This is Amendment 004 to Solicitation 12363N26Q4189 for the Mitchell Jackson Integrated Restoration and Stewardship Contracting (IRSC) project issued by the USDA Forest Service Stewardship Contracting Branch. The amendment, effective July 1, 2026, provides informational documents and answers to contractor questions without extending the response due date. The period of performance runs from June 15, 2027 to October 15, 2032.
The amendment shares five supporting documents for informational purposes only that will not be binding in any resultant contract: weighted average haul information, logging plans and volume summaries for both Area 56 and Powerhouse areas. The amendment also addresses four questions from potential contractors regarding silvicultural slashing prescriptions (which are specified in Appendix A), biomass removal requirements (trees designated for cutting that meet utilization specifications must also be removed), whether blue-marked trees are designated for removal (yes, if they meet utilization specs), and the early start date for work (work may begin prior to the June 15, 2027 start date if conditions permit and are mutually agreed upon). The Contracting Officer is Mark T. Phillipp, and the Contracting Officer's Representative is Lauren Saint Pierre.
View the file
Other files
Show all 34
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
12363N26Q4189 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
363N
WASHINGTON DC 20250-1138
MS-1138
1400 INDEPENDENCE AVE SW
USDA-FS STEWARDSHIP CONTRACTING BR
07/01/20260004
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
07/01/2026
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Mitchell Jackson IRSC -12363N26R4189 Amendment 004
COR: Lauren Saint Pierre
This amendment makes the following changes to the Mitchell Jackson IRSC solicitation:
1. Shares answers to additional questions received
2. Shares logging plans, volume summary reports and estimated haul information. This information is shared for informational purposes only and will not be binding in a resultant contract. Documents shared include:
a. C05b_A004_MJ_Weighted Average Haul
b. C05c_A004_Area56_LoggingPlans
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
MARK T. PHILLIPP
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 3
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
12363N26Q4189/0004
c. C05d_A004_Area56_VolumeSummary
d. C05e_A004_Powerhouse_LoggingPlans
e. C05f_A004_Powerhouse_VolumeSummary
3. The response due date is not extended Period of Performance: 06/15/2027 to 10/15/2032
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
Mitchell Jackson IRSC- Amendment 004 Questions
Q1) Appendix A item 8 Slashing states ¿Silvicultural prescriptions for slashing will be provided by the FS upon request of the contractor" Can you please provide the slashing prescription?
A1) Specifications for slashing are called out in Appendix A. The prescriptions specify all the activities associated with a treatment unit and internal reporting codes.
Q2) Is Biomass removal required? Section C2.11 and C2.211 are confusing.
A2) Per B2.2 Utilization and Removal of Included Timber, "Except for timber required or authorized to be left Contractor shall fell and buck such trees and shall remove from Contract Area and present for Scaling all pieces that: (a) Meet minimum piece standards in Division A2 or (b) Do not meet such standards but would have qualified as part of minimum pieces if bucking lengths were varied to include such material." To simplify, trees that meet utilization specs and that are designated for cutting, are also designated for removal.
Q3) Are blue marked trees designated for cutting only or also for removal?
A3) Per B2.2 Utilization and Removal of Included Timber, "Except for timber required or authorized to be left Contractor shall fell and buck such trees and shall remove from Contract Area and present for Scaling all pieces that: (a) Meet minimum piece standards in Division A2 or (b) Do not meet such standards but would have qualified as part of minimum pieces if bucking lengths were varied to include such material." To simplify, trees that meet utilization specs and that are designated for cutting, are also designated for removal.
Q4) The stated period of performance begins on 6/15/2027, can work start prior to that if conditions allow?
A4) 6/15 is the annual start date of the normal operating season, work prior to this date may be agreed
to. Refer to the Contract Operations Schedule in the solicitation for additional information.