This is a Task Assignment Notification Form (Task Assignment No. 06) issued by the Florida Department of Environmental Protection (FDEP) to Aptim Environmental & Infrastructure, LLC for the John D. MacArthur Beach State Park Floating Dock Rehabilitation Project. The task assignment operates under the parent Professional Services Agreement DEP CN327 and is governed by the terms and conditions established therein. Key personnel include Douglas W. Mann, P.E., D.CE. (Consultant Representative), Jeffrey Whitfield (FDEP Contract Manager), and Jim McGuire (Project Manager). The document was executed on February 2-3, 2022, and received final contract authority approval on March 8, 2022.
The scope of services encompasses three subtasks: (1) field observation and reporting on the existing floating dock system's condition and response to boat wakes and loads, (2) development of final plans, technical specifications, and an engineering opinion of probable construction cost based on manufacturer consultation, and (3) attendance at one informal meeting with Park and District staff. All services are provided on a fixed-price basis with no reimbursable costs. The total contract amount is $10,866.06, comprised of $4,012.46 for Subtask 1, $5,884.84 for Subtask 2, and $968.76 for Subtask 3. Project timelines extend 45 to 75 calendar days from the Notice to Proceed. Payment is contingent upon FDEP approval of deliverables for each subtask. The project requires owner-provided items, including original dock shop drawings and closure of the marina during field observations to generate and assess boat wake impacts.
View the file
Other files
Show all 31
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT NOTIFICATION FORM
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Owner’s Name: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description of Task:
Project Manager:
Schedule Start Date: Fixed Price Cost:
Completion Date: Cost Reimbursement not to exceed:
Total Task Amount:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 digit FLAIR Code: Total:
CN327 06 FDEP-BDC 61393C
John D. MacArthur Beach State Park Floating Dock Rehabilitation Project
Aptim Environmental & Infrastructure, LLC
Douglas W. Mann, P.E., D.CE. (561)361-3148 Douglas.Mann@aptim.com
Jeffrey Whitfield 850-245-2781 Jeffrey.Whitfield@FloridaDEP.gov
APTIM is submitting this proposal in response to your request for coastal engineering, to design rehabilitations to the existing floating docks along the Intracoastal Waterway at John D. MacArthur Beach State Park. The scope of services at Munyon Island with cost breakdown is included in Appendix A, per attached 1/11/22.
Jim McGuire
Upon execution $ 10,866.06
$ 10,866.06
Greg Turral Gregory Turral Digitally signed by Gregory Turral Date: 2022.02.02 13:29:37 -05'00'
James McGuire James McGuire Digitally signed by James McGuire Date: 2022.02.03 08:38:48 -05'00'
Jeffrey Whitfield Jeffrey Whitfield Digitally signed by Jeffrey Whitfield Date: 2022.02.21 10:53:05 -05'00'
Douglas W. Mann, P.E., D.CE. Douglas W Mann Digitally signed by Douglas W Mann Date: 2022.02.22 10:46:29 -05'00'
Michael W. Foster Jr., P.E. Michael W. Foster Jr., P.E.
Digitally signed by Michael W.
Foster Jr., P.E.
Date: 2022.03.08 08:33:16 -05'00'
61393C 37505000140 080039/22 423001 U3200 131500 QK $ 10,866.06
$ 10,866.06
Douglas Mann, P.E., D.CE.
Lead Coastal Engineer Coastal Restoration Team
APTIM
6401 Congress Avenue, Suite 140
Boca Raton FL 33487 Tel: +1 561 361 3148 Fax: +1 561 391 9116
Douglas.Mann@aptim.com
631024442
January 11, 2022
Jim McGuire Florida Department of Environmental Protection Bureau of Design and Construction 3800 Commonwealth Boulevard Tallahassee, FL 32399
RE: Contract No. CN327 TA06
John D. MacArthur Beach State Park Floating Dock Rehabilitation Project
Dear Mr. McGuire:
Aptim Environmental & Infrastructure, LLC (APTIM) is submitting this proposal in response to your request for coastal engineering, to design rehabilitations to the existing floating docks along the Intracoastal Waterway at John D. MacArthur Beach State Park (Park). A scope of services with cost breakdown is included in Appendix A.
The proposed subtasks identified herein will be performed under and governed by the terms and conditions of the Professional Services Agreement between APTIM and the Florida Department of Environmental Protection (Department), titled DEP CN327 for a lump sum total of $11,063.66. A cost breakdown is included in Appendix A. Please authorize us to begin by executing a Task Assignment to perform the requested services in the name of our licensed contracting entity Aptim Environmental & Infrastructure, LLC.
If you have any questions, please call me.
Very truly yours, Douglas W. Mann, P.E., D.CE.
Lead Coastal Engineer Aptim Environmental & Infrastructure, LLC
Appendix A
Scope of Services and Cost Breakdown John D. MacArthur Beach State Park Floating Dock Rehabilitation Project
Introduction
The Park has a previously established floating dock system along the Intracoastal Waterway side of the Park. The docks are showing indications that they are not fully functioning as intended. The Park has requested that APTIM develop a rehabilitation plan for the floating docks. The docks were originally manufactured by Bellingham Marine, Inc. (Bellingham). A phone conversation with Bellingham occurred to support this proposal. A copy of the shop drawings from Bellingham was requested. The following subtasks are proposed:
Subtask 1:
Description: Subtask 1 Field Observation. A coastal engineer will make a field observation of the floating dock system as it is impacted by boat wakes and live loads. Any other observable defects will also be noted. A report of the observations will be produced. To support the field investigation the dock shop drawings will be reviewed.
Deliverable: The final deliverable will be a report in pdf format.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 1
Firm Name Position Classification Hourly Rate
Hours Total Fixed Price Cost
APTIM Boat Captain $80.00 16 $1,280.00 APTIM Clerical $74.55 2 $149.10 APTIM Sr. Coastal Engineer $161.46 16 $2,583.36
Fixed Price Cost: $4,012.46
Reimbursable Cost: $0.00
Total for Subtask 1: (Fixed Price Cost + Reimbursable) $4,012.46
Subtask 2:
Description: Subtask 2 Final Plans and Specifications. Based on consultation with the manufacturer of the dock system, a rehabilitation plan will be developed. Final plans and technical specifications will be produced. An engineering opinion of probable construction cost will be prepared.
Deliverable: 100% plans and technical specifications will be provided in pdf format. The opinion of probable construction cost will be submitted in pdf format.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 2
Firm Name Position Classification Hourly Rate
Hours Total Fixed Price Cost
APTIM Sr. Coastal Engineer
$161.46 12 $1,937.52
APTIM Coastal Engineer III $130.00 16 $2,080.00 APTIM CAD Operator $98.07 16 $1,569.12 APTIM Clerical $74.55 4 $298.20
Fixed Price Cost: $5,884.84
Reimbursable Cost: $0.00
Total for Subtask 2: (Fixed Price Cost + Reimbursable) $4,916.08
Subtask 3:
Description: Subtask 3. Meeting. APTIM will attend one meeting with Park and District staff to discuss the development of the project. The meeting will be informal and no formal presentation will be made.
The meeting will be at the Park or District office.
Deliverable: Meeting minutes will be provided in pdf format.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 3
Firm Name Position Classification Hourly Rate
Hours Total Fixed Price Cost
APTIM Sr. Coastal Engineer
$161.46 6 $968.76
Fixed Price Cost: $968.76
Reimbursable Cost: $0.00
Total for Subtask 3: (Fixed Price Cost + Reimbursable) $968.76
Williams_BrD Text Box $5,884.84
Project Schedule:
Activity Duration (Calendar Days) Dates Subtask 1: 45 days from Notice to
Proceed To be scheduled
Subtask 2:
75 days from Notice to Proceed
To be scheduled
Subtask 3: 75 days from Notice to Proceed
To be scheduled
Summary of Fees:
Subtask Subtask Fixed Price Cost Subtask Reimbursable Subtask 1: $4,012.46 $ 0.00
Subtask 2: $5,884.84 $ 0.00
Subtask 3: $ 968.76 $ 0.00
Total Fixed Price Cost: $11,063.66 Total Reimbursable Cost: $ 0.00
Overall Total Cost: $11,063.66
Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified. (Please do not alter this language)
Owner Provided Items.
1. It is imperative that the original shop drawings for the floating dock be provided to us from either the Park or the manufacturer to complete this task.
2. On the day of the field observation, it is requested that the Park close the marina to the public while boat wakes are generated outside of the marina and observed within the marina.
Caveat. Engineering opinions of probable construction cost will be prepared based on historical data, and industry input. If more formal cost estimating services is required by FDEP, please advise.
Williams_BrD Text Box $10,866.06
Williams_BrD Text Box $10,866.06
| Task Assignment Form 5.19.2016.pdf |
| MacArthur State Park floating dock 011122 (002).pdf |
File details come from the government source that posted it. Updated .