This document is Appendix A: Technical Specifications for the Mitchell-Jackson DxP Stewardship Project on the Kootenai National Forest, Libby Ranger District. It establishes comprehensive work item requirements across two subdivisions (Area 56 and Powerhouse) spanning approximately 2,153 acres of commercial timber harvesting and related stewardship activities.
The contract encompasses ten primary work items with multiple subitems: Item #1 involves commercial timber harvesting of 2,153 acres; Items #2-3 address road construction and reconstruction with specifications referenced in separate attachments; Item #4 covers road maintenance associated with harvesting; Item #5 includes timber stand improvement through pre-commercial thinning (PCT) at varying densities (110-295 acres per density level), Western White Pine pruning (61 acres), and Western Larch girdling (274 acres); Item #6 specifies reforestation through tree planting at 15x15, 17x17, and 20x20-foot spacings (848 total acres) plus animal damage control installations; Item #7 addresses site preparation including hand slashing, mechanical scarification, and fireline/fuel break construction (17.94 total miles); Item #8 covers fuels treatments including optional air curtain burning, commercial and non-commercial slashing and piling, mastication, and hand piling; Item #9 mandates noxious weed treatment on specified road segments using approved herbicides with 85% mortality as the acceptable quality level; and Item #10 optionally includes removal of 2,993 CCF/6,002 tons of non-sawtimber material. All acreage measurements were determined using GPS with unit boundaries marked by colored flagging. Payment methodologies vary by work item, with visual inspection and formal plot-based sampling used to verify compliance, and payment tied to achieving minimum acceptable quality levels (90-100% depending on work type). The contractor must submit a Quality Control Plan demonstrating compliance monitoring procedures, and the Forest Service will conduct periodic quality assurance inspections with authority to require rework at no cost if standards are not met.
View the file
Other files
Show all 34
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MITCHELL-JACKSON DxP Stewardship IRSC Kootenai National Forest Page 1 of 28 Libby Ranger District
Attachment 2 Appendix A Technical Specifications
APPENDIX A
TECHNICAL SPECIFICATIONS FOR SERVICE WORK ITEMS
SECTION I – GENERAL DESCRIPTION of WORK:
The purpose of the Mitchell Jackson DxP Stewardship Project IRSC is to modify the forest fuel conditions that influence fire intensity across the landscape, and reduce the potential for wildland fire to spread into Operable Unit 3 (OU3) and the corresponding exposure and migration risks in of Libby Amphibole Asbestos (LA) released from contaminated source media (e.g., soil, duff, and post-fire ash).
All work described herein is split into two separate subdivisions. Subdivision #1 will be henceforth referred to as Area 56. Subdivision #2 will be henceforth referred to as Powerhouse.
The contractor shall provide all management, supervision, labor, personnel, transportation, materials, equipment, and supplies, unless otherwise stated under Government Furnished Equipment and / or supplies. Contractor will also maintain written Quality Control documentation that will be made available to the COR at the completion of the work. All work shall be performed in accordance with the description of work for each individual work item included. All state, federal and local laws and regulations must be followed.
SECTION II – WORK ITEMS
Item #1: Commercial Timber Harvesting of 2,153 acres across both subdivsions.
Cut and remove from the Contract Area timber which meets the minimum tree specifications identified in Appendix B. Appendix B contains the estimated commercial product quantities, contractor requirements (Division A), general contract clauses (Division B), and contract provisions (Division C) specific to the harvesting of timber products within each of the two subdivision areas.
Item #2 and 3: Road Construction and Reconstruction
Powerhouse Subdivision: Refer to attachments 5a and 5b for Specifications and performance requirements.
Area 56 Subdivision: Refer to attachments 5c and 5d for Specifications and performance requirements.
Item #4: Road Maintenance associated with the Commercial Timber Harvesting Described in Item #1.
Refer to attachment 4-Appendix C for specifications. Road Maintenance will be performed commensurate with use and upon determination of the Forest Service.
Item #5: Timber Stand Improvement
ITEM # DESCRIPTION of PRE-COMMERCIAL THINNING (PCT) DENSITIES
5a
PCT - Low Density Thinning: - Hand (manual) work within designated units. Cutting of Small Trees 1.5 Feet in height or greater, and 0.00 to 6.90 inches in diameter at breast height, Cutting 0 – 700 Trees Per Acre.
Area 56 Subdivision PCT Units: N/A
Powerhouse Subdivision PCT Units: P-59, P-63, P-70, P-191, (110 Acres)
5b
PCT - Moderate Density Thinning: - Hand (manual) work within designated units.
Cutting of Small Diameter Trees – 1.5 Feet in height or greater, and 0.00 to 6.90 inches in diameter at breast height, Cutting 701 – 1,500 Trees Per Acre.
Area 56 Subdivision PCT Units: P-23, P-26 (137 Acres)
Page 2 of 28 Libby Ranger District
Powerhouse Subdivision PCT Units: P-47, P-51, P-52, P-54, P-60, P-64, P-65, P-66, P-67, P-68, P-69, P-83, (210 Acres)
5c
PCT - High Density Thinning: - Hand (manual) work within designated units. Cutting of Small Diameter Trees – 1.5 Feet in height or greater, and 0.00 to 6.90 inches in diameter at breast height, Cutting 1,501 or more Trees Per Acre.
Area 56 Subdivision PCT Units: P-20, P-21, P-22, P-24, P-25 (92 Acres)
Powerhouse Subdivision PCT Units: P-44, P-46, P-48, P-49, P-50, P-53, P-55, P-56, P-57, P-58, P-62, P-71, P-72 (295 Acres)
Silvicultural prescriptions for each individual PCT unit will be provided by the FS upon request of the contractor.
1. General leave tree descriptions will include good crown form, live crown ratio > 40%, species preference, good leader growth, color of foliage, straight bole, no significant defect or damage, and insect/disease free. Tree spacing and specifics will be covered in the individual harvest prescriptions.
2. Trees designated for removal as defined in the prescription shall be cut below the lowest live limb, except when prevented by natural obstacles. All live limbs below the point where cut, shall be removed.
3. Stumps shall be cut flat and not exceed 6 inches in height as measured from ground surface on the uphill side and shall be cut flat or with a minimal angle to avoid creating a sharp stump. Trees shall be completely severed from the stump.
4. Designated cut trees shall be felled away from unit boundaries, roads, telephone lines, established trails, stock driveways, fence lines, established land survey monuments, and streams. Any trees falling on such areas shall be removed. Any tree that is felled onto private land, roadside ditches, or within culvert inlets shall be pulled back a minimum of 10 feet into the PCT unit.
5. All PCT slash shall be placed on or near the ground surface, not to exceed an average of 2 feet in depth and shall be cut into lengths no greater than 6 feet long, so that it is not leaning against or suspended by an uncut tree, stump, log, or any obstacle. Snags may not be cut unless the contractor elects to fall them for safety reasons and receives concurrence from the FS prior to felling.
a. If felled, snags should be felled prior to selecting leave trees within a distance equal to the height of the snag in the direction of fall.
Item 5d: Western White Pine (WP) Pruning
General Requirements
All work shall be performed in accordance with this description of work and the Silvicultural Prescription which is prepared for each unit. When prescribed, the pruning will occur at the same time as the thinning.
White Pine Pruning, Area 56 and Powerhouse Subdivisions
Unit number Unit Acres
Planted WP Acres Notes
P-47 11 11 50 TPA (550 total) WP planted, mostly in the eastern 1/2 of unit.
Page 3 of 28 Libby Ranger District
P-51 19 19 2.5 TPA (50 total) WP planted, mostly below the road
P-55 11 11 2.5 TPA (50 total) WP planted, mostly below the road
P-56 14 14 72 TPA (1,080 total) WP planted, mostly above the road
P-24 6 6 92 TPA (550 total) WP planted.
Total Acres 61 61
Specifications for Correctly Pruning Western White Pine
Prune all trees 8 feet and greater in height unless a different height is specified. All branches within the lower ½ of the bole will be pruned up to a maximum height of 8 feet, leaving ½ of the crown of the tree or at least four whorls. All limbs pruned shall be cut to within ¼ inch of the limb collar and needles removed at the bole. A diagram is included below. Pruned limbs shall be completely severed from the tree. The contractor may need to remove duff from around base of tree to ensure all live branches are severed according to specifications. The bole of the tree and limbs to be retained shall not be damaged in the pruning operation. The Contractor shall not use chainsaws for pruning unless approved in writing by the Contracting Officer. Bypass pruners are preferred.
Page 4 of 28 Libby Ranger District
Western White Pine Pruning diagram
Page 5 of 28 Libby Ranger District
5e: Western Larch Girdling within PCT Units.
Dwarf mistletoe is a parasitic plant the relies on its host for water and nutrients. The focus in this contract is western larch (larch) dwarf mistletoe. Heavily infected stands typically have many trees with stunted growth, witches’ brooms, dying or dead tops. Dwarf mistletoe impacts larch by increasing mortality, reducing growth rates, lowering timber quality and results in loss of vigor. Infected larch trees should be killed once reproduction is established to reduce the chances of infection to small trees.
• When prescribed, the girdling will occur at the same time as the PCT.
Unit Number Unit Acres Girdle Acres
P-20 16 16
P-21 33 2
P-22 16 16
P-24 6 6
P-25 21 21
P-44 29 29
P-46 22 22
P-52 13 13
P-55 11 3
P-58 35 7
P-60 20 4
P-66 9 9
P-67 6 6
P-71 15 15
P-72 26 26
P-83 15 15
Total Acres 293 274
Girdle Acres represent the estimated acres within each PCT unit listed which contain larch that are appropriate for this treatment.
Page 6 of 28 Libby Ranger District
Girdling.
Girdling deliberately kills the tree and the associated dwarf mistletoe, leaving the tree to become a snag. The Contractor shall select, and girdle trees specified in Silvicultural Summary Prescription. Girdling shall utilize a minimum of two 1” wide cuts, 6” apart, completely through the bark and cambium tissue (but not more than ¾ inch past the cambium), completely encircling tree bole so that trees are deliberately killed. To facilitate public safety, specified larch within two tree lengths of an open road or trail may be felled rather than girdled pending prior FS approval.
Not all overstory larch will need to be girdled. Only larch with a Dwarf Mistletoe Rating (DMR) of 2 or greater will be girdled. Use the Hawksworth Dwarf Mistletoe Rating instruction to determine the DMR.
Instructions: Hawksworth
Dwarf Mistletoe Rating Example:
Step 1
Divide live crown into thirds.
````Rating of 1
Step 2
Rate each third separately. Each third should be given a rating of 0, 1, or 2 as described below.
Rating of 2
0 = No visible infections
1 = Light infection (1/2 or less of the total number of branches in the crown-third are infected).
``Rating of 0
2 = Heavy infection (more than 1/2 of total number of branches in the crown-third are infected).
The dwarf mistletoe rating for the above tree is 3 (top 1 + middle 2 + bottom 0).
Step 3
Add ratings of thirds to obtain rating for total tree.
Page 7 of 28 Libby Ranger District
Item 6: Reforestation – Tree Planting and Seedling Protection within designated commercial units post-harvest.
General Reforestation Requirements – Items 6a, 6b, 6c, and 6d
General Description of Services:
All work shall be performed in accordance with this description of work and the Silvicultural Prescription which is prepared for each unit. Government will supply seedlings, maps, plot sheets, and a Detailed Information Chart for each individual planting unit.
Refer to the Attachment 2b Tree Planting and Animal Damage Control Performance Work Statement and associated Exhibits (Reforestation PWS), for all tree planting and Animal Damage Control (ADC) guidance on technique, quality control requirements, term definitions, tree handling specifications and anything else required to execute a successful tree planting program. A COR and/or Government Technical Monitor will always be present during the planting / ADC treatments. They will be responsible for tree delivery to each unit, tree distribution, species mix if required and Government Quality Assurance monitoring for payment. Each planting unit will have an individual Detailed Information Chart that includes the specifications required such as, but not limited to, spacing, scalp size requirements, shade requirements, species mix, and ADC treatment materials and specifications.
ITEM # DESCRIPTION of PLANTING SPACING
6a
15 x 15-foot plant spacing
Area 56: Seedling planting within commercial units: 3, 3A, 6, 10, 11, 17, 17A, 20B, 20C, 20D, 60, 61, 62, 63, 64, 66, 67, 69, 71, 72, 75, 76, 84, 85, 86, 88, 89, 89A, 109, 112, 113, and 190 (570 Acres).
Powerhouse: Seedling planting within commercial units: 125, 126, 130, 152, 163, 177, and 233 (157 Acres).
6b 17 x 17-foot plant spacing
Powerhouse: Seedling planting within commercial units: 143, 157, and 174 (34 Acres).
6c
20 x 20-foot plant spacing
Area 56: Seedling planting within commercial units: 90 (20 Acres).
Powerhouse: Seedling planting within commercial units: 149, 150, 150A, 151, 158, 162, 173, 175, 175A, 179, 179A, 179B, 182, 186, (258 Acres).
Item 6d: Animal Damage Control (ADC): Install rigid seedling protector tubes on Ponderosa Pine seedlings within specified commercial units.
Area 56- ADC Installation within units: 3, 3A, 6, 10, 11, 17, 17A, 20B, 20C, 20D, 62, 63, 64, 66, 67, 72, 75, 76, 84, 88, 90, 109, 112, 113, and 190.
Powerhouse- ADC Installation within units: 130, 143, 149, 150, 150A, 151, 152, 158, 162, 163, 173, 174, 175, 175A, 179, 179A, 179B, 182, 186.
Item 7: Site Preparation for Reforestation
Page 8 of 28 Libby Ranger District
Item 7a Hand Slashing (cutting) of Ninebark brush to create planting sites within certain commercial timber harvesting units. Area 56: Ninebark Slashing within units 11 and 112.
Slash a 6-foot x 6-foot area every 15 feet throughout each specified unit. Slash all brush within the created 6-foot x 6-foot openings for planting. Cut stems must be completely severed from the stump, removed from the 6-foot area, and are to be left within 24 inches of the ground level. Any cut stems 6 feet or greater in length shall be cut in half. Openings created from slashing will be evenly distributed across the units. Trees are intended to be planted within each of the 6-foot x 6-foot slashed openings. Slashing of brush will occur only one fall prior to the planned spring planting.
Item 7b Mechanical (Excavator) Soil Scarification within commercial units for reforestation.
Area 56: Scarification within units 6, 10, 17A, 20C, 60, 63, 64, 66, 67, 69, 71, 72, 75, 76, 84, 86, 88, 89, 89A, 109, and 113.
General Scarification Specification
An excavator type machine equipped with a digging bucket is to be used. Other machines are subject to approval by Forest Service.
A minimum of 20 percent and a maximum of 30 percent of the workable ground shall be scarified to reduce duff to less than ½ inch or to mineral soil. Scarified patches (at least 1 meter by 1 meter square) shall be evenly distributed over the workable ground in the unit. Scarification shall only be done during periods of dry soil conditions as determined by the Forest Service. In cutting units in which utilization is accepted between July 16th and September 30th, scarification work shall be completed by October 31st of the same year. In cutting units in which utilization is accepted between October 1 of the previous year and July 15th of the current year, scarification work shall be completed by October 31st of the current year.
Items 7c and 7d Fireline/Fuel break Construction: Mechanical (Machine) and Hand Construction
ITEM # DESCRIPTION of CONSTRUCTION METHOD
7c Mechanical Construction: Fireline/fuel break. Low to gentle to moderate slopes, easy terrain with little to no features that would slow production rates. Fuel loading for fuel break is low to small portions of moderate loading.
7d Hand Construction: Fireline/Fuel break on moderate to steeper slopes, with short pitches of 40%.
Terrain is moderate to difficult which may slow production. Fuel loading for fuel break is moderate with small portions of high loading.
A. Fireline and fuel breaks may be constructed with either an excavator with bucket and thumb or by hand crews. Excavators will not be permitted to operate on slopes with a continuous run over 35%, however, it may exceed 35% for short runs.
B. Fireline/ Fuel break Specifications
1. Fireline is composed of a continuous line of bare mineral soil 18 - 24 inches wide.
2. Fuel breaks are constructed on both sides of the constructed fireline which removes all concentrations of vegetation material that will easily ignite, maintain, or increase fire intensity.
Fuel breaks will be a minimum of 20 feet in width with the fireline roughly in the middle of the fuel break (approximately 10 feet on either side of fireline).
Page 9 of 28 Libby Ranger District
C. Miles of fireline/fuel break construction:
1. Machine Construction: approximately 10.28 miles
2. Hand Construction: approximately 7.66 miles
Item 8: Fuels Treatments
Item 8a (OPTIONAL): Air Curtain Burner Operations for Slash Disposal
Purpose: An air curtain burner is a piece of equipment designed to minimize air pollution associated with the burning of wood and vegetative waste – the burner uses a series of air blowers to generate a “curtain” of air that drives volatile gases back into the burner to be consumed as fuel in the fire.
Scope: Either trench or box style burners, or other approved methods may be used. Air curtain burning will be conducted at agreed upon log landing sites to dispose of slash at the landing. Only landing piles will be burned while using an air curtain. Landing piles will be fed into the air curtain burner with an excavator with brush rake or bucket with thump. Air curtain burning will only be allowed when fire danger is LOW and approved by the Forest Service. The ground must be wet, or snow covered to prevent any fire spread. Once the location of the air curtain burning operation is completed, the contractor must cover the trench, and/or spread the ashes to recontour the site to its original condition.
Items 8b and 8c: Slashing (cutting) Within designated COMMERCIAL Units
Area 56 Ground-Based Skidding Units: 3A, 6, 10, 17A, 20, 20C, 60, 66, 67, 68, 71, 72, 73, 75, 76, 84, 87, 89, 91, 94A, 96A, and 113.
Area 56 Cable-Based Yarding Units: 3, 11, 17, 20B, 20D, 61, 62, 63, 64, 69, 85, 86, 88, 89A, 90, 109, 112, and 190.
Powerhouse Ground-Based Skidding Units: 126, 127, 127A, 129, 134, 145, 150, 150A, 151, 157, 158, 169, 173, 186, 189, and 226.
Powerhouse Cable-Based Yarding Units: 125, 130, 134A, 138 ,143, 149, 152, 162, 163, 166, 168, 174, 175, 175A, 177, 179, 179A, 179B, 182, 185, 189A, 193, and 233.
ITEM DESCRIPTION of COMPLEXITY
8b Within Commercial Units Utilizing Ground-Based Skidding – Cutting of Non-Saw material.
8c Within Commercial Units Utilizing Cable-Based Yarding – Cutting of Non-Saw material.
Slashing within commercial harvests units may be performed mechanically with feller-buncher, masticator, or similar machinery, or by hand crews with chainsaws.
1. Cutting Specifications
A. Silvicultural prescriptions for slashing will be provided by the FS upon request of the contractor.
B. Contractor shall fell all live and dead conifers not meeting utilization standards and over 2 feet in height, unless otherwise designated to be left standing.
i. All material shall be felled into the units and away from identified fireline, improvements, and property boundaries.
ii. Remaining stumps shall be less than 6 inches in height as measured from the ground surface on the uphill side and shall be cut flat or with a minimal angle to avoid creating a sharp stump.
Page 10 of 28 Libby Ranger District
iii. Completely sever cut material from the stump, leaving no live limbs on the stump. Keep all systems roads and drainage structures, including roadside ditches, free of slashed material from within the units.
iv. Buck all resulting slash greater than 3 inches to a maximum of 10-foot lengths. The maximum slash depth throughout the unit shall be less than 18 inches above the surface of the ground.
C. Commercial Units Requiring Slashing
Items 8d: Machine Piling of Slash within Designated COMMERCIAL Units.
Area 56 Commercial Units: 6, 10, 17A, 20C, 60, 63, 64, 66, 67, 69, 70, 71, 72, 73, 75, 76, 84, 86, 87, 88, 89, 89A, 91, 92A, 92C, 94B, 94C, 97, 101, 109, and 113.
Powerhouse Commercial Units: 126, 127, 127A, 129, 134, 157, 158, 173, 186, 189, and 226.
1. Machine Piling Specifications
A. Silvicultural prescriptions for units requiring machine piling of created slash will be provided by the FS upon request of the contractor.
B. Contractor shall pile timber harvesting slash within the commercial units or portions thereof as shown on the Contract Area, Hazard Reduction, and Site Preparation Map.
i. Equipment used for piling shall be equipped with thumb, grapple or other attachment and approved by the Forest Service.
ii. Piles shall be reasonably compact and free of soil and stumps to facilitate clean burning.
iii. Slash to be piled shall include material greater than 3-inch diameter at the large end, however, smaller material may be piled incidental to and in conjunction with this material.
iv. The minimum piece length will be 3 feet.
v. Piles shall range from 6 feet to 15 feet in height and 4 feet to 15 feet in diameter.
vi. Piles shall be placed no closer than 20 feet from the outside perimeter of the unit, system roads, wet areas, or other areas designated on the ground by the Forest Service.
vii. No pile shall be closer than 15 feet from any standing residual trees.
viii. All pieces which extend more than 8 feet in any direction from the pile profile will be cut off and returned to the pile.
ix. Stack boles of trees parallel so piles are compact.
C. Conduct piling operations when soils conditions are dry, frozen, or as approved by the Forest Service.
D. In the event timber harvesting activities result in significant accumulations of Contractor generated slash due to breakage or resulting from slashing activities, machine piling shall be performed to mitigate the accumulations of slash that can include diameters less than 3-inch on the large end.
i. A significant accumulation of slash is defined as Contractor created slash concentrations over one-tenth acre in size that could be accumulated into a pile with a minimum of 6 feet in height and 4 feet in diameter.
E. Units Requiring Machine Piling of fuels by subdivision
Page 11 of 28 Libby Ranger District
Item 8e: Mechanical Mastication of Roadside Material Roadside Mastication Units (Powerhouse Subdivision): 175x Road, 192x Road, and 195x Road
Roadside mastication will consist of a boom-mounted masticator masticating to the following specs within units located along road #4872 within the Powerhouse Subdivision area. Mastication will be accomplished to 25 feet from the edge of the road on both sides.
Using a boom mounted masticator the contractor shall masticate the following material:
• All shrubs and brush greater than 1-foot in height.
• All trees with a diameter at breast height (DBH) of 8 inches or less and greater than 1-foot in height that can be masticated without damaging leave trees.
• All limbs that extend over the road prism and are 14 vertical feet or less above the road.
• Maximum stump height of 8 inches as measured on the uphill side of the stump and no lower live limbs left on the stump.
• The result of the roadside mastication will be small debris (limbs, sticks, needles, “chips”) less than or equal to 3-inch diameter and 1 to 4 feet in length.
• Contractor shall remove any debris, slash material or chip residue, that is cast into or falls onto roadways.
• Contractor shall remove any debris concentrations that will interfere with the function of ditches and/or culverts created from masticated materials.
• All existing facilities such as signs, cattleguards, gates, barricades, and drainage structures damaged by the Contractor shall be replaced or repaired by the contractor at no additional cost to the Government.
• The contractor shall include all applicable work zone signage while working along the roadway.
Item 8f: Mechanical Mastication in NON-COMMERCIAL Units.
Powerhouse: Units S10 and S12
1. Mastication Specifications
A. Acceptable mastication equipment will consist of a boom-mounted masticator.
B. Silvicultural prescriptions for mastication will be provided by the FS upon request of the contractor.
i. Operate machinery in a way so as not to damage any residual trees (a maximum of 10% damage to the residual stand) or cause undo damage to surrounding resources such as roadways, trails, ditches, etc.
ii. Machines used shall be designated and operated in such a way to minimize soil disturbance such as rutting and compaction.
iii. After mastication, stump heights shall be no more than 6 inches in height as measured on the uphill side or 4 inches above natural obstacles.
iv. No slash of vegetative debris shall be more than 12 inches deep as measured from the natural ground level. A maximum of 15% of the individual pieces of slash or vegetative debris will be allowed to exceed 6 feet in length. No masticated or cut material shall lean against or be suspended by a residual tree.
v. Masticated material will be within the following specifications unless otherwise designated:
75% of chips from masticating must be < 3 feet in length, 25% of chips from masticating may be a maximum of 8 feet in length, however, a slash depth must be no more than 12 inches in depth.
Page 12 of 28 Libby Ranger District
vi. In addition to standing vegetation, mastication of existing downed wood may be required in some individual unit prescriptions.
Item 8g: Hand Slashing (cutting of small diameter trees; ladder fuels reduction.) In NON-COMMERCIAL units.
Units: S4, S6, S7, S8, S11, S16, S24, S24A, S25, S26, S31, S32, S37, S20z North, S20z East, S20z West, S71z, S75z, S88z, S90z, S94z, S96z, S97z, S98z, S100z, S101z, S113z, S122z, S180z, S183z, S125x, S126x West, S126x North, S127x, S127x South, S129, S133x, S135x East, S135x West, S138x, S139x, S141x, S143x, S144x, S145x, S149x, S150x, S151x, S157x, S162x, S164x, S166x, S175x East, S175x North, S179x North, S185x, S189x, S124x, and S126x.
1. Hand slashing Specifications
A. Silvicultural prescriptions for hand slashing will be provided by the FS upon request of the contractor. Prescriptions may vary by individual units. The maximum diameter of tree to slash is
7.9” DBH.
Item 8h: Hand piling of slash within NON-COMMERCIAL units.
Units: S4, S6, S7, S8, S11, S16, S24A, S25, S26, S31, S32, S37, S20z North, S20z East, S20z West, S71z, S75z, S88z, S90z, S94z, S96z, S97z, S98z, S100z, S101z, S113z, S122z, S180z, S183z, S125x, S126x West, S126x North, S127x, S127x South, S129, S133x, S135x East, S135x West, S138x, S139x, S141x, S143x, S149x, S157x, S162x, S164x, S166x, S175x East, S175x North, S179x North, S185x, S189x, S124x, and S126x.
1. Hand Piling Specifications
A. Silvicultural prescriptions for hand piling will be provided by the FS upon request of the contractor.
B. Hand pile all slash created from the hand slashing within units identified as needing hand piles.
Minimum acceptable hand pile size will be 3 feet in height and range from 3 to 8 feet in diameter.
i. Piles shall be compact with smaller material such as needles and branched in the bottom and center, and larger material such as boles on top to compress lighter fuels.
ii. Boles of trees will be oriented parallel to the slope (pointing up and down hill) to prevent rollout during burning.
iii. Piles constructed on slopes exceeding 30% may be secured by leaving one or two activity generated stumps per piles 4-6 feet in height with a minimum stump diameter of 4 inches or greater, slash shall be piled perpendicular to the stumps on the uphill side.
iv. Materials shall be piled in a parallel configuration, similar to pencils in a box. Once a pile meets the minimum diameter and height; slash maybe added vertically on the edge of ta pile to prevent the pile from toppling.
v. Pile covering is required for all hand piles built by the contractor. Piles shall be covered with a burnable 80# kraft, water-repellent, non-toxic (when burned) paper. Plastic or tar paper will not be approved for pile covering. Paper shall be firmly places within the pile such that ¾ of the diameter and ¾ of the height of the pile is covered and held firmly in place be heavy slash on top of it.
Item 9: Noxious Weed Treatment
The roads shown in the Table 1 below and being used by the Contractor shall be treated with herbicide to remove seed-bearing noxious weeds.
Unless otherwise agreed, Contractor shall:
A. Include a schedule for herbicide treatment of noxious weeds as part of the Annual Operating Schedule.
Page 13 of 28 Libby Ranger District
B. Treat roads or road segments required to have noxious weeds treated between June 1 and September
C. Follow the “TECHNICAL SPRAYING SPECIFICATIONS” below.
Treatment shall consist of spot applications that target those noxious weeds identified on the State of Montana’sNoxious weed list (Refer to Exhibit B) that occur on the listed roads. Reasonable care shall be exercised to limit application so that spraying does not contact native forbs, grasses, herbs, and trees.
Table 1 – Road Segments to Recieve Noxious Weed Treatment
Road Number Road Termini MP to MP Total Miles Post-
Reconstruction Post-Haul
755 0.00 to 4.20 4.20 YES YES
1018 0.00 to 3.02 3.02 YES YES
4736 0.00 to 1.30 1.30 YES YES
4751 0.00 to 1.22 1.22 YES YES
4752 0.00 to 1.08 1.08 YES YES
4752A 0.00 to 0.83 0.83 YES YES
4753 0.00 to 6.96 6.96 YES YES
4753H 0.00 to 2.00 2.00 YES YES
4755 0.44 to 1.48 1.04 YES YES
4756 0.00 to 5.21 5.21 YES YES
4756G 0.00 to 0.19 0.19 YES YES
5033 0.00 to 0.28 0.28 YES YES
5082 0.00 to 0.31 0.31 YES YES
5083 0.00 to 0.41 0.41 YES YES
4753N 0.00 to 1.45 1.45 YES YES
5348 0.00 to 1.79 1.79 YES YES
14413 0.00 to 1.57 1.57 YES YES
14415 0.00 to 0.79 0.79 YES YES
14419 0.00 to 0.16 0.16 YES YES
14421 0.00 to 0.17 0.17 YES YES
Page 14 of 28 Libby Ranger District
Road Number Road Termini MP to MP Total Miles Post-
Reconstruction Post-Haul
99443B 0.00 to 0.58 0.58 YES YES
5348EXT 1.79 to 2.01 0.22 YES YES
4755A 0.00 to 1.22 1.22 YES YES
14415EXT 0.79 to 1.71 0.92 YES YES
1018EXT 3.02 to 3.75 0.73 YES YES
1018A 0.00 to 1.72 1.72 YES YES
99443AEXT 0.83 to 1.15 0.32 YES YES
4753HEXT 2.00 to 2.97 0.97 YES YES
4755RA 0.00 to 0.51 0.51 YES YES
4857 0.00 to 1.52 1.52 YES YES
4857D 0.00 to 0.93 0.93 YES YES
4872 0.00 to 7.68 7.68 YES YES
4872B 0.48 to 0.82 0.34 YES YES
4873 0.00 to 3.51 3.51 YES YES
4878 0.00 to 2.50 2.50 YES YES
4879 0.00 to 2.08 2.08 YES YES
8833 0.81 to 1.12 0.31 YES YES
99443A 0.00 to 0.83 0.83 YES YES
99444 0.00 to 0.65 0.65 YES YES
228 0.00 to 4.11 4.11 YES YES
4872B 0.00 to 0.48 0.48 YES YES
Technical Spraying Specifications for the Kootenai National Forest
1. The Contractor shall give the Forest Service a 48 hour notification prior to spraying.
2. All treatments will occur when target plants are most identifiable. This is dependent on species and localized conditions including time of year, location, elevation, and aspects.
Page 15 of 28 Libby Ranger District
3. Spraying will be done by a State of Montanalicensed commercial applicator and personnel under the direct supervision of the licensed applicator.
4. A BLUE water-based dye shall be used to further identify target species that have been sprayed and shall be added at a rate in compliance with the EPA lable.
5. The following herbicides and application rates are approved for use. Other herbicides and appliction rates shall be approved by the Forest Service prior to use. All use of herbicides, dyes and surfactants shall follow EPA label requirements.
Common Name Trade name(s) Application Rate (lbs active ingredient / acre or oz / ac)
Dye (application rate)
Aminopyralid Milestone 3-7 oz/acre 6-32oz/100gal of water
2,4-D Broadrange 55 24 oz/acre 6-32oz/100gal of water
Metsulfuron-methyl Escort XP 1 oz/acre 6-32oz/100gal of water
Indaziflam Rejuvra 5 oz/acre 6-32oz/100gal of water
Organosylicone/modified vegetable oil concentrate
Syl-Tac-EA 4 oz/acre 6-32oz/100gal of water
Picloram Tordon 16 oz/acre 6-32oz/100gal of water
6. For treatments from July 1 to September 30,surfactants that cause herbicide to adhere to the plant (stickers) shall be applied with herbicides.
7. Weed infestations within 15feet of open water and/or wet areas can only be treated with herbicides labeled for the treatment of aquatics, unless otherwise approved in writing by the Forest Service. No spray shall come in contact with open water at any time.
8. No spraying shall occur when rain is expected within six (6) hours of completion of the treatment.
9. Nozzles shall be made of stainless steel or ceramic material.
10. All equipment shall be in good mechanical condition and will be inspected prior to work. The spray pattern, application rates, and calibration shall also be checked before beginning the job and thereafter as deemed necessary by the Forest Service.
11. A tight-fitting lid on all spray tanks is mandatory.
12. Mixing, loading, and equipment cleaning shall be done more than 200 feet from private land or open water.
Mixing and cleaning water shall come from public or cooperator supplies, and shall be transported to the site in labeled containers separate from water used for other purposes. On-site locations for water drafting must be approved in advance by the Forest Service. Equipment used to draft water from creeks or rivers must be equipped with anti back siphoning devices.
13. Weather conditions shall be monitored before and during all spraying projects. Spraying is NOT allowed when any of the following conditions exist:
Hand-held equipment: temperature greater than 95 degrees F.; humidity less than 20 percent, or wind greater than 5 MPH.
Page 16 of 28 Libby Ranger District
Truck-mounted equipment: temperature greater than 95 degrees F.; humidity less than 20 percent; or wind greater than 5 MPH.
14. Herbicides shall be transported daily to the project site with the following conditions: Transport only the quantity needed for that day's work; transport concentrate containers only in a manner that will prevent spills;
and transport spray in a compartment that is isolated from food, clothing, and safety equipment.
15. Mixing shall only occur on site.
16. The Contractor shall inspect equipment daily for leaks.
17. The Contractor shall remove all herbicide containers from national forest land and dispose of them in accordance with all local, state, and federal requirements
18. Applicators will complete a daily pesticide application reports as required by the Montana Department of Agriculture. Applicators will use the daily pesticide application report form provided by the Forest Service.
Daily application reports shall be submitted to the Forest Service within 10 days of application.
19. Applicators will collect and include GIS data for all applications along with the daily pesticide reports.
Attributes to be collected are specified in Exhibit A.
20. Spraying shall occur as specified in Table 1 above after reconstruction work has been completed on each idividual road segment, and again after the road maintenance following all timber product removal.
21. The wilting, curling, discoloration or killing of target plants shall be used as a measure of application effectiveness and performance acceptability.
Item 9a: Mandatory – Noxious Weed Treatment: Right-of-Way (ROW) Applications
This work will occur on right-of-way (ROW), road and roadside, within the project area for haul routes managed by the Forest Service. ROW spraying should combine roadbeds and bank, fill slope, cut slope, pullouts, and ditches.
No work shall occur in areas within 10 days of herbicide application to allow maximum efficacy. Such applications may be accomplished using truck or UTV mounted application equipment.
Spray coverage should include 30 feet from center of roadbed to encompass the road surface and include up to 15 feet beyond the road edge for all established roads.
Application equipment will be inspected for sound operating condition.
Inspections should include:
- Physical and visual examination of spray apparatus and related equipment.
- Ensure spray pattern and coverage is adequate for the desired results.
- Confirm correct mixing/cleaning/maintenance procedures are in place.
Item 9b: Mandatory - Noxious Weed Treatment: Front Country Applications with Backpack Equipment
This work will occur within areas such as landings and decommissioned temporary roads not to exceed 1/2 mile in length may need to be accessed by foot travel.
Item 9c: Optional - Noxious Weed Treatment: Back Country Applications with Backpack Equipment
This work may occur within an Inventoried Roadless Area (IRA) on the project. Much of the IRA has slopes greater than 40%. An indeterminate number of acres will be treated.
Workers will cover all areas within boundaries that are established during operations covered in item 8d and treat all noxious and invasive weeds listed on the Montana Noxious Weeds list (see Attachment 4 for complete list).
Item 10: Optional – Removal (Hauling) of Non-Sawtimber material created during timber harvesting activities.
Page 17 of 28 Libby Ranger District
Removal of non-sawtimber material from the project area as agreed upon by the Forest Service.
There is an estimated 2,993 CCF/6,002 tons of combined softwood non-sawtimber material within the project area. Approximately one third of this volume is primary product with the balance being top wood and material defected out of sawlogs.
SECTION III – INSPECTION AND ACCEPTANCE
For All Work Items:
At any point during the project, the Contractor and/or Project Manager may request (documented through email, text, or hand-written request) an in-the-field consultation with the Forest Service to inspect work progress, review contract specifications, or clarify issues. The Forest Service shall respond to Contractor’s request within 5 working days, excluding weekends and federal holidays. The Contractor shall perform Quality Control in accordance with the work item specific Contractor Quality Control plan(s).
QUALITY CONTROL
The Contractor, not the Government, is responsible for management and quality control actions to meet the terms of the contract. The role of the Government is quality assurance to ensure contract standards are met.
The Contractor shall provide a Quality Control Plan (QCP) with the technical proposal.
The general QCP must demonstrate how the Contractor will assure quality meets the requirements and specifications of each work item, mandatory and optional items, included in this contract. It shall specify how quality will be monitored to ensure the performance standards are met; the supervision of crew and work; and the personnel that will be performing the quality control. Quality control includes monitoring of quality while work is progressing. The Contractor may utilize a range of methods to determine the Contractor’s compliance with the contract specifications. During the issuance of certain work items, the Contractor may propose or the Government may require the use of a plot-based quality control to determine the actual quality percentage. In addition to the description of how quality will be monitored to assure that performance standards are met, the plan shall also include: (1) corrective or preventive actions that will be taken to meet quality standards; (2) control procedures for security of Government-provided items such as keys, and lock combinations; and (3) location of the inspection documents and other quality control records.
Records of quality inspections shall be kept and made available to the Government throughout the performance period and for the period after contract completion until final settlement of any claims under this contract.
GOVERNMENT QUALITY ASSURANCE SURVEILLANCE PLAN - QASP
Quality assurance will be performed by the Government during the contract at regular intervals. Methods may include random sampling, 100% inspection of the work, and/or visual survey and review of contractor quality control documents. Unacceptable work shall require rework at no cost to the Government. All work shall meet all the standards listed in above sections.
Quality assurance will ensure proposed activity in the Project Implementation Plan adhere to the purpose and need, project objectives and site-specific silviculture, fuels reduction, harvest plan and resource protection requirements as stated within the Non-Time-Critical Removal Action at the Mitchell Jackson Project Area, and other attached project design criteria.
Government Inspection Procedures - The COR, or a designated inspector (GTM) for each work item, will make periodic inspections while work is in progress as needed to ensure work is proceeding satisfactorily. The Contractor shall notify the COR when units are started, when problems are encountered, and when contract work needs government oversight.
1. Each unit will be inspected as a separate unit. Units will not be averaged with other units for acceptance or payment.
Page 18 of 28 Libby Ranger District
2. When units are completed and ready for government inspection, Contractor’s designated Project manager shall request unit inspection in writing, prior to moving out of the general area.
3. The COR, or designated inspector, will determine compliance with contract specifications through informal visual inspections. In the event visual inspection indicates work to be in non-compliance with specifications, prompt corrective action and/or rework shall be required.
UNSATISFACTORY PERFORMANCE
1. If the work quality falls below AQL shown in table 1 below, the COR will immediately notify the Contractor, in writing, and order him to improve the quality of subsequent work. If the quality of subsequent work is not raised to the AQL standard within 24 business hours after receipt of such written notice, the Contractor’s right to proceed may be terminated and the contract considered in default.
2. When the work quality falls below AQL, the Government may elect to do one of the following:
(a) Order rework to be performed and withhold payment until the results of a post-rework Government inspection shows quality to be at AQL or more. No rework shall be performed unless ordered or authorized by the COR.
(b) Order that no rework be performed and payment will either be made at a reduced rate, or not at all, as determined from the Inspection Report.
3. Repeated failure to produce work quality at or above the AQL standard will be considered reason for contract termination and default action.
REINSPECTION UPON CONTRACTOR REQUEST
1. If Government inspection results are unacceptable to the Contractor, a reinspection may be requested, in writing, within 5 business days after receipt of notice of said inspection results. The same inspection procedure will be used; however, the inspection pattern will be shifted so that new inspection plots will not overlap previously inspected plots.
2. If reinspection results – rounded up to the nearest whole percent – indicate a variance of more than 5 percent from the first inspection, the results of the second inspection will be used to calculate work quality and payment, and the Government will bear the cost of reinspection.
3. If reinspection results – rounded up to the nearest whole percent – are within 5 percent of the first inspection, plots from the initial inspection and the reinspection will be combined and used to calculate work quality and payment, and the Contractor shall bear the cost of reinspection.
GOVERNMENT INSPECTION PROCEDURES
Item 1. Cut and Remove Included Timber Products (Timber Harvest): Refer to Appendix B, Divisions A, B, and C for specific inspection and acceptance language.
Items 2 and 3. Road Construction and Reconstruction: Refer to Appendix D Road Construction and Reconstruction Package for specific inspection and acceptance language.
Item 4a – 4g. Road Maintenance associated with Commercial Timber Harvesting: Visual inspections will be accomplished by the Government comparing the individual maintenance specifications to the product achieved on the ground by the contractor.
Items 5- Timber Stand Improvement, 7 Site Preparation and 8 Fuels Treatment
For all associated work, the COR or Government Technical Monitor will conduct periodic visual inspections of each work item to assure full compliance.
Page 19 of 28 Libby Ranger District
Work Activity Acceptable Quality Level (AQL)
Government Method of Assessment Incentive/Deduction
Fireline / Fuelbreak Construction
Slashing in Commercial Units
Slashing in Non- Commercial Units
Machine Piling in Commercial Units
Piling in Non- Commercial Units
Mastication – Roadsides
Mastication – Non- Commercial Units
Hand Piling – Non- Commercial Units
Air Curtain Burning
100% of the unit of measure is treated
90% Meets work activity specifications & requirements.
90% Meets Prescription/Work Description requirements
COR or Government Technical Monitor conduct periodic monitoring
Visual Inspections
Formal Plots
• Rework is required if Contractor fails to meet standard.
• If quality does not meet standard, pay deduction as stated in calculating Payment
Section and/or additional costs to the Government will be assessed.
• If the Contractor fails or refuses to repair any damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor.
• The Contractor’s quality will be reflected in the performance assessment either positive or negative.
Items 6a – 6d. Reforestation (Planting and ADC)
Quality Control and Quality Assurance is explained in detail in Section 8 of the Reforestation PWS, and the planting inspection method is found in Exhibit 11. The planting inspection plot sheet is found in Exhibit 9 and 10.
The contractor will follow all these guidelines when conducting the quality control inspection. A 1% sample, 5 plot minimum is required for all sub-items.
- For Item 6a (plant spacing of 15 feet), a 1/50th acre (16.7-foot radius) plot will be used for the inspection.
- For Item 6b (plant spacing of 17 feet), a 1/20th acre (26.4-foot radius) plot size will be used for the inspection.
- For Item 6c (planting spacing of 20 feet), a 1/20th acre (26.4-foot radius) plot size will be used for the inspection.
Use the charts in the Exhibit 10 for plantable spots, maximum plantable spots, and number of trees to inspect underground. The same number of plots and plot size that was used in the planting will be used for the installation of the Animal Damage Control (ADC) material. Use Exhibit 15, Inspection Plot Sheet for ADC. The Government and Contractor will be consistent in plot inspection, plot size, and number of plots.
Page 20 of 28 Libby Ranger District
Work Activity Acceptable Quality Level (AQL)
Government Method of Assessment Incentive/Deduction
Tree Handling and Care
Planting Operations
Shade/ADC Installation
100% Meets contract handling and care specifications
90% Meets planting quality standards as evaluated in inspection plots
90% Meets shade/ADC treatment specifications
Continuous visual surveillance of handling, storage, and care procedures
Use of Inspection Sheets and Government‑selected plot densities and locations
Meeting or Exceeding AQL:
• Payment made at the full quoted task order price.
• Good Past Performance ratings.
• Options exercised (if work is needed & have budget).
Failure to meet AQL:
• Rework at contractor’s expense.
• Re-inspection charges are deducted from payment.
• Total payment reduced by AQL deduction % if cannot meet AQL.
Item 9 Noxious Weeds Treatment
Work Activity Acceptable Quality Level
(AQL)
Government Method of Assessment Incentive/Deduction
Noxious Weed Treatment
85% mortality of target species.
100% compliance manufacture label direction
Less than 20% loss of non-target species.
No more than one warning to fix any equipment leaks or clean-up drafting or mixing sites.
100% visual inspection of reporting sheets.
Random Visual Field Inspections
Random plot sampling.
Random compliance checks of contractor inspection plots.
100% inspection of equipment
Meeting or Exceeding
AQL:
• Payment made at the full quoted task order price.
• Good Past Performance ratings.
• Options exercised (if work is needed & have budget).
Page 21 of 28 Libby Ranger District
Work Activity Acceptable Quality Level
(AQL)
Government Method of Assessment Incentive/Deduction
One warning for lack of proper identification of area treated
Random field inspection of drafting and mixing site(s)
Failure to meet AQL:
• Rework at contractor’s expense.
• Re-inspection charges are deducted from payment.
• Total payment reduced by AQL deduction % if cannot meet
AQL.
Data Submittal for Herbicide
Applications
Records submitted within timeframe stated in Description of work.
95% of spray records will have no missing data values. Applicator spray records shall conform to Montana State standards.
Applicator spray records will state equipment calibration for gallon/acres.
GIS data for all treatments to be included with application records
Visual Inspection of application records
100% of GIS data complies with required Geospatial Attribute Standards
The contractor will immediately notify the COR when treatments are complete each year and ready for inspection.
The contractor is required to collect geospatial data for all weed treatments and collect a separate geospatial file for all Class A and B priority species found to exist within infestations of non-priority species. Geospatial data will include attributes listed in Attachment 6 and be compatible with ESRI software. All geospatial data will be provided as polygons. Small and linear treatments may be recorded as a point or line with correct dimensions provided. During yearly treatments, geospatial data and attributes will be submitted to the COR weekly, unless otherwise directed by the COR. All reports must be submitted by October 1st each year.
Acceptance of Work specific to Noxious Weeds Treatment.
Upon Contractor’s written request and assurance that work has been completed, Forest Service shall perform an inspection within 5 days, excluding weekends and Federal holidays, so as not to delay unnecessarily the progress of Contractor’s Operations. Such a request may be for acceptance of:
(a) Any reasonable portion of Specified Road listed in the Description of Work;
(b) Specific requirements on a subdivision of Contract Area (such as logging, stewardship project operations, slash disposal, erosion control, or snag felling); or
(c) All contract requirements on a subdivision of Contract Area. Forest Service may perform such inspections without request from Contractor.
Within 2 days of inspection, excluding weekends and Federal holidays, Forest Service shall furnish Contractor with written notice either of acceptance or of work remaining to be done.
In the event that Forest Service is unable to make such inspection within 5 days of Contractor’s request, Contractor shall be notified in writing of necessity for postponement and time when inspection can be made. The same final approval procedure shall be used at the end of Contractor’s construction period on any completed portion of road.
Page 22 of 28 Libby Ranger District
When all contractual work of the Contractor has been accepted for any subdivision of Contract Area or cutting unit or stewardship project area identified on Contract Area Map, such area shall be eliminated from Contract Area on written notice of either party to this contract, unless such area is a portion of a larger work area. In the latter circumstance such area may be eliminated only by agreement.
SECTION IV – PAYMENT METHODS
M…