This is a procurement schedule document from the Orange County Transportation Authority (OCTA) for Invitation for Bid (IFB) 250095 regarding Compressed Natural Gas Fuel Tank Replacement. The project involves providing and delivering CNG fuel tanks for forty-eight (48) 2007-2008 New Flyer LFR buses. The procurement timeline establishes key milestones including Board approval to issue the IFB on March 23, 2026, with advertisement occurring on March 23 and March 30, 2026. Written questions from proposers are due by 5:00 p.m. on March 26, 2026, with OCTA's responses provided by April 2, 2026. Bids are due on April 20, 2026 at 11:00 a.m., followed by a responsiveness check and CPA finalization between April 20-24, 2026 and April 27-May 1, 2026. The Staff Report is scheduled for submission to the CAMM on May 7, 2026, with a CAMM Board of Directors presentation on May 11, 2026. The award of the Blanket Purchase Order is expected on June 22, 2026, following a presentation to the PM Transit Committee on June 11, 2026.

The contract budget for this effort is $2,721,744.00 for a two-year term. The document is a procurement schedule memo dated January 21, 2026, from Ellis Hoskin, Senior Contract Administrator in CAMM, to Sunil Chettiar, Senior Section Manager of Transit Technical Services, requesting review of the timeline and requesting immediate notification of any issues with the proposed dates or schedules.

View the file

Other files

File Type Posted
Compressed_Natural_Gas_Fuel_Tank_Replacement.pdf PDF
C250095_IFB_Exhibit_A_SOW.pdf PDF
C250095_IFB_Exhibit_A_SOW_GMEDITS.pdf PDF
C250095_Staff_Report_3-23-2026.pdf PDF
C250095_PP-APPROVED.pdf PDF
C250095_PP.docx DOCX document
C250095_IFB_Exhibit_C_Insurance.docx DOCX document
C250095_Public_Notice_Proof.pdf PDF
C250095_ICE.pdf PDF
C250095_R000451.pdf PDF
C250095_IFB_Exhibit_B_Price_Summary_Sheet.docx DOCX document
C250095_IFB_Exhibit_D_Safety_Specifications.doc DOC document
C250095_Insurance_and_Indemnification_Memo_and_RM_Review.pdf PDF
C250095_SOWV.pdf PDF
DBE_Program_Requirements.docx DOCX document
Davis-Bacon_Labor_Provisions.pdf PDF
Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

January 21, 2026 To:

Sunil Chettiar, Senior Section Manager, Transit Technical Services From:

Ellis Hoskin, Senior Contract Administrator, CAMM Subject:

Procurement Schedule for Release, Selection and Award

IFB - 250095 “Compressed Natural Gas Fuel Tank Replacement”

Please review the time schedule for the subject IFB. If you have a problem with any of the dates or timelines let me know as soon as possible.

March 23, 2026
Board Approval to Issue IFB

March 23, 2026 and March 30, 2026 Advertise

March 26, 2026
Written Questions Due from Proposers by 5:00 pm
April 2, 2026
OCTA’s response to Proposers
April 20, 2026
Bids Due – 11:00 a.m.

April 20, 2026 April 20 - 24, 2026

April 27 – May 1, 2026

May 7, 2026 May 11, 2026

June 11, 2026

Staff Report due to CAMM Responsiveness Check, CPA

Finalize Staff Report CAMM BOD Presentation Staff Report to PM

Transit Committee

June 22, 2026

BOD

June 22, 2026

Blanket Purchase Order Award Project Manager Concurrence:

Sunil Chettiar, Senior Section Manager, Transit Technical Services Date Revised: 3/20/2019