The document is a Buy American Certification for Construction Projects issued by the Federal Aviation Administration (FAA), applicable to the Kenton County Airport Board's (KCAB) North & South Aircraft Rescue and Firefighting (ARFF) Stations Mechanical, Electrical & Plumbing (MEP) Modifications & Tank Installation project. The project involves comprehensive modifications to ARFF facilities, transitioning from Aqueous Film Forming Foam (AFFF) to Fluorine Free Foam (F3), which requires installing new 2000-gallon polyethylene foam storage tanks, centrifugal chemical processing pumps, distribution piping, valves, and electrical modifications at both North and South ARFF stations. A mandatory pre-bid meeting and site visit is scheduled for Thursday, November 6, 2025, at 10:00 am, with bidder questions due by November 20, 2025, and the final bid submission deadline set for Thursday, December 4, 2025, at 2:00 pm.

The project is estimated to cost $660,000, with $545,000 allocated for construction/installation and $109,000 for contingency, to be funded through CAPEX. The procurement emphasizes equal opportunity, compliance with federal regulations, and Buy American provisions, requiring contractors to certify that steel and manufactured goods used in the project are produced in the United States. Bidders must provide comprehensive documentation including safety evaluations, incident rates, workers' compensation modification rates, and OSHA documentation. The project is scheduled for procurement completion in November 2025 and design/construction completion by July 2026, with the contractor expected to commence work within 10 calendar days of receiving the Notice to Proceed. Known project risks include potential reduced fire suppression effectiveness, higher costs, limited foam availability, required firefighter retraining, and specialized storage and disposal requirements.

View the file

Other files

File Type Posted
25-069-ITB_Pre-Bid_Sign-In_Sheets.pdf PDF
25-069-ITB_Pre-Bid_Meeting_Agenda.pdf PDF
North_&_South_ARFF_Stations_Mechanical,_Electrical_&_Plumbing_(MEP)_Modifications_&_Tank_Installation.pdf PDF
25-069-ITB_N_&_S_ARFF_MEP_&_Tank_Installation_-_Ad.pdf PDF
25-069-ITB_N_&_S_ARFF_MEP_&_Tank_Installation_-_Exhibit_B-Contract_&_Bonds.pdf PDF
25-069-ITB_Bidders_List_2025.xlsx XLSX spreadsheet
25-069-ITB_N_&_S_ARFF_MEP_&_Tank_Installation_-_Exhibit_A-Proposal_Forms.pdf PDF
25-069-ITB_South_ARFF-AFFF_-_Full_Set_Drawings.pdf PDF
25-069-ITB_North_ARFF-AFFF_-_Full_Set_Drawings.pdf PDF
25-069-ITB_N_&_S_ARFF_-_AFFF_-_Technical_Specifications.pdf PDF
5035-05-CVG_-_South_ARFF-AFFF-Full_Set_ITB.pdf PDF
5035-05-CVG_-_North_ARFF-AFFF-Full_Set_ITB.pdf PDF
5035-05-CVG-ARFF-AFFF-ITB_Specifications.pdf PDF
2025.10.16_APPROVED_ADDITION_Q4_2025_-_Business_Case_-_ARFF_AFFF_Transition_-_New_Construction_-_signed.pdf PDF
2025.06.13_Construction_Cost_Estimate.pdf PDF
Buy_American_Certification-Construction_Projects.docx DOCX document
EEO_Certification.docx DOCX document
Affirmative_Action_Certification.docx DOCX document
Non_Debarment_or_Suspension_Certification.docx DOCX document
Buy_American_Certification-Equipment-Building_Projects.docx DOCX document
NonSegregated_Facilities_Certification.docx DOCX document
Certification_of_Offeror-Bidder_Regarding_Tax_Delinquency_and_Felony_Convictions.docx DOCX document
Disclosure_of_Lobbying_Activities_Certification.docx DOCX document
Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BUY AMERICAN CERTIFICATION –

CONSTRUCTION PROJECTS

The contractor shall comply with 49 USC § 50101, which provides that Federal funds may not be obligated unless all steel and manufactured goods used in AIP-funded projects are produced in the United States, unless the FAA has issued a waiver for the product; the product is listed as an Excepted Article, Material Or Supply in Federal Acquisition Regulation subpart 25.108; or is included in the FAA Nationwide Buy American Waivers Issued list.

As a matter of bid responsiveness, the bidder or offeror must complete, sign, date, and submit this certification statement with their proposal. The bidder or offeror must indicate how they intend to comply with 49 USC § 50101 by selecting one on the following certification statements. These statements are mutually exclusive. Bidder must select one or the other (not both) by inserting a checkmark (ü) or the letter “X”.

· Bidder or offeror hereby certifies that it will comply with 49 USC § 50101 by:

a) Only installing steel and manufactured products produced in the United States, or;

b) Installing manufactured products for which the FAA has issued a waiver as indicated by inclusion on the current FAA Nationwide Buy American Waivers Issued listing, or;

c) Installing products listed as an Excepted Article, Material or Supply in Federal Acquisition Regulation Subpart 25.108.

By selecting this certification statement, the bidder or offeror agrees:

1. To provide to the Owner evidence that documents the source and origin of the steel and manufactured product.

2. To faithfully comply with providing US domestic product

3. To furnish US domestic product for any waiver request that the FAA rejects

4. To refrain from seeking a waiver request after establishment of the contract, unless extenuating circumstances emerge that the FAA determines justified.

· The bidder or offeror hereby certifies it cannot comply with the 100% Buy American Preferences of 49 USC § 50101(a) but may qualify for either a Type 3 or Type 4 waiver under 49 USC § 50101(b). By selecting this certification statement, the apparent bidder or offeror with the apparent low bid agrees:

1. To the submit to the Owner within 15 calendar days of the bid opening, a formal waiver request and required documentation that support the type of waiver being requested.

2. That failure to submit the required documentation within the specified timeframe is cause for a non-responsive determination may result in rejection of the proposal.

3. To faithfully comply with providing US domestic products at or above the approved US domestic content percentage as approved by the FAA.

4. To refrain from seeking a waiver request after establishment of the contract, unless extenuating circumstances emerge that the FAA determines justified.

Required Documentation Type 3 Waiver - The cost of the item components and subcomponents produced in the United States is more that 60% of the cost of all components and subcomponents of the “item”. The required documentation for a type 3 waiver is:

a) Listing of all product components and subcomponents that are not comprised of 100% US domestic content (Excludes products listed on the FAA Nationwide Buy American Waivers Issued listing and products excluded by Federal Acquisition Regulation Subpart 25.108; products of unknown origin must be considered as non-domestic products in their entirety).

b) Cost of non-domestic components and subcomponents, excluding labor costs associated with final assembly at place of manufacture.

c) Percentage of non-domestic component and subcomponent cost as compared to total “item” component and subcomponent costs, excluding labor costs associated with final assembly at place of manufacture.

Type 4 Waiver – Total cost of project using US domestic source product exceeds the total project cost using non-domestic product by 25%. The required documentation for a type 4 of waiver is:

a) Detailed cost information for total project using US domestic product

b) Detailed cost information for total project using non-domestic product False Statements: Per 49 USC § 47126, this certification concerns a matter within the jurisdiction of the Federal Aviation Administration and the making of a false, fictitious or fraudulent certification may render the maker subject to prosecution under Title 18, United States Code.