CDRL A015 Enclosure 1 (BLK 16) FEB19.pdf
PDF 282 KB Posted
- Solicitation number
- N00024-20-R-4404
About this file
This document contains a solicitation for the USS WASP (LHD 1) FY21 Dry-Docking Selected Restricted Availability. The Naval Sea Systems Command seeks to execute maintenance, modernization, and repair of the USS WASP through a single-award contract with a capable contractor. Interested offerors must register in the System for Award Management and monitor the beta.SAM.gov site for solicitation release and amendments. While certain work packages and attachments will not be posted to beta.SAM.gov, interested parties may request them from specified Navy contacts. The availability start date is anticipated to be December 2020, with delivery of the USS WASP required by April 2022. Proposals are due in August 2020 and award will be made on or around that same date. The work will be performed at the contractor's East or Gulf Coast facility and includes a combination of maintenance, modernization, and repair for the USS WASP class.
View the file
Other files
Show 40 more
Latest 50 of 53 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(BLK 4) SUBMISSIONS: PROVIDED THE FOLLOWING REPORTS WITHIN 5 DAYS
WORKING DAYS AFTER THE CLOSE OF THE REPORTED WEEK.
DEFINTIONS
BUDGETED COST OF WORK SCHEDULED (BCWS) IS THE SUM OF THE BUDGETS FOR
ALL WORK SCHEDULED TO BE ACCOMPLISHED WITH A GIVEN TIME PERIOD.
BUDGETED COST OF WORK PERFORMED (BCWP) IS THE BUDGETED COST OF THE
VALUE OF WORK THAT HAS ACTUALLY BEEN ACCOMPLISHED OR COMPLETED TO
DATE.
ACTUAL COST OF WORK PERFORMED (ACWP) IS THE COST INCURRED AND RECORDED
FOR WORK COMPLETED WITHIN A GIVEN TIME PERIOD. THE ACWP IS REPORTED BY
THE CONTRACTOR’S ACCOUNTING SYSTEM IN ACCORDANCE WITH GENERALLY
ACCEPTED ACCOUNTING PROCEDURES AND IS SIMPLY STATED ACTUALS ARE
ACTUALS.
BUDGET AT COMPLETION (BAC) REPRESENT THE TOTAL BUDGET FROM WHICH
INDIVIDUAL PERIOD BUDGETED COST OF WORK SCHEDULED (BCWS) VALUES ARE
DERIVED AND THEY ARE THE BENCHMARKS FOR COMPUTING OVERRUNS AND UNDER
RUNS AT THE END OF THE CONTRACT. THE BUDGETS FOR ALL AUTHORIZED WORK
MUST BE CAPTURED WITHIN THE BAC.
ESTIMATE AT COMPLETE (EAC) IS THE SUM OF THE CONTRACT'S CUMULATIVE TO-
DATE ACTUAL COST OF WORK PERFORMED (ACWP) PLUS THE ESTIMATE OF THE
TIME-PHASED RESOURCES REQUIRED TO COMPLETE THE REMAINING AUTHORIZED
WORK.
THE CONTRACTOR SHALL PROVIDE THE FOLLOWING DELIVERABLES, IN ACCORDANCE
WITH ENCLOSURE (2) AND THE INSTRUCTIONS BELOW:
COMMON HEADING INFORMATION (APPLICABLE TO ALL REPORTS)
CONTRACTOR ENTER IN BLOCK 1.A THE CONTRACTOR'S NAME AND DIVISION (IF
APPLICABLE). ENTER IN BLOCK 1.B THE FACILITY LOCATION AND MAILING
ADDRESS OF THE REPORTING CONTRACTOR.
CONTRACT. ENTER THE CONTRACT INFORMATION IN BLOCK 2.
• ENTER THE CONTRACT NAME IN BLOCK 2.A;
• ENTER THE CONTRACT NUMBER AND THE APPLICABLE CONTRACT LINE ITEM
NUMBER(S) (CLIN(S) IN BLOCK 2.B;
• ENTER “FFP” IN BLOCK 2.C;
• ENTER “NOT APPLICABLE” IN BLOCK 2.D;
PROGRAM. ENTER IN THE PROGRAM INFORMATION IN BLOCK 3.
• ENTER THE VESSEL’S NAME AND HULL NUMBER UNDERGOING REPAIRS IN
BLOCK 3.A;
• ENTER THE AVAILABILITY TYPE (E.G. SRA, DPMA, ETC) IN BLOCK 3.B.;
• LEAVE BLANK BLOCK 3.C.
REPORT PERIOD. ENTER THE BEGINNING DATE IN BLOCK 4.A AND THE ENDING
DATE IN BLOCK 4.B OF THE TIME PERIOD COVERED BY THE REPORT.
SECURITY. ALL ELECTRONIC FILE DELIVERABLES SHALL INCLUDE THE
APPROPRIATE SECURITY DESIGNATIONS.
DOLLARS IN. IF REPORTED DOLLAR AMOUNTS ARE NOT IN WHOLE DOLLARS, ENTER
THE UNITS USED (E.G. $K, $M, $B) AT THE TOP OF EACH PAGE.
WORK ITEM PERFORMANCE REPORT INSTRUCTIONS:
REPORTING SHALL BE PROVIDED ON A WEEKLY BASIS. REPORTING SHALL PROVIDE
TOTAL PRIME AND SUBCONTRACTOR PRODUCTION HOURS AT THE WORK ITEM LEVEL.
SUBCONTRACTOR LABOR SHALL BE REPORTED AS LABOR HOURS, NOT AS MATERIAL
DOLLARS. ACTUAL SUBCONTRACTOR HOURS MAY BE ESTIMATED BASED ON PRIME
CONTRACTOR OUTLAYS.
• BLOCK 5.A – NOT APPLICABLE
• NEGOTIATED PRODUCTION HOURS. ENTER IN BLOCK 5.B THE NUMBER OF
PRODUCTION HOURS (BOTH PRIME AND SUBCONTRACTOR) ON WHICH
CONTRACTUAL AGREEMENT WAS REACHED AS OF THE REFLECTED REPORTING
PERIOD. AMOUNTS FOR CHANGES SHALL NOT BE INCLUDED UNTIL THEY HAVE
BEEN DEFINITIZED IN THE CONTRACT.
• ESTIMATED PRODUCTION HOURS FOR AUTHORIZED, UNPRICED WORK (AUW).
AUTHORIZED, UNPRICED WORK IS APPROVED WORK SCOPE THAT HAS NOT
BEEN DEFINITIZED. THE ESTIMATED NUMBER OF PRODUCTION HOURS (BOTH
PRIME AND SUBCONTRACTOR) OF AUW SHALL BE ENTERED IN BLOCK 5.C.
THE VALUE OF AUW IS THE VALUE OF THE SCOPE THAT WAS COORDINATED
BETWEEN THE CONTRACTOR AND THE PROGRAM OFFICE, AND AUTHORIZED BY
THE CONTRACTING OFFICER. AUW CAN NEVER BE A NEGATIVE VALUE. FOR
EFFORT DE-SCOPED AND NOT YET REFLECTED IN THE CONTRACT BUDGET
BASE (CBB), REPORT THE ESTIMATED VALUE IN THE PERFORMANCE
ANALYSIS.
• BLOCK 5.D – NOT APPLICABLE
• BLOCK 5.E – NOT APPLICABLE
• ESTIMATED PRODUCTION HOURS. BASED ON THE CONTRACTOR’S MOST LIKELY
ESTIMATE OF THE NUMBER OF PRODUCTION HOURS (BOTH PRIME AND
SUBCONTRACTOR) EXPENDED AT COMPLETION FOR ALL AUTHORIZED WORK,
ENTER IN BLOCK 5.F THE ESTIMATED FINAL PRODUCTION HOURS. THIS
NUMBER SHALL BE BASED ON THE CONTRACTOR’S MOST LIKELY MANAGEMENT
EAC IN BLOCK 6.C.1 AND NORMALLY WILL CHANGE WHEN THE EAC IS
UPDATED AND/OR WHEN THE CONTRACT IS REVISED.
• BLOCK 5.G – NOT APPLICABLE
• BLOCK 5.H – NOT APPLICABLE
• OVER TARGET BASELINE (OTB)/OVER TARGET SCHEDULE (OTS). ENTER IN
BLOCK 5.I THE DATE THE LAST OTB OR OTS WAS IMPLEMENTED, IF
APPLICABLE.
• MANAGEMENT ESTIMATE AT COMPLETION - MOST LIKELY. ENTER IN BLOCK
6.C.1 THE CONTRACTOR'S MOST LIKELY EAC. THIS EAC IS THE
CONTRACTOR'S OFFICIAL CONTRACT EAC. THE MOST LIKELY EAC IS THE
VALUE THAT THE CONTRACTOR'S MANAGEMENT BELIEVES IS THE MOST
POSSIBLE OUTCOME BASED ON A KNOWLEDGEABLE ESTIMATION OF ALL
AUTHORIZED WORK, KNOWN FACTORED RISKS, AND PROBABLE FUTURE
CONDITIONS. THIS VALUE SHALL AGREE WITH THE TOTAL OF COLUMN (15)
(BLOCK 8.E).
• CONTRACT BUDGET BASE (CBB). ENTER IN BLOCK 6.C.2 THE TOTAL NUMBER
OF NEGOTIATED PRODUCTION HOURS (BLOCK 5.B) AND ESTIMATED NUMBER
OF PRODUCTION HOURS OF AUTHORIZED, UNPRICED WORK (BLOCK 5.C).
PERFORMANCE DATA.
• COLUMN (1A) - WORK ITEM NUMBER. ENTER IN COLUMN (1A) OF BLOCK 8.A
THE WORK ITEM NUMBER AGAINST WHICH COST INFORMATION IS BEING
REPORTED.
• COLUMN (1B) - DESCRIPTION. ENTER IN COLUMN (1B) OF BLOCK 8.A THE
ITEM DESCRIPTION AGAINST WHICH COST INFORMATION IS BEING
REPORTED.
• TOTAL. IN COLUMNS (2) THROUGH (16) OF BLOCKS 8.A, ENTER THE SUM
OF THE PRODUCTION HOURS FOR THE REPORTED WORK ITEMS.
PERFORMANCE DATA COLUMNS (2) THROUGH (16).
• COLUMN (2) AND COLUMN (7) - BUDGETED COST - WORK SCHEDULED. FOR
THE REPORT PERIOD NOTED, ENTER THE BCWS IN THESE COLUMNS.
• COLUMN (3) AND COLUMN (8) - BUDGETED COST - WORK PERFORMED. FOR
THE REPORT PERIOD NOTED, ENTER THE BCWP IN THESE COLUMNS.
• COLUMN (4) AND COLUMN (9) - ACTUAL COST - WORK PERFORMED. FOR THE
REPORT PERIOD NOTED, ENTER THE ACWP IN THESE COLUMNS WITHOUT
REGARD TO CEILING. IN ALL CASES, COSTS AND BUDGETS SHALL BE
REPORTED ON A COMPARABLE BASIS.
• COLUMN (5) AND COLUMN (10) - VARIANCE – SCHEDULE. FOR THE REPORT
PERIOD, THESE COLUMNS SHALL REFLECT THE DIFFERENCES BETWEEN BCWS
AND BCWP.
o FOR THE CURRENT PERIOD COLUMN, COLUMN (5) (SCHEDULE
VARIANCE) IS DERIVED BY SUBTRACTING COLUMN (2) (BCWS) FROM
COLUMN (3) (BCWP).
o FOR THE CUMULATIVE TO DATE COLUMN, COLUMN (10) (SCHEDULE
VARIANCE) IS DERIVED BY SUBTRACTING COLUMN (7) (BCWS) FROM
COLUMN (8) (BCWP).
o A POSITIVE NUMBER IN COLUMN (5) AND COLUMN (10) INDICATES A
FAVORABLE VARIANCE. A NEGATIVE NUMBER INDICATES AN
UNFAVORABLE VARIANCE.
• COLUMN (6) AND COLUMN (11) - VARIANCE - COST. FOR THE REPORT
PERIOD, THESE COLUMNS SHALL REFLECT THE DIFFERENCE BETWEEN BCWP
AND ACWP.
o FOR THE CURRENT PERIOD COLUMN, COLUMN (6) (COST VARIANCE)
IS DERIVED BY SUBTRACTING COLUMN (4) (ACWP) FROM COLUMN (3)
(BCWP).
o FOR THE CUMULATIVE TO DATE COLUMN, COLUMN (11) (COST
VARIANCE) IS DERIVED BY SUBTRACTING COLUMN (9) (ACWP) FROM
COLUMN (8) (BCWP).
o A POSITIVE VALUE INDICATES A FAVORABLE VARIANCE. A NEGATIVE
VALUE INDICATES AN UNFAVORABLE VARIANCE.
• COLUMN (12) – NOT APPLICABLE
• COLUMN (13) – NOT APPLICABLE
• COLUMN (14) – NOT APPLICABLE
• COLUMN (15) - AT COMPLETION - ESTIMATED. ENTER THE LATEST REVISED
ESTIMATE OF COST AT COMPLETION INCLUDING ANY ESTIMATED
OVERRUN/UNDERRUN FOR ALL AUTHORIZED WORK.
• COLUMN (16) - AT COMPLETION - VARIANCE. ENTER THE DIFFERENCE
BETWEEN THE EAC COLUMN (15) AND THE BAC COLUMN (14) BY
SUBTRACTING THE EAC COLUMN FROM THE BAC COLUMN. THIS VARIANCE AT
COMPLETION (VAC), WHEN NEGATIVE, REFLECTS AN UNFAVORABLE
POSITION.
SCHEDULE OF RECORD (SOR) REPORT INSTRUCTIONS:
THIS DELIVERABLE DEFINES CHANGES TO THE SCHEDULE OF RECORD (SOR), AS
DEFINED IN NSI 009-60 PARAGRAPH 3.1.4, AND IS TO BE PROVIDED ON A
WEEKLY BASIS. THE BASELINE CHANGE BREAKOUT SHOULD BE BY WEEK FOR THE
NEXT FIVE WEEKS, A REMAINDER PERIOD BETWEEN FIVE WEEKS AND THE START
OF SECOND TO NEXT MONTH, AND THEN MONTHLY THEREAFTER.
• ORIGINAL NEGOTIATED PRODUCTION HOURS. ENTER IN BLOCK 5.A THE
NUMBER OF HOURS NEGOTIATED IN THE ORIGINAL CONTRACT. The production hours included in the contractor’s Schedule of Record shall equal:
o The production hours for each work item included in the solicitation as both Base and Option items (as proposed in the offeror’s J-4 and J-14), o Production Hours shall align to the definition of production hours provided in Section B, Note B entitled
“FIXED SHIP REPAIR LABOR AND MATERIAL BURDEN RATES FOR
BASE, GROWTH AND NEW WORK”.
o Any contractual changes to work items included in the solicitation as both Base and Option items made after award but prior to Availability execution (as applicable), and o Work item scope negotiated into the contract over and above the requirements of the solicited work package utilizing the Base work LOE to completion CLINs (as applicable).
• NEGOTIATED CONTRACT CHANGES. ENTER IN BLOCK 5.B THE TOTAL NUMBER
OF PRODUCTION HOURS OF ALL DEFINITIZED CONTRACT CHANGES THAT HAVE
OCCURRED SINCE DEFINITIZATION OF THE ORIGINAL CONTRACT.
• CURRENT NEGOTIATED PRODUCTION HOURS. ENTER IN BLOCK 5.C THE SUM
OF BLOCKS 5.A AND 5.B. THE AMOUNT SHOWN SHALL EQUAL THE AMOUNT IN
NEGOTIATED COST (BLOCK 5.B) IN THE WORK ITEM PERFORMANCE REPORT.
• ESTIMATED PRODUCTION HOURS FOR AUTHORIZED, UNPRICED WORK (AUW).
ENTER IN BLOCK 5.D THE AUW AMOUNT CONSISTENT WITH WORK ITEM
PERFORMANCE REPORT BLOCK 5.C.
• CONTRACT BUDGET BASE (CBB). ENTER IN BLOCK 5.E THE SUM OF BLOCKS
5.C AND 5.D.
• TOTAL ALLOCATED BUDGET (TAB). ENTER IN BLOCK 5.F THE SUM OF ALL
PRODUCTION HOUR BUDGETS ALLOCATED TO THE PERFORMANCE OF THE
CONTRACTUAL EFFORT.
THIS AMOUNT SHALL BE THE SAME AS THAT SHOWN ON THE TOTAL LINE IN
COLUMN (14) IN THE WORK ITEM PERFORMANCE REPORT (BLOCK 8.B).
DIFFERENCE. ENTER IN BLOCK 5.G THE DIFFERENCE BETWEEN BLOCKS 5.E AND
5.F.
CONTRACT START DATE. ENTER IN BLOCK 5.H THE DATE THE CONTRACTOR WAS
AUTHORIZED TO START WORK ON THE CONTRACT, REGARDLESS OF THE DATE OF
CONTRACT DEFINITIZATION.
CONTRACT DEFINITIZATION DATE. ENTER IN BLOCK 5.I THE DATE THE CONTRACT
WAS ORIGINALLY AWARDED.
PLANNED COMPLETION DATE. ENTER IN BLOCK 5.J THE COMPLETION DATE FOR
WHICH THE BUDGETS ALLOCATED IN THE SOR HAVE BEEN PLANNED. THIS DATE
REPRESENTS THE PLANNED COMPLETION OF ALL EFFORTS ON THE CONTRACT.
THE NUMBER OF PRODUCTION HOURS ASSOCIATED WITH THIS DATE’S SCHEDULED
EFFORTS IS THE TAB (BLOCK 5.F OF THE SCHEDULE OF RECORD (SOR) REPORT).
THE CONTRACTOR MAY RE-PHASE THE SOR SCHEDULE TO NEW DATES THAT EXCEED
THE CONTRACTUAL MILESTONES, A CONDITION KNOWN AS AN OTS, WITH
GOVERNMENT APPROVAL. THESE NEW SCHEDULE DATES ARE FOR PERFORMANCE
MEASUREMENT PURPOSES ONLY AND DO NOT REPRESENT AN AGREEMENT TO MODIFY
THE CONTRACT TERMS AND CONDITIONS.
THE GOVERNMENT AND THE CONTRACTOR SHALL AGREE ON THE NEW SOR SCHEDULE
PRIOR TO REPORTING IT. THE CONTRACTOR SHALL PROVIDE PERTINENT
INFORMATION IN THE PERFORMANCE ANALYSIS ON ANY SCHEDULE MILESTONES
THAT ARE INCONSISTENT WITH CONTRACTUAL MILESTONES, BEGINNING THE MONTH
THE OTS IS IMPLEMENTED AND EACH MONTH THEREAFTER.
CONTRACT COMPLETION DATE. ENTER IN BLOCK 5.K THE CONTRACT SCHEDULED
COMPLETION DATE IN ACCORDANCE WITH THE LATEST CONTRACT MODIFICATION.
THE COST ASSOCIATED WITH THE SCHEDULE FROM WHICH THIS DATE IS TAKEN IS
THE CBB (BLOCK 5.E OF THE SCHEDULE OF RECORD (SOR) REPORT).
ESTIMATED COMPLETION DATE. ENTER IN BLOCK 5.L THE CONTRACTOR'S LATEST
ESTIMATED COMPLETION DATE. THIS DATE SHALL BE CONSISTENT WITH THE
UNDERLYING ASSUMPTIONS BEHIND BLOCK 6.C.1 OF THE WORK ITEM PERFORMANCE
REPORT.
PERFORMANCE DATA (BLOCK 6).
BLOCK 6.A – SCHEDULE OF RECORD (BEGINNING OF PERIOD). ENTER IN BLOCK
6.A THE TIME-PHASED SOR VALUE AS IT EXISTED AT THE BEGINNING OF THE
CURRENT REPORTING PERIOD. NORMALLY THE ENTRIES ON THIS LINE (E.G., FOR
COLUMNS (4) THROUGH (9)) ARE TAKEN DIRECTLY FROM THE SOR (END OF
PERIOD) LINE ON THE PREVIOUS REPORT.
BASELINE CHANGES AUTHORIZED DURING REPORT PERIOD.
IN BLOCK 6.B, LIST ALL SIGNIFICANT BASELINE CHANGES THAT HAVE OCCURRED
DURING THE REPORTING PERIOD IN THEIR RESPECTIVE TIMEFRAMES IN COLUMNS
(2)-(15).
• THIS LIST SHALL INCLUDE THE CONTRACT CHANGES AND AUW AUTHORIZED
DURING THE REPORTING PERIOD, AND ANY SIGNIFICANT RE-PHASING OF
BUDGETS.
• ALL SIGNIFICANT AUTHORIZED BASELINE CHANGES SHALL BE LISTED
INDIVIDUALLY, WHETHER PRICED OR UNPRICED; ALL OTHER CHANGES SHALL
BE SUMMARIZED AND TITLED “OTHER.”
• BLOCK 6.B, WHEN ADDED TO BLOCK 6.A, EQUALS BLOCK 6.C.
• SIGNIFICANT DIFFERENCES, THOSE THAT ARE ABSOLUTE VALUES EXCEEDING
+/- 5%, BETWEEN THE SCHEDULE OF RECORD, AT THE BEGINNING AND END
OF EACH SPECIFIED PERIOD BY WEEK AND IN TOTAL SHALL BE EXPLAINED
IN THE PERFORMANCE ANALYSIS.
• THE REASONS FOR THE SIGNIFICANT CHANGES SHALL BE DISCUSSED IN THE
PERFORMANCE ANALYSIS.
BLOCK 6.C – SCHEDULE OF RECORD (END OF PERIOD). ENTER IN BLOCK 6.C THE
TIME-PHASED SOR AS IT EXISTS AT THE END OF THE REPORTING PERIOD.
COLUMN (2) - BCWS - CUMULATIVE TO DATE. ON THE SOR (BEGINNING OF
PERIOD) LINE (BLOCK 6.A), ENTER THE CUMULATIVE BCWS AS OF THE FIRST
DAY OF THE REPORTING PERIOD.
COLUMN (3) - BCWS FOR REPORT PERIOD. ON THE SOR (BEGINNING OF PERIOD)
LINE (BLOCK 6.A),ENTER THE BCWS PLANNED FOR THE REPORTING PERIOD.
COLUMNS (4) THROUGH (14). ENTER THE WEEK START DATE IN THE HEADINGS OF
EACH OF THE COLUMNS (4) THROUGH (8). COLUMN (4) THROUGH (8) SHALL
REFLECT 5 FORECAST WEEKS. COLUMN (9) SHALL BE TITLED “2ND MONTH
REMAINDER” AND SHALL REPRESENT THE PERIOD STARTING ON THE 6TH FORECAST
WEEK AND CONCLUDING AT THE START OF 1ST DAY OF SECOND TO NEXT MONTH.
COLUMNS (10) THROUGH (13). ENTER THE NAMES OF EACH MONTH FOR THE
REMAINING CONTRACT PERIOD OF PERFORMANCE IN THE HEADINGS OF EACH OF
THE COLUMNS (10) THROUGH (14).
ENTER THE NAMES OF THE APPROPRIATE PERIODS, AS DEFINED IN THE CDRL OR
DETERMINED BY THE CONTRACTOR, IF UNDEFINED, IN THE HEADINGS OF EACH OF
THE COLUMNS (10) THROUGH (14) OF BLOCK 6.
IN THE SOR (BEGINNING OF PERIOD) LINE (BLOCK 6.A), ENTER THE BCWS AS
REPORTED IN THE SCHEDULE OF RECORD (SOR) REPORT OF THE PREVIOUS SOR
(END OF PERIOD).
IN THE SOR (BASELINE CHANGES AUTHORIZED DURING REPORTING PERIOD) LINE
(BLOCK 6.B) ENTER THE TIME-PHASED CHANGES.
COLUMN (15) - TOTAL BUDGET. ON THE SOR (BEGINNING OF PERIOD) LINE
(BLOCK 6.A) ENTER THE NUMBER FROM COLUMN (16) ON THE SOR (END OF
PERIOD) LINE (BLOCK 6.C) FROM THE PREVIOUS IPMR. IN THE SECTION WHERE
BASELINE CHANGES THAT OCCURRED DURING THE PERIOD ARE LISTED (COLUMN
(1) OF BLOCK 6.B), ENTER THE AMOUNT OF EACH OF THE CHANGES LISTED.
ON THE TOTAL BASELINE CHANGES AUTHORIZED DURING REPORT PERIOD LINE
(BLOCK 6.B), ENTER THE SUM OF THE AMOUNTS IN THE PRECEDING COLUMNS.
ON THE SOR (END OF PERIOD) LINE (BLOCK 6.C), ENTER THE SUM OF THE
AMOUNTS IN THE PRECEDING COLUMNS ON THIS LINE.
ON THE TOTAL LINE (BLOCK 8) ENTER THE SUM OF THE AMOUNTS IN THIS
COLUMN ON THE SOR (END OF PERIOD) LINE AND THE MR LINE. [NOTE: THIS
SHALL EQUAL THE AMOUNT IN BLOCK 5.F ON THIS FORMAT AND THE AMOUNT OF
THE TOTAL LINE IN COLUMN (14), BLOCK 8.G, OF THE WORK ITEM PERFORMANCE
REPORT.]
WORK ITEM STAFFING PERFORMANCE REPORTS (PLAN)/(ACTUAL) INSTRUCTIONS:
REPORTING SHALL BE PROVIDED ON A WEEKLY BASIS. REPORTING SHALL PROVIDE
TOTAL PRIME AND SUBCONTRACTOR PRODUCTION STAFFING HOURS AT THE WORK
ITEM LEVEL. PLANNED AND ACTUAL SUBCONTRACTOR STAFFING MAY BE ESTIMATED
BASED ON PLANNED AND ACTUAL PRIME CONTRACTOR OUTLAYS.
THE STAFFING PERFORMANCE REPORTS SHALL FOLLOW THE SAME FORMAT AS THE
SCHEDULE OF RECORD (SOR) REPORT, IN BLOCKS 1-5. THE COLUMNS (4)
THROUGH (14) SHALL REPRESENT THE SAME TIME PERIODS AS REFLECTED IN THE
SCHEDULE OF RECORD (SOR) REPORT.
PERFORMANCE DATA. FOR EACH WORK ITEM INCLUDED IN COLUMN (1) OF BLOCK
6, EQUIVALENT MONTHS SHALL BE INDICATED FOR THE CURRENT REPORTING
PERIOD (COLUMN (2)), CUMULATIVE THROUGH THE CURRENT PERIOD (COLUMN
(3)), FORECAST TO COMPLETION (COLUMNS (4) THROUGH (14)), AND AT
COMPLETION (COLUMN(15)).
• THE REPORTABLE UNIT SHALL SHOW STAFFING IN EQUIVALENT PERSON AND
MAJOR SUBCONTRACTORS SHALL BE REPORTED
• DIRECT EQUIVALENT MONTHS SHALL BE SHOWN FOR EACH WORK ITEM
INCLUDED IN THE CONTRACT. AN EQUIVALENT PERSON IS DEFINED AS THE
EFFORT EQUAL TO THAT OF ONE PERSON FOR THE REPORTING TIME PERIOD.
• VALUES SHALL BE REPORTED IN WHOLE NUMBERS. [NOTE: PARTIAL MONTHS
SHALL BE ROUNDED; 0.5 AND ABOVE SHALL BE ROUNDED TO 1; BELOW 0.5
ROUNDED TO 0.]
COLUMN (1) - ORGANIZATIONAL CATEGORY. IN BLOCK 5, LIST ALL AWARDED
WORK ITEMS IN THE AVAILABILITY.
PLANNED STAFFING
COLUMN (2) - PLANNED - CURRENT PERIOD. ENTER THE PLANNED UNITS
INCURRED DURING THE CURRENT REPORTING PERIOD.
COLUMN (3) - PLANNED END OF CURRENT PERIOD (CUMULATIVE). ENTER THE
PLANNED UNITS TO BE INCURRED TO DATE (CUMULATIVE) AS OF THE END OF THE
REPORTING PERIOD.
COLUMNS (4) THROUGH (14) – COLUMNS (4) THROUGH (14) SHALL REPRESENT
THE SAME TIME PERIODS AS REFLECTED IN THE SCHEDULE OF RECORD (SOR)
REPORT. ENTER THE STAFFING PLANNED FOR EACH PERIOD.
• THE PLANNED STAFFING SHALL REFLECT THE SAME STAFFING USED AS THE
BASIS FOR THE BAC IN COLUMN (14) ON THE WORK ITEM PERFORMANCE
REPORT AND THE SCHEDULE OF RECORD (END OF PERIOD) IN ROW 6.C OF
THE SCHEDULE OF RECORD REPORT.
COLUMN (15) – PLAN AT COMPLETION. ENTER THE NUMBER OF UNITS PLANNED
FOR THE TOTAL CONTRACT IN COLUMN (15) BY WORK ITEM. THIS ESTIMATE
SHALL BE CONSISTENT WITH THE BAC IN COLUMN (14) ON THE WORK ITEM
PERFORMANCE REPORT AND THE SCHEDULE OF RECORD (END OF PERIOD) IN ROW
6.C OF THE SCHEDULE OF RECORD REPORT.
TOTAL DIRECT. IN BLOCK 7, COLUMNS (2) THROUGH (15), ENTER THE SUM OF
ALL DIRECT UNITS FOR THE WORK ITEMS SHOWN IN COLUMN (1).w
ACTUAL AND FORECASTED STAFFING
COLUMN (2) - ACTUAL - CURRENT PERIOD. ENTER THE ACTUAL UNITS INCURRED
DURING THE CURRENT REPORTING PERIOD.
COLUMN (3) - ACTUAL END OF CURRENT PERIOD (CUMULATIVE). ENTER THE
INCURRED ACTUAL UNITS TO DATE (CUMULATIVE) AS OF THE END OF THE
REPORTING PERIOD.
COLUMNS (4) THROUGH (14) – COLUMNS (4) THROUGH (14) SHALL REPRESENT
THE SAME TIME PERIODS AS REFLECTED IN THE SCHEDULE OF RECORD (SOR)
REPORT. ENTER A STAFFING FORECAST BY MONTH FOR EACH PERIOD.
• THE STAFFING FORECAST SHALL BE UPDATED AS PART OF THE FORMAL EAC
PROCESS FOLLOWED BY THE CONTRACTOR.
• THE STAFFING FORECAST SHALL REFLECT THE SAME STAFFING ESTIMATE
USED AS THE BASIS FOR THE EAC IN COLUMN (15) ON THE WORK ITEM
PERFORMANCE REPORT.
COLUMN (15) – PLAN AT COMPLETION. ENTER THE NUMBER OF UNITS PLANNED
FOR THE TOTAL CONTRACT IN COLUMN (15) BY WORK ITEM. THIS ESTIMATE
SHALL BE CONSISTENT WITH THE EAC IN COLUMN (15) ON THE WORK ITEM
PERFORMANCE REPORT.
TOTAL DIRECT. IN BLOCK 7, COLUMNS (2) THROUGH (15), ENTER THE SUM OF
ALL DIRECT UNITS FOR THE WORK ITEMS SHOWN IN COLUMN (1).
TRADE STAFFING PERFORMANCE REPORTS (PLAN)/(ACTUAL) INSTRUCTIONS:
REPORTING SHALL BE PROVIDED ON A WEEKLY BASIS. REPORTING SHALL PROVIDE
TOTAL PRIME AND SUBCONTRACTOR PRODUCTION HOURS AT THE PRODUCTION TRADE
LEVEL. SUBCONTRACTOR LABOR SHALL BE REPORTED AS LABOR HOURS, NOT AS
MATERIAL DOLLARS. ACTUAL SUBCONTRACTOR HOURS MAY BE ESTIMATED BASED ON
PRIME CONTRACTOR OUTLAYS.
THE TRADE PERFORMANCE REPORT SHALL FOLLOW THE SAME FORMAT AS THE WORK
ITEM STAFFING PERFORMANCE REPORTS, EXCEPT THAT UNDER COLUMN (1A) –
TRADE, THE CONTRACTOR SHALL ENTER IN COLUMN (1) OF BLOCK 6.A THE TRADE
AGAINST WHICH COST INFORMATION IS BEING REPORTED.