CDRL A015 Enclosure 1 (BLK 16) FEB19.pdf

PDF 282 KB Posted

Attached to
USS WASP (LHD 1) FY21 Dry-Docking Selected Restricted Availability (DSRA)
Solicitation number
N00024-20-R-4404
Issued by

About this file

This document contains a solicitation for the USS WASP (LHD 1) FY21 Dry-Docking Selected Restricted Availability. The Naval Sea Systems Command seeks to execute maintenance, modernization, and repair of the USS WASP through a single-award contract with a capable contractor. Interested offerors must register in the System for Award Management and monitor the beta.SAM.gov site for solicitation release and amendments. While certain work packages and attachments will not be posted to beta.SAM.gov, interested parties may request them from specified Navy contacts. The availability start date is anticipated to be December 2020, with delivery of the USS WASP required by April 2022. Proposals are due in August 2020 and award will be made on or around that same date. The work will be performed at the contractor's East or Gulf Coast facility and includes a combination of maintenance, modernization, and repair for the USS WASP class.

View the file

Other files

File Type Posted
(USS WASP) Attachment S-7 Proposal Assessment 27Apr20.xlsx XLSX spreadsheet
N00024-20-R-4404_A0005 USS WASP (LHD 1) DSRA.pdf PDF
N00024-20-R-4404_A0004 USS WASP (LHD 1) DSRA.pdf PDF
USS WASP PPI 35-55_2020-04-14.xlsx XLSX spreadsheet
USS WASP PPI 34_2020-03-31.xlsx XLSX spreadsheet
USS WASP PPI 14-33_2020-03-26.xlsx XLSX spreadsheet
N00024-20-R-4404_A0003 USS WASP (LHD 1) DSRA.pdf PDF
USS WASP PPI 10-13_2020-03-20.xlsx XLSX spreadsheet
(USS WASP) Attachment S-6 (A0001) VATEP.xlsx XLSX spreadsheet
N00024-20-R-4404_A0002 USS WASP (LHD 1) DSRA.pdf PDF
USS WASP PPI 1-9_2020-03-16.xlsx XLSX spreadsheet
N00024-20-R-4404_A0001 USS WASP (LHD 1) DSRA.pdf PDF
USS WASP BQs 1-3_2020-03-09.xlsx XLSX spreadsheet
CDRL A011 Status of GFE Rev1.pdf PDF
(USS WASP) Attachment S-8 Pier and Drydock Graphical Representation Template.xlsx XLSX spreadsheet
CDRL B005 LMI Interim Support Data Rev1.pdf PDF
CDRL B008 Logistics Product Data Rev1.pdf PDF
CDRL B004 LMI ISIL Rev1.pdf PDF
CDRL A014 Weight and Stability Report Rev1.pdf PDF
(USS WASP) Attachment S-5 Enclosure (1).PDF PDF
CDRL A003 RCC Report Rev1.pdf PDF
CDRL B002 LMI Data Provisioning Rev1.pdf PDF
(USS WASP) Attachment J-7 Schedule Model Review.docx DOCX document
CDRL A015 Performance Report Rev3.pdf PDF
CDRL A016 Enc (1) Final Labor-Duration-Material Data.xlsx XLSX spreadsheet
CDRL B009 LMI Demand Only Trans Rpt Rev1.pdf PDF
CDRL A007 QA Program Plan Fire Prevention-Housekeeping Rev1.pdf PDF
CDRL A008 QA Program Plan PCP Rev1.pdf PDF
CDRL A015 Enclosure 2 (Template) FEB19.xlsx XLSX spreadsheet
CDRL B006 LMI Component Ident Data Rev1.pdf PDF
(USS WASP) Attachment J-5 QASP WASP FY21 DSRA.docx DOCX document
CDRL A012 Key Event Schedule Rev 2.pdf PDF
CDRL C001 COTS Equipment Manual Suprt Rev1.pdf PDF
N00024-20-R-4404 USS WASP (LHD 1) FY21 DSRA Solicitation.pdf PDF
CDRL A009 Technical Report - Welding, Fab, Insp Rev1.pdf PDF
(USS WASP) Attachment S-2 Past Performance Questionnaire.docx DOCX document
CDRL A001 Small Business Subcontract Rpt Rev1.pdf PDF
CDRL B001 LMI PPL Rev1.pdf PDF
(USS WASP) Attachment S-1 Manpower Utilization Data Sheet.xlsx XLSX spreadsheet
CDRL B007 Provisioning Tech Docs Rev1.pdf PDF
CDRL A005 Purchase Order Rev1.pdf PDF
CDRL A006 QA Program Plan QMS Rev1.pdf PDF
(USS WASP) Attachment S-9 PP CPARS Reference List.docx DOCX document
CDRL C002 Tech Manual Rqmts Rev1.pdf PDF
(USS WASP) Attachment S-4 Manpower Performance 15Jan20.xlsx XLSX spreadsheet
(USS WASP) Attachment S-7 Proposal Assessment 15Jan20.xlsx XLSX spreadsheet
CDRL B003 LMI Design Change Notice Rev1.pdf PDF
(USS WASP) Attachment J-10 Compartment Closeout List.xlsx XLSX spreadsheet
(USS WASP) Attachment S-6 Value Adjusted Total Evaluated Price.xlsx XLSX spreadsheet
CDRL A016 Final Labor-Duration-Material Data Rev2.pdf PDF
Show 40 more

Latest 50 of 53 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(BLK 4) SUBMISSIONS: PROVIDED THE FOLLOWING REPORTS WITHIN 5 DAYS

WORKING DAYS AFTER THE CLOSE OF THE REPORTED WEEK.

DEFINTIONS

BUDGETED COST OF WORK SCHEDULED (BCWS) IS THE SUM OF THE BUDGETS FOR

ALL WORK SCHEDULED TO BE ACCOMPLISHED WITH A GIVEN TIME PERIOD.

BUDGETED COST OF WORK PERFORMED (BCWP) IS THE BUDGETED COST OF THE

VALUE OF WORK THAT HAS ACTUALLY BEEN ACCOMPLISHED OR COMPLETED TO

DATE.

ACTUAL COST OF WORK PERFORMED (ACWP) IS THE COST INCURRED AND RECORDED

FOR WORK COMPLETED WITHIN A GIVEN TIME PERIOD. THE ACWP IS REPORTED BY

THE CONTRACTOR’S ACCOUNTING SYSTEM IN ACCORDANCE WITH GENERALLY

ACCEPTED ACCOUNTING PROCEDURES AND IS SIMPLY STATED ACTUALS ARE

ACTUALS.

BUDGET AT COMPLETION (BAC) REPRESENT THE TOTAL BUDGET FROM WHICH

INDIVIDUAL PERIOD BUDGETED COST OF WORK SCHEDULED (BCWS) VALUES ARE

DERIVED AND THEY ARE THE BENCHMARKS FOR COMPUTING OVERRUNS AND UNDER

RUNS AT THE END OF THE CONTRACT. THE BUDGETS FOR ALL AUTHORIZED WORK

MUST BE CAPTURED WITHIN THE BAC.

ESTIMATE AT COMPLETE (EAC) IS THE SUM OF THE CONTRACT'S CUMULATIVE TO-

DATE ACTUAL COST OF WORK PERFORMED (ACWP) PLUS THE ESTIMATE OF THE

TIME-PHASED RESOURCES REQUIRED TO COMPLETE THE REMAINING AUTHORIZED

WORK.

THE CONTRACTOR SHALL PROVIDE THE FOLLOWING DELIVERABLES, IN ACCORDANCE

WITH ENCLOSURE (2) AND THE INSTRUCTIONS BELOW:

COMMON HEADING INFORMATION (APPLICABLE TO ALL REPORTS)

CONTRACTOR ENTER IN BLOCK 1.A THE CONTRACTOR'S NAME AND DIVISION (IF

APPLICABLE). ENTER IN BLOCK 1.B THE FACILITY LOCATION AND MAILING

ADDRESS OF THE REPORTING CONTRACTOR.

CONTRACT. ENTER THE CONTRACT INFORMATION IN BLOCK 2.

• ENTER THE CONTRACT NAME IN BLOCK 2.A;

• ENTER THE CONTRACT NUMBER AND THE APPLICABLE CONTRACT LINE ITEM

NUMBER(S) (CLIN(S) IN BLOCK 2.B;

• ENTER “FFP” IN BLOCK 2.C;

• ENTER “NOT APPLICABLE” IN BLOCK 2.D;

PROGRAM. ENTER IN THE PROGRAM INFORMATION IN BLOCK 3.

• ENTER THE VESSEL’S NAME AND HULL NUMBER UNDERGOING REPAIRS IN

BLOCK 3.A;

• ENTER THE AVAILABILITY TYPE (E.G. SRA, DPMA, ETC) IN BLOCK 3.B.;

• LEAVE BLANK BLOCK 3.C.

REPORT PERIOD. ENTER THE BEGINNING DATE IN BLOCK 4.A AND THE ENDING

DATE IN BLOCK 4.B OF THE TIME PERIOD COVERED BY THE REPORT.

SECURITY. ALL ELECTRONIC FILE DELIVERABLES SHALL INCLUDE THE

APPROPRIATE SECURITY DESIGNATIONS.

DOLLARS IN. IF REPORTED DOLLAR AMOUNTS ARE NOT IN WHOLE DOLLARS, ENTER

THE UNITS USED (E.G. $K, $M, $B) AT THE TOP OF EACH PAGE.

WORK ITEM PERFORMANCE REPORT INSTRUCTIONS:

REPORTING SHALL BE PROVIDED ON A WEEKLY BASIS. REPORTING SHALL PROVIDE

TOTAL PRIME AND SUBCONTRACTOR PRODUCTION HOURS AT THE WORK ITEM LEVEL.

SUBCONTRACTOR LABOR SHALL BE REPORTED AS LABOR HOURS, NOT AS MATERIAL

DOLLARS. ACTUAL SUBCONTRACTOR HOURS MAY BE ESTIMATED BASED ON PRIME

CONTRACTOR OUTLAYS.

• BLOCK 5.A – NOT APPLICABLE

• NEGOTIATED PRODUCTION HOURS. ENTER IN BLOCK 5.B THE NUMBER OF

PRODUCTION HOURS (BOTH PRIME AND SUBCONTRACTOR) ON WHICH

CONTRACTUAL AGREEMENT WAS REACHED AS OF THE REFLECTED REPORTING

PERIOD. AMOUNTS FOR CHANGES SHALL NOT BE INCLUDED UNTIL THEY HAVE

BEEN DEFINITIZED IN THE CONTRACT.

• ESTIMATED PRODUCTION HOURS FOR AUTHORIZED, UNPRICED WORK (AUW).

AUTHORIZED, UNPRICED WORK IS APPROVED WORK SCOPE THAT HAS NOT

BEEN DEFINITIZED. THE ESTIMATED NUMBER OF PRODUCTION HOURS (BOTH

PRIME AND SUBCONTRACTOR) OF AUW SHALL BE ENTERED IN BLOCK 5.C.

THE VALUE OF AUW IS THE VALUE OF THE SCOPE THAT WAS COORDINATED

BETWEEN THE CONTRACTOR AND THE PROGRAM OFFICE, AND AUTHORIZED BY

THE CONTRACTING OFFICER. AUW CAN NEVER BE A NEGATIVE VALUE. FOR

EFFORT DE-SCOPED AND NOT YET REFLECTED IN THE CONTRACT BUDGET

BASE (CBB), REPORT THE ESTIMATED VALUE IN THE PERFORMANCE

ANALYSIS.

• BLOCK 5.D – NOT APPLICABLE

• BLOCK 5.E – NOT APPLICABLE

• ESTIMATED PRODUCTION HOURS. BASED ON THE CONTRACTOR’S MOST LIKELY

ESTIMATE OF THE NUMBER OF PRODUCTION HOURS (BOTH PRIME AND

SUBCONTRACTOR) EXPENDED AT COMPLETION FOR ALL AUTHORIZED WORK,

ENTER IN BLOCK 5.F THE ESTIMATED FINAL PRODUCTION HOURS. THIS

NUMBER SHALL BE BASED ON THE CONTRACTOR’S MOST LIKELY MANAGEMENT

EAC IN BLOCK 6.C.1 AND NORMALLY WILL CHANGE WHEN THE EAC IS

UPDATED AND/OR WHEN THE CONTRACT IS REVISED.

• BLOCK 5.G – NOT APPLICABLE

• BLOCK 5.H – NOT APPLICABLE

• OVER TARGET BASELINE (OTB)/OVER TARGET SCHEDULE (OTS). ENTER IN

BLOCK 5.I THE DATE THE LAST OTB OR OTS WAS IMPLEMENTED, IF

APPLICABLE.

• MANAGEMENT ESTIMATE AT COMPLETION - MOST LIKELY. ENTER IN BLOCK

6.C.1 THE CONTRACTOR'S MOST LIKELY EAC. THIS EAC IS THE

CONTRACTOR'S OFFICIAL CONTRACT EAC. THE MOST LIKELY EAC IS THE

VALUE THAT THE CONTRACTOR'S MANAGEMENT BELIEVES IS THE MOST

POSSIBLE OUTCOME BASED ON A KNOWLEDGEABLE ESTIMATION OF ALL

AUTHORIZED WORK, KNOWN FACTORED RISKS, AND PROBABLE FUTURE

CONDITIONS. THIS VALUE SHALL AGREE WITH THE TOTAL OF COLUMN (15)

(BLOCK 8.E).

• CONTRACT BUDGET BASE (CBB). ENTER IN BLOCK 6.C.2 THE TOTAL NUMBER

OF NEGOTIATED PRODUCTION HOURS (BLOCK 5.B) AND ESTIMATED NUMBER

OF PRODUCTION HOURS OF AUTHORIZED, UNPRICED WORK (BLOCK 5.C).

PERFORMANCE DATA.

• COLUMN (1A) - WORK ITEM NUMBER. ENTER IN COLUMN (1A) OF BLOCK 8.A

THE WORK ITEM NUMBER AGAINST WHICH COST INFORMATION IS BEING

REPORTED.

• COLUMN (1B) - DESCRIPTION. ENTER IN COLUMN (1B) OF BLOCK 8.A THE

ITEM DESCRIPTION AGAINST WHICH COST INFORMATION IS BEING

REPORTED.

• TOTAL. IN COLUMNS (2) THROUGH (16) OF BLOCKS 8.A, ENTER THE SUM

OF THE PRODUCTION HOURS FOR THE REPORTED WORK ITEMS.

PERFORMANCE DATA COLUMNS (2) THROUGH (16).

• COLUMN (2) AND COLUMN (7) - BUDGETED COST - WORK SCHEDULED. FOR

THE REPORT PERIOD NOTED, ENTER THE BCWS IN THESE COLUMNS.

• COLUMN (3) AND COLUMN (8) - BUDGETED COST - WORK PERFORMED. FOR

THE REPORT PERIOD NOTED, ENTER THE BCWP IN THESE COLUMNS.

• COLUMN (4) AND COLUMN (9) - ACTUAL COST - WORK PERFORMED. FOR THE

REPORT PERIOD NOTED, ENTER THE ACWP IN THESE COLUMNS WITHOUT

REGARD TO CEILING. IN ALL CASES, COSTS AND BUDGETS SHALL BE

REPORTED ON A COMPARABLE BASIS.

• COLUMN (5) AND COLUMN (10) - VARIANCE – SCHEDULE. FOR THE REPORT

PERIOD, THESE COLUMNS SHALL REFLECT THE DIFFERENCES BETWEEN BCWS

AND BCWP.

o FOR THE CURRENT PERIOD COLUMN, COLUMN (5) (SCHEDULE

VARIANCE) IS DERIVED BY SUBTRACTING COLUMN (2) (BCWS) FROM

COLUMN (3) (BCWP).

o FOR THE CUMULATIVE TO DATE COLUMN, COLUMN (10) (SCHEDULE

VARIANCE) IS DERIVED BY SUBTRACTING COLUMN (7) (BCWS) FROM

COLUMN (8) (BCWP).

o A POSITIVE NUMBER IN COLUMN (5) AND COLUMN (10) INDICATES A

FAVORABLE VARIANCE. A NEGATIVE NUMBER INDICATES AN

UNFAVORABLE VARIANCE.

• COLUMN (6) AND COLUMN (11) - VARIANCE - COST. FOR THE REPORT

PERIOD, THESE COLUMNS SHALL REFLECT THE DIFFERENCE BETWEEN BCWP

AND ACWP.

o FOR THE CURRENT PERIOD COLUMN, COLUMN (6) (COST VARIANCE)

IS DERIVED BY SUBTRACTING COLUMN (4) (ACWP) FROM COLUMN (3)

(BCWP).

o FOR THE CUMULATIVE TO DATE COLUMN, COLUMN (11) (COST

VARIANCE) IS DERIVED BY SUBTRACTING COLUMN (9) (ACWP) FROM

COLUMN (8) (BCWP).

o A POSITIVE VALUE INDICATES A FAVORABLE VARIANCE. A NEGATIVE

VALUE INDICATES AN UNFAVORABLE VARIANCE.

• COLUMN (12) – NOT APPLICABLE

• COLUMN (13) – NOT APPLICABLE

• COLUMN (14) – NOT APPLICABLE

• COLUMN (15) - AT COMPLETION - ESTIMATED. ENTER THE LATEST REVISED

ESTIMATE OF COST AT COMPLETION INCLUDING ANY ESTIMATED

OVERRUN/UNDERRUN FOR ALL AUTHORIZED WORK.

• COLUMN (16) - AT COMPLETION - VARIANCE. ENTER THE DIFFERENCE

BETWEEN THE EAC COLUMN (15) AND THE BAC COLUMN (14) BY

SUBTRACTING THE EAC COLUMN FROM THE BAC COLUMN. THIS VARIANCE AT

COMPLETION (VAC), WHEN NEGATIVE, REFLECTS AN UNFAVORABLE

POSITION.

SCHEDULE OF RECORD (SOR) REPORT INSTRUCTIONS:

THIS DELIVERABLE DEFINES CHANGES TO THE SCHEDULE OF RECORD (SOR), AS

DEFINED IN NSI 009-60 PARAGRAPH 3.1.4, AND IS TO BE PROVIDED ON A

WEEKLY BASIS. THE BASELINE CHANGE BREAKOUT SHOULD BE BY WEEK FOR THE

NEXT FIVE WEEKS, A REMAINDER PERIOD BETWEEN FIVE WEEKS AND THE START

OF SECOND TO NEXT MONTH, AND THEN MONTHLY THEREAFTER.

• ORIGINAL NEGOTIATED PRODUCTION HOURS. ENTER IN BLOCK 5.A THE

NUMBER OF HOURS NEGOTIATED IN THE ORIGINAL CONTRACT. The production hours included in the contractor’s Schedule of Record shall equal:

o The production hours for each work item included in the solicitation as both Base and Option items (as proposed in the offeror’s J-4 and J-14), o Production Hours shall align to the definition of production hours provided in Section B, Note B entitled

“FIXED SHIP REPAIR LABOR AND MATERIAL BURDEN RATES FOR

BASE, GROWTH AND NEW WORK”.

o Any contractual changes to work items included in the solicitation as both Base and Option items made after award but prior to Availability execution (as applicable), and o Work item scope negotiated into the contract over and above the requirements of the solicited work package utilizing the Base work LOE to completion CLINs (as applicable).

• NEGOTIATED CONTRACT CHANGES. ENTER IN BLOCK 5.B THE TOTAL NUMBER

OF PRODUCTION HOURS OF ALL DEFINITIZED CONTRACT CHANGES THAT HAVE

OCCURRED SINCE DEFINITIZATION OF THE ORIGINAL CONTRACT.

• CURRENT NEGOTIATED PRODUCTION HOURS. ENTER IN BLOCK 5.C THE SUM

OF BLOCKS 5.A AND 5.B. THE AMOUNT SHOWN SHALL EQUAL THE AMOUNT IN

NEGOTIATED COST (BLOCK 5.B) IN THE WORK ITEM PERFORMANCE REPORT.

• ESTIMATED PRODUCTION HOURS FOR AUTHORIZED, UNPRICED WORK (AUW).

ENTER IN BLOCK 5.D THE AUW AMOUNT CONSISTENT WITH WORK ITEM

PERFORMANCE REPORT BLOCK 5.C.

• CONTRACT BUDGET BASE (CBB). ENTER IN BLOCK 5.E THE SUM OF BLOCKS

5.C AND 5.D.

• TOTAL ALLOCATED BUDGET (TAB). ENTER IN BLOCK 5.F THE SUM OF ALL

PRODUCTION HOUR BUDGETS ALLOCATED TO THE PERFORMANCE OF THE

CONTRACTUAL EFFORT.

THIS AMOUNT SHALL BE THE SAME AS THAT SHOWN ON THE TOTAL LINE IN

COLUMN (14) IN THE WORK ITEM PERFORMANCE REPORT (BLOCK 8.B).

DIFFERENCE. ENTER IN BLOCK 5.G THE DIFFERENCE BETWEEN BLOCKS 5.E AND

5.F.

CONTRACT START DATE. ENTER IN BLOCK 5.H THE DATE THE CONTRACTOR WAS

AUTHORIZED TO START WORK ON THE CONTRACT, REGARDLESS OF THE DATE OF

CONTRACT DEFINITIZATION.

CONTRACT DEFINITIZATION DATE. ENTER IN BLOCK 5.I THE DATE THE CONTRACT

WAS ORIGINALLY AWARDED.

PLANNED COMPLETION DATE. ENTER IN BLOCK 5.J THE COMPLETION DATE FOR

WHICH THE BUDGETS ALLOCATED IN THE SOR HAVE BEEN PLANNED. THIS DATE

REPRESENTS THE PLANNED COMPLETION OF ALL EFFORTS ON THE CONTRACT.

THE NUMBER OF PRODUCTION HOURS ASSOCIATED WITH THIS DATE’S SCHEDULED

EFFORTS IS THE TAB (BLOCK 5.F OF THE SCHEDULE OF RECORD (SOR) REPORT).

THE CONTRACTOR MAY RE-PHASE THE SOR SCHEDULE TO NEW DATES THAT EXCEED

THE CONTRACTUAL MILESTONES, A CONDITION KNOWN AS AN OTS, WITH

GOVERNMENT APPROVAL. THESE NEW SCHEDULE DATES ARE FOR PERFORMANCE

MEASUREMENT PURPOSES ONLY AND DO NOT REPRESENT AN AGREEMENT TO MODIFY

THE CONTRACT TERMS AND CONDITIONS.

THE GOVERNMENT AND THE CONTRACTOR SHALL AGREE ON THE NEW SOR SCHEDULE

PRIOR TO REPORTING IT. THE CONTRACTOR SHALL PROVIDE PERTINENT

INFORMATION IN THE PERFORMANCE ANALYSIS ON ANY SCHEDULE MILESTONES

THAT ARE INCONSISTENT WITH CONTRACTUAL MILESTONES, BEGINNING THE MONTH

THE OTS IS IMPLEMENTED AND EACH MONTH THEREAFTER.

CONTRACT COMPLETION DATE. ENTER IN BLOCK 5.K THE CONTRACT SCHEDULED

COMPLETION DATE IN ACCORDANCE WITH THE LATEST CONTRACT MODIFICATION.

THE COST ASSOCIATED WITH THE SCHEDULE FROM WHICH THIS DATE IS TAKEN IS

THE CBB (BLOCK 5.E OF THE SCHEDULE OF RECORD (SOR) REPORT).

ESTIMATED COMPLETION DATE. ENTER IN BLOCK 5.L THE CONTRACTOR'S LATEST

ESTIMATED COMPLETION DATE. THIS DATE SHALL BE CONSISTENT WITH THE

UNDERLYING ASSUMPTIONS BEHIND BLOCK 6.C.1 OF THE WORK ITEM PERFORMANCE

REPORT.

PERFORMANCE DATA (BLOCK 6).

BLOCK 6.A – SCHEDULE OF RECORD (BEGINNING OF PERIOD). ENTER IN BLOCK

6.A THE TIME-PHASED SOR VALUE AS IT EXISTED AT THE BEGINNING OF THE

CURRENT REPORTING PERIOD. NORMALLY THE ENTRIES ON THIS LINE (E.G., FOR

COLUMNS (4) THROUGH (9)) ARE TAKEN DIRECTLY FROM THE SOR (END OF

PERIOD) LINE ON THE PREVIOUS REPORT.

BASELINE CHANGES AUTHORIZED DURING REPORT PERIOD.

IN BLOCK 6.B, LIST ALL SIGNIFICANT BASELINE CHANGES THAT HAVE OCCURRED

DURING THE REPORTING PERIOD IN THEIR RESPECTIVE TIMEFRAMES IN COLUMNS

(2)-(15).

• THIS LIST SHALL INCLUDE THE CONTRACT CHANGES AND AUW AUTHORIZED

DURING THE REPORTING PERIOD, AND ANY SIGNIFICANT RE-PHASING OF

BUDGETS.

• ALL SIGNIFICANT AUTHORIZED BASELINE CHANGES SHALL BE LISTED

INDIVIDUALLY, WHETHER PRICED OR UNPRICED; ALL OTHER CHANGES SHALL

BE SUMMARIZED AND TITLED “OTHER.”

• BLOCK 6.B, WHEN ADDED TO BLOCK 6.A, EQUALS BLOCK 6.C.

• SIGNIFICANT DIFFERENCES, THOSE THAT ARE ABSOLUTE VALUES EXCEEDING

+/- 5%, BETWEEN THE SCHEDULE OF RECORD, AT THE BEGINNING AND END

OF EACH SPECIFIED PERIOD BY WEEK AND IN TOTAL SHALL BE EXPLAINED

IN THE PERFORMANCE ANALYSIS.

• THE REASONS FOR THE SIGNIFICANT CHANGES SHALL BE DISCUSSED IN THE

PERFORMANCE ANALYSIS.

BLOCK 6.C – SCHEDULE OF RECORD (END OF PERIOD). ENTER IN BLOCK 6.C THE

TIME-PHASED SOR AS IT EXISTS AT THE END OF THE REPORTING PERIOD.

COLUMN (2) - BCWS - CUMULATIVE TO DATE. ON THE SOR (BEGINNING OF

PERIOD) LINE (BLOCK 6.A), ENTER THE CUMULATIVE BCWS AS OF THE FIRST

DAY OF THE REPORTING PERIOD.

COLUMN (3) - BCWS FOR REPORT PERIOD. ON THE SOR (BEGINNING OF PERIOD)

LINE (BLOCK 6.A),ENTER THE BCWS PLANNED FOR THE REPORTING PERIOD.

COLUMNS (4) THROUGH (14). ENTER THE WEEK START DATE IN THE HEADINGS OF

EACH OF THE COLUMNS (4) THROUGH (8). COLUMN (4) THROUGH (8) SHALL

REFLECT 5 FORECAST WEEKS. COLUMN (9) SHALL BE TITLED “2ND MONTH

REMAINDER” AND SHALL REPRESENT THE PERIOD STARTING ON THE 6TH FORECAST

WEEK AND CONCLUDING AT THE START OF 1ST DAY OF SECOND TO NEXT MONTH.

COLUMNS (10) THROUGH (13). ENTER THE NAMES OF EACH MONTH FOR THE

REMAINING CONTRACT PERIOD OF PERFORMANCE IN THE HEADINGS OF EACH OF

THE COLUMNS (10) THROUGH (14).

ENTER THE NAMES OF THE APPROPRIATE PERIODS, AS DEFINED IN THE CDRL OR

DETERMINED BY THE CONTRACTOR, IF UNDEFINED, IN THE HEADINGS OF EACH OF

THE COLUMNS (10) THROUGH (14) OF BLOCK 6.

IN THE SOR (BEGINNING OF PERIOD) LINE (BLOCK 6.A), ENTER THE BCWS AS

REPORTED IN THE SCHEDULE OF RECORD (SOR) REPORT OF THE PREVIOUS SOR

(END OF PERIOD).

IN THE SOR (BASELINE CHANGES AUTHORIZED DURING REPORTING PERIOD) LINE

(BLOCK 6.B) ENTER THE TIME-PHASED CHANGES.

COLUMN (15) - TOTAL BUDGET. ON THE SOR (BEGINNING OF PERIOD) LINE

(BLOCK 6.A) ENTER THE NUMBER FROM COLUMN (16) ON THE SOR (END OF

PERIOD) LINE (BLOCK 6.C) FROM THE PREVIOUS IPMR. IN THE SECTION WHERE

BASELINE CHANGES THAT OCCURRED DURING THE PERIOD ARE LISTED (COLUMN

(1) OF BLOCK 6.B), ENTER THE AMOUNT OF EACH OF THE CHANGES LISTED.

ON THE TOTAL BASELINE CHANGES AUTHORIZED DURING REPORT PERIOD LINE

(BLOCK 6.B), ENTER THE SUM OF THE AMOUNTS IN THE PRECEDING COLUMNS.

ON THE SOR (END OF PERIOD) LINE (BLOCK 6.C), ENTER THE SUM OF THE

AMOUNTS IN THE PRECEDING COLUMNS ON THIS LINE.

ON THE TOTAL LINE (BLOCK 8) ENTER THE SUM OF THE AMOUNTS IN THIS

COLUMN ON THE SOR (END OF PERIOD) LINE AND THE MR LINE. [NOTE: THIS

SHALL EQUAL THE AMOUNT IN BLOCK 5.F ON THIS FORMAT AND THE AMOUNT OF

THE TOTAL LINE IN COLUMN (14), BLOCK 8.G, OF THE WORK ITEM PERFORMANCE

REPORT.]

WORK ITEM STAFFING PERFORMANCE REPORTS (PLAN)/(ACTUAL) INSTRUCTIONS:

REPORTING SHALL BE PROVIDED ON A WEEKLY BASIS. REPORTING SHALL PROVIDE

TOTAL PRIME AND SUBCONTRACTOR PRODUCTION STAFFING HOURS AT THE WORK

ITEM LEVEL. PLANNED AND ACTUAL SUBCONTRACTOR STAFFING MAY BE ESTIMATED

BASED ON PLANNED AND ACTUAL PRIME CONTRACTOR OUTLAYS.

THE STAFFING PERFORMANCE REPORTS SHALL FOLLOW THE SAME FORMAT AS THE

SCHEDULE OF RECORD (SOR) REPORT, IN BLOCKS 1-5. THE COLUMNS (4)

THROUGH (14) SHALL REPRESENT THE SAME TIME PERIODS AS REFLECTED IN THE

SCHEDULE OF RECORD (SOR) REPORT.

PERFORMANCE DATA. FOR EACH WORK ITEM INCLUDED IN COLUMN (1) OF BLOCK

6, EQUIVALENT MONTHS SHALL BE INDICATED FOR THE CURRENT REPORTING

PERIOD (COLUMN (2)), CUMULATIVE THROUGH THE CURRENT PERIOD (COLUMN

(3)), FORECAST TO COMPLETION (COLUMNS (4) THROUGH (14)), AND AT

COMPLETION (COLUMN(15)).

• THE REPORTABLE UNIT SHALL SHOW STAFFING IN EQUIVALENT PERSON AND

MAJOR SUBCONTRACTORS SHALL BE REPORTED

• DIRECT EQUIVALENT MONTHS SHALL BE SHOWN FOR EACH WORK ITEM

INCLUDED IN THE CONTRACT. AN EQUIVALENT PERSON IS DEFINED AS THE

EFFORT EQUAL TO THAT OF ONE PERSON FOR THE REPORTING TIME PERIOD.

• VALUES SHALL BE REPORTED IN WHOLE NUMBERS. [NOTE: PARTIAL MONTHS

SHALL BE ROUNDED; 0.5 AND ABOVE SHALL BE ROUNDED TO 1; BELOW 0.5

ROUNDED TO 0.]

COLUMN (1) - ORGANIZATIONAL CATEGORY. IN BLOCK 5, LIST ALL AWARDED

WORK ITEMS IN THE AVAILABILITY.

PLANNED STAFFING

COLUMN (2) - PLANNED - CURRENT PERIOD. ENTER THE PLANNED UNITS

INCURRED DURING THE CURRENT REPORTING PERIOD.

COLUMN (3) - PLANNED END OF CURRENT PERIOD (CUMULATIVE). ENTER THE

PLANNED UNITS TO BE INCURRED TO DATE (CUMULATIVE) AS OF THE END OF THE

REPORTING PERIOD.

COLUMNS (4) THROUGH (14) – COLUMNS (4) THROUGH (14) SHALL REPRESENT

THE SAME TIME PERIODS AS REFLECTED IN THE SCHEDULE OF RECORD (SOR)

REPORT. ENTER THE STAFFING PLANNED FOR EACH PERIOD.

• THE PLANNED STAFFING SHALL REFLECT THE SAME STAFFING USED AS THE

BASIS FOR THE BAC IN COLUMN (14) ON THE WORK ITEM PERFORMANCE

REPORT AND THE SCHEDULE OF RECORD (END OF PERIOD) IN ROW 6.C OF

THE SCHEDULE OF RECORD REPORT.

COLUMN (15) – PLAN AT COMPLETION. ENTER THE NUMBER OF UNITS PLANNED

FOR THE TOTAL CONTRACT IN COLUMN (15) BY WORK ITEM. THIS ESTIMATE

SHALL BE CONSISTENT WITH THE BAC IN COLUMN (14) ON THE WORK ITEM

PERFORMANCE REPORT AND THE SCHEDULE OF RECORD (END OF PERIOD) IN ROW

6.C OF THE SCHEDULE OF RECORD REPORT.

TOTAL DIRECT. IN BLOCK 7, COLUMNS (2) THROUGH (15), ENTER THE SUM OF

ALL DIRECT UNITS FOR THE WORK ITEMS SHOWN IN COLUMN (1).w

ACTUAL AND FORECASTED STAFFING

COLUMN (2) - ACTUAL - CURRENT PERIOD. ENTER THE ACTUAL UNITS INCURRED

DURING THE CURRENT REPORTING PERIOD.

COLUMN (3) - ACTUAL END OF CURRENT PERIOD (CUMULATIVE). ENTER THE

INCURRED ACTUAL UNITS TO DATE (CUMULATIVE) AS OF THE END OF THE

REPORTING PERIOD.

COLUMNS (4) THROUGH (14) – COLUMNS (4) THROUGH (14) SHALL REPRESENT

THE SAME TIME PERIODS AS REFLECTED IN THE SCHEDULE OF RECORD (SOR)

REPORT. ENTER A STAFFING FORECAST BY MONTH FOR EACH PERIOD.

• THE STAFFING FORECAST SHALL BE UPDATED AS PART OF THE FORMAL EAC

PROCESS FOLLOWED BY THE CONTRACTOR.

• THE STAFFING FORECAST SHALL REFLECT THE SAME STAFFING ESTIMATE

USED AS THE BASIS FOR THE EAC IN COLUMN (15) ON THE WORK ITEM

PERFORMANCE REPORT.

COLUMN (15) – PLAN AT COMPLETION. ENTER THE NUMBER OF UNITS PLANNED

FOR THE TOTAL CONTRACT IN COLUMN (15) BY WORK ITEM. THIS ESTIMATE

SHALL BE CONSISTENT WITH THE EAC IN COLUMN (15) ON THE WORK ITEM

PERFORMANCE REPORT.

TOTAL DIRECT. IN BLOCK 7, COLUMNS (2) THROUGH (15), ENTER THE SUM OF

ALL DIRECT UNITS FOR THE WORK ITEMS SHOWN IN COLUMN (1).

TRADE STAFFING PERFORMANCE REPORTS (PLAN)/(ACTUAL) INSTRUCTIONS:

REPORTING SHALL BE PROVIDED ON A WEEKLY BASIS. REPORTING SHALL PROVIDE

TOTAL PRIME AND SUBCONTRACTOR PRODUCTION HOURS AT THE PRODUCTION TRADE

LEVEL. SUBCONTRACTOR LABOR SHALL BE REPORTED AS LABOR HOURS, NOT AS

MATERIAL DOLLARS. ACTUAL SUBCONTRACTOR HOURS MAY BE ESTIMATED BASED ON

PRIME CONTRACTOR OUTLAYS.

THE TRADE PERFORMANCE REPORT SHALL FOLLOW THE SAME FORMAT AS THE WORK

ITEM STAFFING PERFORMANCE REPORTS, EXCEPT THAT UNDER COLUMN (1A) –

TRADE, THE CONTRACTOR SHALL ENTER IN COLUMN (1) OF BLOCK 6.A THE TRADE

AGAINST WHICH COST INFORMATION IS BEING REPORTED.