2025.06.13_Construction_Cost_Estimate.pdf

PDF 88 KB Posted

Attached to
North & South ARFF Stations Mechanical, Electrical & Plumbing (MEP) Modifications & Tank Installation
Solicitation number
25-069-ITB
Issued by
Kenton County, Kentucky

About this file

This document is an Estimate of Probable Cost for the CVG ARFF AFFF Build Back project located in Erlanger, Kentucky, dated 6/13/2025. The project involves renovation of Aircraft Rescue and Firefighting (ARFF) facilities at the North and South truck bay areas, with a total renovation scope of 1,740 square feet. The project is divided into multiple construction divisions, including demolition, masonry, metals, finishes, fire protection, and electrical work. Key components include installing 2000-gallon tanks, foam pumps, piping, electrical wiring, and associated infrastructure upgrades.

The total project cost is estimated at $229,915, with $127,937 allocated for the North section and $101,977 for the South section. The cost breakdown includes direct costs, general conditions, overhead and profit, and a 15% contingency. The North section has a cost per square foot of $92, while the South section is estimated at $63 per square foot. The project will involve specific tasks such as demolishing CMU walls, installing steel channels and railings, painting, and electrical system upgrades. The estimate is prepared at 100% documentation level and uses a unit price estimation method.

View the file

Other files

File Type Posted
25-069-ITB_Pre-Bid_Sign-In_Sheets.pdf PDF
25-069-ITB_Pre-Bid_Meeting_Agenda.pdf PDF
North_&_South_ARFF_Stations_Mechanical,_Electrical_&_Plumbing_(MEP)_Modifications_&_Tank_Installation.pdf PDF
25-069-ITB_N_&_S_ARFF_MEP_&_Tank_Installation_-_Ad.pdf PDF
25-069-ITB_N_&_S_ARFF_MEP_&_Tank_Installation_-_Exhibit_B-Contract_&_Bonds.pdf PDF
25-069-ITB_Bidders_List_2025.xlsx XLSX spreadsheet
25-069-ITB_N_&_S_ARFF_MEP_&_Tank_Installation_-_Exhibit_A-Proposal_Forms.pdf PDF
25-069-ITB_South_ARFF-AFFF_-_Full_Set_Drawings.pdf PDF
25-069-ITB_North_ARFF-AFFF_-_Full_Set_Drawings.pdf PDF
25-069-ITB_N_&_S_ARFF_-_AFFF_-_Technical_Specifications.pdf PDF
5035-05-CVG_-_South_ARFF-AFFF-Full_Set_ITB.pdf PDF
5035-05-CVG_-_North_ARFF-AFFF-Full_Set_ITB.pdf PDF
5035-05-CVG-ARFF-AFFF-ITB_Specifications.pdf PDF
2025.10.16_APPROVED_ADDITION_Q4_2025_-_Business_Case_-_ARFF_AFFF_Transition_-_New_Construction_-_signed.pdf PDF
Buy_American_Certification-Construction_Projects.docx DOCX document
EEO_Certification.docx DOCX document
Affirmative_Action_Certification.docx DOCX document
Non_Debarment_or_Suspension_Certification.docx DOCX document
Buy_American_Certification-Equipment-Building_Projects.docx DOCX document
NonSegregated_Facilities_Certification.docx DOCX document
Certification_of_Offeror-Bidder_Regarding_Tax_Delinquency_and_Felony_Convictions.docx DOCX document
Disclosure_of_Lobbying_Activities_Certification.docx DOCX document
Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project No. 5035-05

Date: 6/13/2025

100% Docs

ARFF North Truck Bay 1270

ARFF North Mezzanine Tank Area 116

ARFF South Truck Bay 1350

ARFF South Mezzanine Tank Area 274

Total Renovation 1740 North South

Division 2 - Demolition 5,000 2,500

Division 4 - Masonry 1,200 0

Division 5 - Metals 8,050 3,750

Division 6 - Wood, Plastic, and Composites 0 0

Division 8 - Openings 0 0

Division 9 - Finishes 1,775 625

Division 21 - Fire Protection 62,500 57,500

Division 22 - Plumbing 0 0

Division 23 - HVAC 0 0

Division 26 - Electrical 8,413 3,538

Division 27 - Communications 0 0

Division 28 - Fire Alarm 0 0

Total Direct Cost $86,938 $67,913

Division 1 General Conditions 12.00% 10,433 8,150

Total Direct Costs & General Conditions 97,370 76,062

GC O&P 18.00% 17,527 13,691

Contingency 15.00% 13,041 12,224

Allowance - Geotech / Survey / Hazardous Materials Survey 0 0

North South Combined

Total Project $127,937 $101,977 $229,915

North cost per SF 1386 $92

South cost per SF 1624 $63

CVG ARFF AFFF Build Back, Erlanger KY

Estimate of Probable Cost

SUMMARY

Total

Cost

General Builing Area SF

Description

Total

Cost

GRW 1 of 7

Project No. 5035-05 Level: 100% Docs

Date: 6/13/2025 Dwg. No. NA

Estimator: Staff Type: Unit Price

Division 1 - General Requirements

Construct. documentation, Temp. Fac., Waste Manage., O/M Man. See summary page

Division 1 Subtotal 0

Division 2 - Existing Conditions, Demolition:

Demo CMU wall 57 SF sawcut, remove, disposal 1 LF 5,000.00 5,000

Division 2 Subtotal 5,000

Division 4- Masonry:

Grout perimeter of new CMU wall opening 1 LF 1,200.00 1,200

Division 4 Subtotal 1,200

Division 5 - Metals

Steel channel C10x15.3 A36 welded and bolted in place 23 LF 23 LF 350.00 8,050

Steel plate 5/8"x1'4"x8'8" bolted in place 9 LF 250.00 2,250

Steel pipe railing 9 LF 250.00 2,250

Division 5 Subtotal 8,050

Division 6 - Wood, Plastic, and Composites :

Division 6 Subtotal 0

Division 7 - Thermal and Moisture Protection :

Division 7 Subtotal 0

Division 8 - Openings

Division 8 Subtotal 0

CVG ARFF AFFF Build Back, Erlanger KY

Estimate of Probable Cost

NORTH BREAKDOWN

Units of

Measure

Unit

Cost

Total

CostDescription

Number of

Units

GRW 2 of 7

Units of

Measure

Unit

Cost

Total

CostDescription

Number of

Units

Division 9 - Finishes

Paint CMU at perimeter of demo openning 23 LF 25.00 575

Paint steel channel, railing, and mounting plate 1 LS 1,200.00 1,200

Division 9 Subtotal 1,775

Division 10 - Specialties:

Division 10 Subtotal 0

Division 11 - Equipment

Division 11 Subtotal 0

Division 12 - Furnishings

Division 12 Subtotal 0

Division 21 - Fire Protection

2000 gallon tank - material and installation 1 EA 15,000.00 15,000

Foam Pump - material and installation 1 EA 7,500.00 7,500

Piping - material and installation 1 LUMP 40,000.00 40,000

Division 21 Subtotal 62,500

Division 22 - Plumbing

Division 22 Subtotal 0

Division 23 - HVAC:

Division 23 Subtotal 0

Division 26 - Electrical:

Wiring, Copper 225 LF 12.50 2,813

Conduit, EMT 225 LF 20.00 4,500

Disconnect Switch, Heavy Duty 1 EA 850.00 850

Circuit Breaker, Bolt-On 1 EA 250.00 250

Division 26 Subtotal 8,413

Division 27 - Communications:

Division 27 Subtotal 0

GRW 3 of 7

Units of

Measure

Unit

Cost

Total

CostDescription

Number of

Units

Division 28 - Fire Alarm:

Division 28 Subtotal 0

Division 31 - Earthwork

Division 31 Subtotal 0

Division 32 - Exterior Improvements

Division 32 Subtotal 0

Division 33 - Utilities

Division 33 Subtotal 0

TOTAL 86,938

GRW 4 of 7

Project No. 5035-05 Level: 100% Docs

Date: 6/13/2025 Dwg. No. NA

Estimator: Staff Type: Unit Price

Division 1 - General Requirements

Construct. documentation, Temp. Fac., Waste Manage., O/M Man. See summary page

Division 1 Subtotal 0

Division 2 - Existing Conditions, Demolition:

Remove steel railing 25 LF 100.00 2,500

Division 2 Subtotal 2,500

Division 4- Masonry:

Division 4 Subtotal 0

Division 5 - Metals

Reinstall steel railing 25 LF 150.00 3,750

Division 5 Subtotal 3,750

Division 6 - Wood, Plastic, and Composites :

Division 6 Subtotal 0

Division 7 - Thermal and Moisture Protection :

Division 7 Subtotal 0

Division 8 - Openings

Division 8 Subtotal 0

Description

Number of

Units

Units of

Measure

Unit

Cost

Total

Cost

CVG ARFF AFFF Build Back, Erlanger KY

Estimate of Probable Cost

SOUTH BREAKDOWN

GRW 5 of 7

Description

Number of

Units

Units of

Measure

Unit

Cost

Total

Cost

Division 9 - Finishes

Paint reinstalled steel railing 25 LF 25.00 625

Division 9 Subtotal 625

Division 10 - Specialties:

Division 10 Subtotal 0

Division 11 - Equipment

Division 11 Subtotal 0

Division 12 - Furnishings

Division 12 Subtotal 0

Division 21 - Fire Protection

2000 gallon tank - material and installation 1 EA 10,000.00 10,000

Foam Pump - material and installation 1 EA 7,500.00 7,500

Piping - material and installation 1 LUMP 40,000.00 40,000

Division 21 Subtotal 57,500

Division 22 - Plumbing

Division 22 Subtotal 0

Division 23 - HVAC:

Division 23 Subtotal 0

Division 26 - Electrical:

Wiring, Copper 75 LF 12.50 938

Conduit, EMT 75 LF 20.00 1,500

Disconnect Switch, Heavy Duty 1 EA 850.00 850

Circuit Breaker, Bolt-On 1 EA 250.00 250

Division 26 Subtotal 3,538

Division 27 - Communications:

Division 27 Subtotal 0

GRW 6 of 7

Description

Number of

Units

Units of

Measure

Unit

Cost

Total

Cost

Division 28 - Fire Alarm:

Division 28 Subtotal 0

Division 31 - Earthwork

Division 31 Subtotal 0

Division 32 - Exterior Improvements

Division 32 Subtotal 0

Division 33 - Utilities

Division 33 Subtotal 0

TOTAL 67,913

GRW 7 of 7