This is an Independent Cost Estimate (ICE) document prepared by the Orange County Transportation Authority for a grants administration consultant support procurement. The Authority is seeking a qualified consultant to provide financial administration and grant management services on a part-time basis at 20 hours per week. The scope of work includes support in annual budget development, revenue accruals and forecasts, variance analyses, and funding analyses. The contract term is two years, with an option term date of 10/15/2025. The procurement was initiated by Rachel Mak, Senior Financial Analyst, with a budget authorization of $250,000.

The cost estimate totals $250,068.00 and is based entirely on direct labor costs for consultant services. The hourly billing rate of $168 per hour was derived from comparable historical contracts (C-3-2336 and C-4-2620) that documented similar consultant work at $160 per hour, with a 5% escalation applied. The estimate reflects 1,488.5 total estimated hours over the contract period. No overhead, materials, information technology support, travel, subcontractor, or other direct costs are included in this estimate. The ICE was prepared on 10/15/2025 and serves as the substantiation document required by the Contracts Administration & Materials Management (CAMM) department to proceed with the procurement process.

View the file

Other files

Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

INDEPENDENT COST ESTIMATE (ICE)

FA-CAMM-006.docm (09/25/15) Page 1 of 3

INSTRUCTIONS

Complete and submit all three pages to Contracts Administration & Materials Management (CAMM), along with your requisition and scope of work. CAMM will not start the procurement until all three documents have been received.

PART I – GENERAL INFORMATION

Project Description: Grants Administration Consultant Support

SHADED AREA FOR PROCUREMENT USE ONLY

Assigned Buyer No.:

D/M/WBE%:

Purchase Requisition No.: R000850

New Contract / Procurement

Contract Amendment Current IFAS Printout Contract / PO No.:

(Required for Amendments)

Contract Task Order

Option Term

Date: 10/15/2025

Requestor: Rachel Mak Senior Financial Analyst Phone Ext.: 5041

Name Title

Signature:

Cost

Estimate: $ 250,068.00 (include shipping, handling and taxes, if applicable)

PART II – ESTIMATE GUIDE

Please substantiate the estimate using the following information.

Estimate Type Items to Include Where to Find Supporting Information

Services (Other than A&E)

1. Tasks you want done

2. Types of people needed (i.e., supervisor, administrative assistant, other)

3. Positions required (i.e., Project Manager, Deputy PM, Senior Engineer / Planner, other)

4. Estimated hours by position

5. Salary / billing rates applied

6. Prevailing wage rate category applied

7. Profit / applied fee

8. Direct expenses

9. Completion schedule

1. Current or past contracts for similar services

2. Other properties / departments doing similar work

3. Historical price and cost data

Estimate Guide Continued

FA-CAMM-006.docm (09/25/15) Page 2 of 3

Estimate Type Items to Include Where to Find Supporting Information

Architects, Engineers, Designers

1. Tasks you want done

2. Types of people needed (i.e., engineers, administrative assistant, other)

3. Positions (Project Manager, Deputy PM, Senior Engineer / Planner, other)

4. Estimated hours by position

5. Salary / billing rates applied

6. Profit / applied fee

7. Overhead rate (%)

8. Direct expenses

9. Completion schedule

1. Current or past contracts for similar services

2. Other properties / departments doing similar work

3. Historical price and cost data

Goods/Equipment 1. Product needed

2. Quantity

3. Unit price

4. Markups, overhead, profit

5. Delivery schedule desired

6. Warranty

1. Vendor survey / market survey

2. Current or past contracts for the same or similar product

3. Historical price and cost data

4. Various published indices

Construction 1. Product needed

2. Labor (at a minimum use Davis Bacon)

3. Materials

4. Bonds

5. Insurance

6. Mobilization

7. Equipment

8. Markups, fringes, overheads, profit

9. Completion schedule

1. “Means Book”

2. “Blue Book”

3. Davis Bacon wage rates / prevailing wages

4. Current or past contracts for the same project

5. Historical price and cost data

Additional Information: The Grants & Revenue Administration department is seeking a Consultant to assist with finanical administration and grant management services on a part-time basis for 20 hours per week. The Consultant will provide support in areas such as annual budget development, revenue accruals, and forecast, variance and funding analyses.

The hourly rate is based on contracts C-3-2336 and C-4-2620, which reflect similar work performed by a consultant for $160 per hour, with an additional 5% escalation rate applied ($160 x (1+5%) = $168).

FA-CAMM-006.docm (09/25/15) Page 3 of 3

PART III – INDEPENDENT COST ESTIMATE

Using the information provided in Part II, prepare the ICE for your procurement.

Use any or all of the categories listed below.

Prepared By: Rachel Mak Date: 10/15/2025

Signature:

DESCRIPTION OF COST ELEMENTS

1. DIRECT LABOR

(List of Labor Categories)

Estimated Hours

Rate Per Hour ($)

Estimated Cost ($)

Total Est.

Cost ($)

Consultant 1,488.5 $ 168.00 $ 250,068.00 $ $ 0.00 $ $ 0.00 $ $ 0.00 $ $ 0.00 $ $ 0.00

Total Direct Labor: $ 250,068.00

2. OVERHEAD

Rate (%)

(use decimal input)

Total Labor ($)

Estimated Cost ($)

Total Est.

Cost ($)

% $ 250,068.00 $ 0.00 $ 0.00

3. MATERIALS/SERVICES (Excluding Information Technology [IT]) Estimated Cost ($)

Total Est.

Cost ($)

$ $ 0.00

4. INFORMATION TECHNOLOGY SUPPORT

Estimated Cost ($)

Total Est.

Cost ($)

Total IT Support: $ 0.00

5. TRAVEL

Estimated

Cost ($) Total Est.

Cost ($)

$ $ 0.00

6. SUBCONTRACTOR(S) / CONSULTANT(S)

Estimated

Cost ($) Total Est.

Cost ($)

Total Subcontractor(s) / Consultant(s): $ 0.00

7. OTHER DIRECT COSTS

Estimated

Cost ($) Total Est.

Cost ($)

$ $ 0.00

8. TOTAL ESTIMATED COST: $ 250,068.00