(USS WASP) Attachment J-7 Schedule Model Review.docx

DOCX document 16 KB Posted

Attached to
USS WASP (LHD 1) FY21 Dry-Docking Selected Restricted Availability (DSRA)
Solicitation number
N00024-20-R-4404
Issued by

About this file

This document contains details regarding a solicitation for the USS WASP (LHD 1) FY21 Dry-Docking Selected Restricted Availability. The Naval Sea Systems Command is soliciting proposals for the execution of maintenance, modernization, and repair of the USS WASP, requiring facilities including a pier capable of accommodating the USS WASP class. Interested parties must register in the System for Award Management and monitor beta.SAM.gov for release of the solicitation and amendments. A site visit is scheduled for April 2020 and proposals are due in June 2020, with award anticipated in August 2020 and availability start in December 2020. The delivery date for the USS WASP is April 2022. The solicitation includes specifications, work item plans and references, milestones, and a pricing workbook.

View the file

Other files

File Type Posted
(USS WASP) Attachment S-7 Proposal Assessment 27Apr20.xlsx XLSX spreadsheet
N00024-20-R-4404_A0005 USS WASP (LHD 1) DSRA.pdf PDF
N00024-20-R-4404_A0004 USS WASP (LHD 1) DSRA.pdf PDF
USS WASP PPI 35-55_2020-04-14.xlsx XLSX spreadsheet
USS WASP PPI 34_2020-03-31.xlsx XLSX spreadsheet
USS WASP PPI 14-33_2020-03-26.xlsx XLSX spreadsheet
N00024-20-R-4404_A0003 USS WASP (LHD 1) DSRA.pdf PDF
USS WASP PPI 10-13_2020-03-20.xlsx XLSX spreadsheet
(USS WASP) Attachment S-6 (A0001) VATEP.xlsx XLSX spreadsheet
N00024-20-R-4404_A0002 USS WASP (LHD 1) DSRA.pdf PDF
USS WASP PPI 1-9_2020-03-16.xlsx XLSX spreadsheet
N00024-20-R-4404_A0001 USS WASP (LHD 1) DSRA.pdf PDF
USS WASP BQs 1-3_2020-03-09.xlsx XLSX spreadsheet
CDRL A011 Status of GFE Rev1.pdf PDF
(USS WASP) Attachment S-8 Pier and Drydock Graphical Representation Template.xlsx XLSX spreadsheet
CDRL B005 LMI Interim Support Data Rev1.pdf PDF
CDRL B008 Logistics Product Data Rev1.pdf PDF
CDRL B004 LMI ISIL Rev1.pdf PDF
CDRL A014 Weight and Stability Report Rev1.pdf PDF
(USS WASP) Attachment S-5 Enclosure (1).PDF PDF
CDRL A003 RCC Report Rev1.pdf PDF
CDRL B002 LMI Data Provisioning Rev1.pdf PDF
CDRL A015 Performance Report Rev3.pdf PDF
CDRL A016 Enc (1) Final Labor-Duration-Material Data.xlsx XLSX spreadsheet
CDRL B009 LMI Demand Only Trans Rpt Rev1.pdf PDF
CDRL A007 QA Program Plan Fire Prevention-Housekeeping Rev1.pdf PDF
CDRL A008 QA Program Plan PCP Rev1.pdf PDF
CDRL A015 Enclosure 2 (Template) FEB19.xlsx XLSX spreadsheet
CDRL B006 LMI Component Ident Data Rev1.pdf PDF
(USS WASP) Attachment J-5 QASP WASP FY21 DSRA.docx DOCX document
CDRL A012 Key Event Schedule Rev 2.pdf PDF
CDRL C001 COTS Equipment Manual Suprt Rev1.pdf PDF
N00024-20-R-4404 USS WASP (LHD 1) FY21 DSRA Solicitation.pdf PDF
CDRL A009 Technical Report - Welding, Fab, Insp Rev1.pdf PDF
(USS WASP) Attachment S-2 Past Performance Questionnaire.docx DOCX document
CDRL A001 Small Business Subcontract Rpt Rev1.pdf PDF
CDRL B001 LMI PPL Rev1.pdf PDF
(USS WASP) Attachment S-1 Manpower Utilization Data Sheet.xlsx XLSX spreadsheet
CDRL B007 Provisioning Tech Docs Rev1.pdf PDF
CDRL A005 Purchase Order Rev1.pdf PDF
CDRL A006 QA Program Plan QMS Rev1.pdf PDF
CDRL A015 Enclosure 1 (BLK 16) FEB19.pdf PDF
(USS WASP) Attachment S-9 PP CPARS Reference List.docx DOCX document
CDRL C002 Tech Manual Rqmts Rev1.pdf PDF
(USS WASP) Attachment S-4 Manpower Performance 15Jan20.xlsx XLSX spreadsheet
(USS WASP) Attachment S-7 Proposal Assessment 15Jan20.xlsx XLSX spreadsheet
CDRL B003 LMI Design Change Notice Rev1.pdf PDF
(USS WASP) Attachment J-10 Compartment Closeout List.xlsx XLSX spreadsheet
(USS WASP) Attachment S-6 Value Adjusted Total Evaluated Price.xlsx XLSX spreadsheet
CDRL A016 Final Labor-Duration-Material Data Rev2.pdf PDF
Show 40 more

Latest 50 of 53 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

J-7 Schedule Model Review USS WASP Purpose: At A-30 the LMA shall lead a Schedule Model Review of the Integrated Production Schedule (IPS) with all parties to validate integration requirements. The Schedule Model Review is intended to be a detailed review of all work items to ensure adequate integration into the master schedule and to de-conflict any overlapping activities. The anticipated duration of this meeting is 5-7 days. Hours for Day 1 is 0800-1600 and for Day2 and following is 0800-1130.

1. Required Attendees:

a. LMA management team

b. Government Project Management Team (NSA)

c. Turnkey Subcontractors

d. AIT On Site Installation Coordinators (OSIC)

e. Intermediate Maintenance Facility (IMF) Ship’s Superintendent, if applicable

f. Ship’s Force (one representative from each department, Ship’s Maintenance Officer)

2. Agenda:

Day 1 WPER (Government Facilitated)

a. Early Start Candidates (LMA)

b. WAF/Tag Out coordination (LMA)

c. Pier Laydown Plan (LMA)

d. First 100 Hour Plan (NSA)

e. Communications Plan (NSA)

f. Process Control Procedures (PCP) (LMA)

g. Access Cuts (LMA)

h. Fire Prevention and Fire Drill (8010) requirements (NSA)

i. Memorandum of Agreement (MOA) – AIT’s only (NSA)

Day 2 - 7

j. LMA to Present the IPS for review. The IPS shall include (but not limited to) all work associated with the Lead Maintenance Activity (LMA), subcontractors, Alteration Installation Teams (AIT), Ship’s Force, and Intermediate Maintenance Activity (IMA).

3. Deliverables:

a. Updated IPS with all maintenance activities fully integrated. (LMA)

b. Early start candidates submitted and approved by the NSA. (LMA)

c. WAF/Tag Out coordination plan established. (LMA)

d. First 100 Hour Plan established. (NSA)

e. Set schedule for all required meetings. (NSA)

f. Pier Laydown Plan submitted for approval by NSA. (LMA)

g. List of Process Control Procedures with projected due dates. (LMA)

h. List of access cuts (if required). (LMA)

i. Fire drill execution date set. (NSA)

j. Detailed review of critical path and top three controlling path items. (LMA)