C250113_PS_12-08-25.doc

DOC document 49 KB Posted

Attached to
Move OC Active Transportation Plan
Solicitation number
250113
Issued by
Orange County, California

About this file

This is a procurement schedule document issued by the Orange County Transportation Authority (OCTA) for Request for Proposal 250113 regarding the Move OC Active Transportation Plan. The RFP will be issued on January 6, 2026, with advertisements placed on January 6 and 12, 2026. A pre-proposal conference is scheduled for January 14, 2026, at 10:00 a.m. in Room 09, available in both in-person and virtual formats. Written questions from proposers are due January 16, 2026, with OCTA's responses provided by January 21, 2026. Proposals must be submitted by 2:00 p.m. on February 4, 2026, followed by a pre-evaluation meeting at 4:00 p.m. the same day. The Evaluation Committee will review proposals on February 18, 2026, from 10:00 a.m. to 12:00 p.m., with interviews scheduled for February 26, 2026, from 9:00 a.m. to 4:00 p.m. The contract is anticipated to be executed by May 29, 2026, following a series of internal reviews and approvals by the Board of Directors on May 11, 2026. The contract term is three years.

The project budget is $1,000,000 for the three-year term. The procurement schedule requires approval from multiple organizational levels, including the CAMM staff review meeting on March 26, 2026, Project Manager approval on April 6, 2026, CEO approval on April 20, 2026, and Chief Operating Officer approval on April 27, 2026. The Regional Transportation Planning Committee review is scheduled for May 4, 2026, prior to final Board of Directors approval and contract execution.

View the file

Other files

Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

December 8, 2025 To:

Peter Sotherland, Section Manager II, Planning & Analysis

From:

Rhea Aninzo, Contract Administrator, CAMM Subject:

Procurement Schedule for Release, Selection and Award

RFP 250113 "Move OC Active Transportation Plan"

Please review the time schedule for the subject RFP. If there is an issue with any of the dates, please advise as soon as possible.

January 6, 2026
Issue RFP

January 6 & 12, 2026

Advertise

January 14, 2026
Pre-Proposal Conference (in-person/virtual)

10:00 a.m. – Room 09

January 16, 2026
Written Questions due from proposers
January 21, 2026
OCTA’s response to proposers

February 4, 2026

Offers submitted by 2:00 p.m./ Pre-Evaluation Meeting 4:00 p.m.

February 18, 2026

Evaluation Committee Reviews Proposals

10:00 a.m. – 12:00 p.m.

February 26, 2026

Interviews

9:00 a.m. – 4:00 p.m.

February 27, 2026
Staff Report to CAMM from Project Manager

March 26, 2026

CAMM staff report review meeting (Thursday Meeting)

April 6, 2026
Staff Report with Procurement Approach to Project Manager
April 20, 2026
Staff Report to CEO
April 27, 2026
Staff Report to COB
May 4, 2026
Regional Transportation Planning Committee
May 11, 2026
BOD Approves Selection
May 29, 2026
Contract Executed

Project Manager Concurrence:

Peter Sotherland, Section Manager II, Planning & Analysis

Date

Revised: 3/20/2019