CDRL A012 Enclosure (1) Nov19.pdf
PDF 48 KB Posted
- Solicitation number
- N00024-20-R-4404
About this file
This document contains details regarding a federal solicitation and key event schedule for ship maintenance and modernization work. The Naval Sea Systems Command is soliciting proposals for execution of the Fiscal Year 2021 USS WASP Docking Selected Restricted Availability, requiring maintenance, modernization, and repair services. Offerors must have substantial facilities including an USS WASP class capable pier, as well as resources to complete, coordinate, and integrate multiple areas of ship work. Proposals are due in August 2020, with work to start in December 2020 and be completed by April 2022. The solicitation will not be set aside for small businesses. Interested parties must register in the System for Award Management and request additional attachments not posted to the solicitation website. A single award is anticipated.
The key event schedule outlines reporting requirements including initial and revised Integrated Production Schedules in Gantt chart and spreadsheet formats, with budgeting and cost data. Weekly updates are required leading up to progress meetings.
View the file
Other files
Show 40 more
Latest 50 of 53 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CDRL A012 (Key Event Schedule) Enclosure (1)
(BLK 9) - DISTRIBUTION STATEMENT D. DISTRIBUTION AUTHORIZED TO THE DEPARTMENT OF DEFENSE
AND U.S. DOD CONTRACTORS ONLY. DUE TO BUSINESS SENSITIVE NATURE OF DATA OTHER REQUESTS
SHALL BE REFERRED TO RMC CODE 300.
(BLKS 4/12/13) THE CONTRACTOR SHALL PROVIDE REQUIRED REPORTS, FILES, AND DATA IAW NSI 009-
60 AS CLARIFIED AND MODIFIED HEREIN. WHERE 009-60 IS INVOKED WITHIN THIS CONTRACT, CDRL
A012 CLARIFICATIONS AND MODIFICATIONS BELOW SHALL APPLY. NSI 009-60 REQUIREMENTS NOT
ADDRESSED OR MODIFIED BELOW REMAIN IN FULL EFFECT.
DEVELOP ONE LEGIBLE COPY IN GANTT CHART FORMAT OF AN INTEGRATED PRODUCTION SCHEDULE
(IPS) THAT REFLECTS THE MANNER IN WHICH THE AVAILABILITY WILL BE ACCOMPLISHED. SUBMIT THE
INITIAL IPS NO LATER THAN 30 DAYS AFTER CONTRACT AWARD. THIS SUBMISSION SHALL SERVE AS THE
PRELIMINARY BASELINE, ALIGNED TO THE BID HOURS OF THE CONTRACT. SUBMIT THE SCHEDULE OF
RECORD (SOR) AT A-0. THE SCHEDULE OF RECORD SHALL REFLECT THE OFFICIAL AVAILABILITY BASELINE
TO WHICH THE AVAILABILITY SCHEDULE (BCWS) AND PERFORMANCE (BCWP) SHALL BE PROGRESSED, AT THE WORK ACTIVITY LEVEL. SUBMIT TO THE SUPERVISOR NO LATER THAN 30 DAYS AFTER
CONTRACT AWARD THE DEVELOPED EXPORT OF THE INITIAL IPS DATA ELEMENTS IN A
SORTABLE/FILTERABLE SPREADSHEET FORMAT COMPATIBLE WITH MICROSOFT EXCEL AND IN THE IPS
NATIVE SOFTWARE FORMAT (E.G. MICROSOFT PROJECT, ORACLE PRIMAVERA, ETC). INITIAL
SUBMISSIONS SHALL SPECIFY THE HOLIDAY CALENDAR UTILIZED. SUBMIT TO THE SUPERVISOR AT A-0
THE DEVELOPED EXPORT OF THE SCHEDULE OF RECORD (REVISED IPS) DATA ELEMENTS IN A
SORTABLE/FILTERABLE SPREADSHEET FORMAT COMPATIBLE WITH MICROSOFT EXCEL AND IN THE IPS
NATIVE SOFTWARE FORMAT. SUBMIT TO THE SUPERVISOR WEEKLY AFTER A-0 AND ONE DAY PRIOR TO
EACH WEEKLY PROGRESS MEETING EACH REVISED IPS AND DEVELOPED EXPORT AT THE WORK ACTIVITY
LEVEL TO INCLUDE ADDITIONS, DELETIONS, MODIFICATIONS, ACTUAL START AND FINISH DATES, PROGRESS, AND COMPLETIONS. IN ADDITION TO THE EXCEL EXPORT, PROVIDE THE IPS NATIVE
SOFTWARE FORMAT.
MODIFICATIONS TO TABLE 1 OF NSI 009-60 ARE AS FOLLOWS:
ADD:
• BUDGETED COST OF WORK SCHEDULED (BCWS):
• BUDGETED COST OF WORK PERFORMED (BCWP):
• ACTUAL COST OF WORK PERFORMED (ACWP):
• BUDGET AT COMPLETION (BAC):
• ESTIMATE AT COMPLETION (EAC):
• PRODUCTION TRADE:
• SUBCONTRACT COMPANY (IF COMPLEX OR NON-COMPLEX MAC-HOLDER):