(USS WASP) Attachment J-7 Schedule Model Review.docx
DOCX document 16 KB Posted
- Solicitation number
- N00024-20-R-4404
About this file
This document contains details regarding a solicitation for the USS WASP (LHD 1) FY21 Dry-Docking Selected Restricted Availability. The Naval Sea Systems Command is soliciting proposals for the execution of maintenance, modernization, and repair of the USS WASP, requiring facilities including a pier capable of accommodating the USS WASP class. Interested parties must register in the System for Award Management and monitor beta.SAM.gov for release of the solicitation and amendments. A site visit is scheduled for April 2020 and proposals are due in June 2020, with award anticipated in August 2020 and availability start in December 2020. The delivery date for the USS WASP is April 2022. The solicitation includes specifications, work item plans and references, milestones, and a pricing workbook.
View the file
Other files
Show 40 more
Latest 50 of 53 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
J-7 Schedule Model Review USS WASP Purpose: At A-30 the LMA shall lead a Schedule Model Review of the Integrated Production Schedule (IPS) with all parties to validate integration requirements. The Schedule Model Review is intended to be a detailed review of all work items to ensure adequate integration into the master schedule and to de-conflict any overlapping activities. The anticipated duration of this meeting is 5-7 days. Hours for Day 1 is 0800-1600 and for Day2 and following is 0800-1130.
1. Required Attendees:
a. LMA management team
b. Government Project Management Team (NSA)
c. Turnkey Subcontractors
d. AIT On Site Installation Coordinators (OSIC)
e. Intermediate Maintenance Facility (IMF) Ship’s Superintendent, if applicable
f. Ship’s Force (one representative from each department, Ship’s Maintenance Officer)
2. Agenda:
Day 1 WPER (Government Facilitated)
a. Early Start Candidates (LMA)
b. WAF/Tag Out coordination (LMA)
c. Pier Laydown Plan (LMA)
d. First 100 Hour Plan (NSA)
e. Communications Plan (NSA)
f. Process Control Procedures (PCP) (LMA)
g. Access Cuts (LMA)
h. Fire Prevention and Fire Drill (8010) requirements (NSA)
i. Memorandum of Agreement (MOA) – AIT’s only (NSA)
Day 2 - 7
j. LMA to Present the IPS for review. The IPS shall include (but not limited to) all work associated with the Lead Maintenance Activity (LMA), subcontractors, Alteration Installation Teams (AIT), Ship’s Force, and Intermediate Maintenance Activity (IMA).
3. Deliverables:
a. Updated IPS with all maintenance activities fully integrated. (LMA)
b. Early start candidates submitted and approved by the NSA. (LMA)
c. WAF/Tag Out coordination plan established. (LMA)
d. First 100 Hour Plan established. (NSA)
e. Set schedule for all required meetings. (NSA)
f. Pier Laydown Plan submitted for approval by NSA. (LMA)
g. List of Process Control Procedures with projected due dates. (LMA)
h. List of access cuts (if required). (LMA)
i. Fire drill execution date set. (NSA)
j. Detailed review of critical path and top three controlling path items. (LMA)