FORM
(Revised 9-26-2018) Page 1 of 1
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description and Justification of Change:
Change in Task Amount:
Item Reimbursement Fixed Fee Total
Original Task Amount:
Task amount including all previous Change Orders:
Net increase/decrease in task amount for this Change Order:
Total Amounts with all Change Orders:
Change in Task Time:
Original Task Execution Date:
Original Task End Date:
Present Task End Date:
Net Change in Days:
New Task End Date:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 Digit FLAIR Code: Total:
CN327 3 1 61394C
St. Lucie Inlet State Park Buoy Replacements
APTIM Environmental & Infrastructure, LLC
Douglas W. Mann 561-361-3148 douglas.mann@APTIM.com
Ralph Perkins 850-245-2460 Ralph.Perkins@FloridaDEP.gov
Time only extension needed to allow completion of construction administration services. See attached email back up dated 11/03/2022
$ 66,854.76 $ 66,854.76 $ 66,854.76 $ 66,854.76
$ 0.00 $ 0.00 $ 66,854.76 $ 66,854.76
11/18/2021
11/18/2022
11/18/2022
02/28/2023
Tamika Bass Tamika Bass Digitally signed by Tamika Bass Date: 2022.11.07 09:46:35 -05'00'
Jim McGuire Jim McGuire Digitally signed by Jim McGuire Date: 2022.11.07 10:46:14 -05'00'
Ralph Perkins Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2022.11.07 11:00:26 -05'00'
Douglas Mann P.E., D.CE. Douglas W Mann Digitally signed by Douglas W Mann Date: 2022.11.09 09:44:49 -05'00'
Michael W. Foster Jr., P.E. Michael W. Foster Jr., P.E.
Digitally signed by Michael W.
Foster Jr., P.E.
Date: 2022.11.10 09:26:04 -05'00'
$ 0.00
Douglas Mann, P.E., D.CE.
Lead Coastal Engineer Coastal Restoration Team
APTIM
6401 Congress Avenue, Suite 140
Boca Raton FL 33487 Tel: +1 561 361 3148
Fax: +1 561 391 9116 Douglas.Mann@aptim.com
631023500
November 3, 2022
Jim McGuire FDEP Bureau of Design and Construction 13798 SE Federal Highway Hobe Sound, Florida 33455
RE: St. Lucie Inlet Preserve State Park Buoy Engineering Services
Dear Jim:
This letter is to request a time extension for the completion of these services to February 28, 2023. The project is currently in permitting with processing taking longer than expected.
If you have any questions, please call me.
Very truly yours, Douglas W. Mann, P.E., D.CE.
Lead Coastal Engineer APTIM Environmental & Infrastructure, LLC
Matson_D Text Box
CN327 TA3 CO1
File details come from the government source that posted it. Updated .