C-4 List of Deliverables.pdf
PDF 188 KB Posted
- Solicitation number
- 70Z02326R93250001
- Issued by
- Not on record
About this file
This document is a List of Deliverables for the Response Boat-Small Third Generation (RB-S III) federal contract. The deliverables span 53 items organized by Statement of Work and specification references, detailing technical documentation, testing procedures, and physical products required throughout the contract lifecycle. All deliverables are submitted to the Contracting Officer (KO) and Contracting Officer's Representative (COR), except the Trailer Title which goes to the Trailer recipient. The document specifies delivery milestones tied to contract events including Post Award Conference, Open Hull Inspection, Acceptance Testing, Physical Configuration Audit (PCA), and Post-Operational Test and Evaluation Review.
Key deliverables include the Offeror Technical Proposal at contract award; formal meeting agendas and minutes for major reviews; Integrated Master Schedules submitted monthly for the first 12 months then quarterly; Configuration Status Accounting data files and revised CSA data files tied to Product Configuration Baseline establishment; Product Drawings and 3-Dimensional Models submitted 45-90 days prior to PCA with 45-day government review periods; engineering calculations and technical manuals; Initial and Final Acceptance Test Procedures and reports; Incline and Drainage Test procedures and reports; Boat Information Books; crew familiarization materials; commercial parts catalogs; maintenance requirement lists; provisioning data; warranty documentation; and safety/compliance certifications. Pricing is allocated across multiple pricing sheets (NSP, X001, 1006 OP1, 1006 OP2, X004-X005, X012-X014) corresponding to different contract options and deliverable categories. Hard copy submissions are generally required with boats, while soft copies typically precede delivery by 14-90 days depending on the deliverable type.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Response Boat -Small Third Generation (RB-S III) Section C Attachment 4 List of Deliverable
RB-S III
List of Deliverables
# SOW / SPEC Ref. Deliverable Description Milestone To Required Delivery Pricing Sheet 1 N/A Offeror Proposal – Volume I
– Technical Proposal including all appendices
Contract Award KO &
COR
At Award NSP
2 040-2.1.2 040-2.4
Formal Meeting Agenda • Post Award Conference
• Open Hull Inspection
• Acceptance Testing
• Post-Operational Test and
Evaluation Review.
• Follow-On Order Year Reviews
KO &
COR
Formal meeting agenda seven days prior to the formal meeting
X001
3 040-2.1.2 040-2.4
Formal Meeting Draft and Final Meeting Minutes
• Post Award Conference
• Open Hull Inspection
• Acceptance Testing
• Post-Operational Test and Evaluation
Review.
• Follow-On Order Year Reviews
KO &
COR
Formal meeting minutes two days after conclusion of the formal meeting
X001
4 040-4 Integrated Master Schedule Post Award Conference KO &
COR
Monthly for the first 12 months; Quarterly thereafter, at the end of March, June, September, and December
X001
5 041-2 Initial Configuration Status Accounting (CSA) Data Files
Starting with acceptance of second boat KO &
COR
• With the boat
• As needed with change(s) to the configuration tracked by hull prior to Product Configuration Baseline (PCB).
1006 (OP2)
6 041-2 Final Configuration Status Accounting (CSA) Data Files
PCB KO &
COR
• With PCB
• 45 days Gov review
• 14 days after first review comments received
1006 (OP2)
RB-S III
List of Deliverables
# SOW / SPEC Ref. Deliverable Description Milestone To Required Delivery Pricing Sheet 7 041-2
041-5 Revised CSA Data Files • Pre-PCB, with each contractor change(s) identified by initial hull
• Post-PCB, with each approved ECP identified by initial hull
KO &
COR
• Pre-PCB, soft copy, 14 days prior to initial hull(s).
• Post-PCB, soft copy, 14 days of approved ECP.
1006 (OP2)
8 041-4.3 Product Drawings for Physical Configuration Audit (PCA)
PCA KO &
COR
• 90 days prior to
• 45 days Gov review
• 14 days after first review comments received
• Hard copy, at PCA.
1006 (OP2)
9 041-4.6 PCA Resolution Report PCA KO &
COR
30 days after USCG provides PCA report to Contractor
1006 (OP2)
10 041-5.1 Engineering Change Installation Instructions
(ECII)
As needed KO &
COR
As needed
11 041-7.1 Configuration Status Report
(CSR)
With boats KO &
COR
• Soft copy 14 day prior
• Hard copy with Boats
X001
12 042-1.4 Warranty Repair Plan As needed KO &
COR
As needed X001
13 042-1.7 Warranty Book listing warranty provided by the contractor and all commercial component warranties
With boats • KO
CO
• Boat
• Soft copy 14 day prior
• Hard copy with Boats
X001
Park, Myung C CIV USCG COMDT (USA) Does this stop at PCB?
RB-S III
List of Deliverables
# SOW / SPEC Ref. Deliverable Description Milestone To Required Delivery Pricing Sheet 14 068-1.3 Hull Structure Construction
Documents Open Hull Inspection KO &
COR
45 days prior to; in Contractor's Format. Shall provide sufficient detail to support Calculations. May be 2-Ddrawings, 3D model, or a combination of both. 2- D drawings and 3D model shall be viewable in AutoCAD. Sketches and vendor's cut sheets shall be submitted as PDFs.
1006 (OP2)
15 077-2.1 Safety Data Sheet (SDS) With boats • KO
CO
• Boat
• Soft copy 14 day prior
• Hard copy with Boats
X001
16 083-1.2 Commercial Parts Catalog With second boat KO &
COR
Soft copy 14 day prior 1006 (OP2)
17 083-2.1 1200 Hr. Maintenance Requirement List (MRL)
With boats • KO
CO
• Boat
• Soft copy 14 day prior
• Hard copy with Boats
X001
18 083-2.4 MRL Kit (1200 Hr. Parts & Tools) Inventory List
With boats • KO
CO
• Boat
• Soft copy 14 day prior
• Hard copy with Boats
X001
19 083-3 Initial Master Equipment Configuration List (MECL)
With first boat KO &
COR
• 90 days prior to
• 45 days Gov review
• 14 days after first review comments received
0006 (OP1)
RB-S III
List of Deliverables
# SOW / SPEC Ref. Deliverable Description Milestone To Required Delivery Pricing Sheet 20 083-3 MECL Starting with second boat and with each boat until PCB is estimated
• KO
CO
• Boat
• Soft copy 14 day prior
• Hard copy with Boat
1006 (OP2)
21 083-4 List of Special Tools & Test Equipment
With second boat
KO &
COR
• 14 day prior
• As needed
1006 (OP2)
22 083-5 System Insurance Stock (SIS) Documentation
With SIS • KO
CO
• SIS
• Soft copy 14 day prior
• Hard copy with SISs
X012 – X014
23 083-7 Provisioning Data With second boat KO &
14 days prior to
24 083-7 Revised Provisioning Data As needed KO &
COR
As needed
25 084-1.6 Shipping Inventory List With boats • KO
CO
• Boat
• Soft copy 14 days prior
• Hard copy with Boats
X001
26 085-2 Initial Drawing Number Assignment Report (DNAR)
With first boat KO &
COR
• 90 days prior to
• 45 days Gov review
• 14 days after first review comments received
0006 (OP1)
27 085-2 Final DNAR PCA KO &
COR
• 90 days prior to
• 45 days Gov review
• 14 days after first review comments received
1006 (OP2)
CPID 2073
RB-S III
List of Deliverables
# SOW / SPEC Ref. Deliverable Description Milestone To Required Delivery Pricing Sheet 28 085-3 Preliminary Drawings;
should include sufficient info to support structure and stability review of preliminary calculations -general arrangement, structural arrangement, and lines and offsets
With first boat • KO
CO
• Boat
• 90 days prior; in Contractor’s Format
• With; in Contractor’s format, one hard copy to be provided.
0006 (OP1)
29 085-3 Product Drawings With PCA Resolution Report KO &
COR
• With
• 45 day Gov review
• 14 days after first review comments received
1006 (OP2)
30 085-6 Preliminary 3-Dimensional Model (3D Model); does not have to comply with MIL- STD-31000 but include details sufficient to support design review, preliminary weight assessment, and evaluation of fabrication geometry
Open Hull Inspection KO &
COR
45 days prior to; in Contractor’s Format.
1006 (OP2)
31 085-6 3D Model With PCA Resolution Report KO &
COR
• With
• 45 day Gov review
• 14 days after first review comments received
1006 (OP2)
CPID 2074
RB-S III
List of Deliverables
# SOW / SPEC Ref. Deliverable Description Milestone To Required Delivery Pricing Sheet 32 085-7 Preliminary Calculations supporting the proposal’s narrative and demonstrating the structure and stability meets ISO 12215 / 12217 requirements
With first boat KO &
COR
90 days prior in Contractor’s Format
0006 (OP1)
33 085-7 Initial Calculations Open Hull Inspection KO &
COR
• 45 days prior to; in Contractor’s Format.
• 30 days Gov review
• 14 days after first review comments received
1006 (OP2)
34 085-7 Final Calculations With PCA Resolution Report KO &
COR
• With
• 45 day Gov review
• 14 days after first review comments received
1006 (OP2)
35 086-1.3 Technical Manuals Index With boats • KO
COR
• Boat
• Soft copy 14 day prior
• Hard copy with Boats
X001
36 086-1.1 086-2.1
OEM Technical Manuals and Publications
With boats • KO
COR
• Boat
• Soft copy 14 day prior
• Hard copy with Boats
X001
37 086-3 Initial Boat Information Book (including HM&E Support Section, C4ISR System/Network Support Section, and Casualty Control Section)
With first boat • KO
COR
• Boat
• Soft copy 90 days prior
• With, Contractor Format:
Shall include preliminary system schematics for fuel, electrical, communication, and navigation system, and lifting system. One hard copy
X001
RB-S III
List of Deliverables
# SOW / SPEC Ref. Deliverable Description Milestone To Required Delivery Pricing Sheet 38 086-3 Final Boat Information Book
(including HM&E Support Section, C4ISR System/Network Support Section, and Casualty Control Section)
Starting with second boat • KO
COR
• Boat
• Soft copy 60 day prior
• 30 days GOV review
• Hard copy with Boats
X001
39 089-1 Crew FAM Syllabus & FAM Material
With crew fam KO &
COR
• Soft copy 14 day prior
• Hard copy with crew fam
X004; X005
40 091-1.4 Acceptance Testing for First Boat, Documentation
With first boat • KO
COR
• Boat
• Soft copy with Boat
• Hard copy with Boat
X001
41 092-3.1.1 Initial Acceptance Test Procedures
Acceptance Test Starting with Second Boat
KO &
COR
• 90 days prior to test
• 45 days Gov Review
1006 (OP2)
42 092-3.1.1 Final Acceptance Test Procedures
Acceptance Test KO &
COR
30 days prior to 1006 (OP2)
43 092-3.1.2 Acceptance Test Reports and Calibration Data and Test Equipment Certification [092-1.4]; Scale Weighing Test result [092-5.28], Firmware and Software Verification [402-1.4].
With boats • KO
COR
• Boat
• Seven days prior to
• With
X001
44 092-3.1.4 Failure and Discrepancy Reports
As needed KO &
COR
As needed NSP
45 096-1 Center of Gravity Report With boats • KO
COR
• Boat
• Seven days prior to
• With
X001
46 097-1.2 Incline Test Plan Incline Test KO &
COR
• 90 days prior to test
• 45 days Gov Review
RB-S III
List of Deliverables
# SOW / SPEC Ref. Deliverable Description Milestone To Required Delivery Pricing Sheet 47 097-1.5 Incline Test Report Incline Test KO &
COR
5 days after Incline Test 1006 (OP2)
48 097-2.1 Drainage Test Procedure Drainage Test KO &
COR
• 90 days prior to test
• 45 days Gov Review
1006 (OP2)
49 097-2.2 Drainage Test Report Drainage Test KO &
COR
5 days after Drainage Test 1006 (OP2)
50 233-1 OEM Certification Letter for 40 CFR Part 1045, Control of Emissions from Spark- Ignition Propulsion Marine Engines and Vessel
With boats KO &
COR
• Soft copy 14 day prior
• Hard copy with Boats
X001
51 402-5 Vulnerability and Resolution Report
With boats KO &
COR
7 days prior X001
52 660-1.1.5 OEM Shock Mitigating Seat Test Report
Open Hull Inspection KO &
45 days prior to
53 910-1.1 Trailer Title With boats Trailer With the boat X001