Supervisory Control and Data Acquisition (SCADA) System Upgrades & Maintenance State and local contract opportunity
Solicitation number
26-035-RFP
Issued by
Bell County, Kentucky

About this file

This is a Business Case document and related state and local contract opportunity from the Kenton County Airport Board (KCAB) in Kentucky for Supervisory Control and Data Acquisition (SCADA) System Upgrades and Maintenance. The project involves replacing legacy Honeywell control systems with Programmable Logic Controller (PLC) platforms, integrating new control systems for the DHL ramp expansion, and consolidating multiple SCADA software platforms into one unified system to manage spent aircraft deicing fluid recovery and stormwater treatment operations. A pre-proposal meeting and site visit will be held on Tuesday, June 2, 2026 at 10:00 am at CVG Centre, Admin. Offices, 77 Comair Blvd., Erlanger, Kentucky. Written questions are due by 11:59 pm on Monday, June 22, 2026, with answers posted no later than Thursday, June 25, 2026 at 11:59 pm. Proposals must be received by Thursday, July 2, 2026 at 2:00 pm, with no late submissions accepted unless extended by addendum. The project schedule indicates software implementation and equipment installation completion by November 1, 2026.

The total appropriations request is $2,686,210, comprised of design costs ($270,000), equipment ($2,100,000), supervisory control and data acquisition system upgrades ($237,000), force labor ($78,210), and miscellaneous costs ($1,000), with recurring operations and maintenance yearly costs of $15,000. Cost estimate certainty is rated at 100 percent based on received vendor quotes. The project is funded through CAPEX and requires board approval. Key organizational benefits include improved system reliability through modern equipment, reduced downtime due to readily available parts, lower total project costs and long-term savings from eliminating tag license requirements, strengthened cybersecurity, regulatory compliance, and expandability for future growth. The failure risk of outdated Honeywell boards would result in loss of control and monitoring capabilities for glycol conveyance assets and improper handling of spent aircraft deicing fluid processing.

View the file

Other files for this state and local contract opportunity

Other files attached to Supervisory Control and Data Acquisition (SCADA) System Upgrades & Maintenance, newest first.
File Type Posted
Supervisory_Control_and_Data_Acquisition_(SCADA)_System_Upgrades_&_Maintenance_(Addendum_#5_Revision).pdf PDF
26-035-RFP_DHL_Expansion_058529_PKG5_-_Electrical_Plans.pdf PDF
26-035-RFP_DHL_Pkg_S5_SADF_&_SW_Conveyance_IFC_Plans_2025.10.13.pdf PDF
26-035-RFP_HMI_Screenshots_06.18.26.pdf PDF
26-035-RFP_Glycol_Control_Systems_Drawings.pdf PDF
26-035-RFP_Photos_-_HW_Panels.pdf PDF
26-035-RFP_SCADA_System_Architecture_Drawings.pdf PDF
26-035-RFP_VTSCADA_Tag_Count_&_Server_List.pdf PDF
26-035-RFP_KPDES_Systems_Map_2025.07.pdf PDF
26-035-RFP_SCADA_Upgrade_-_Ad.pdf PDF
Davis-Bacon_Wage_Determination_-_Heavy_01.02.2026_-_Attachment_G.pdf PDF
26-035-RFP_SCADA_Upgrade_-_Sample_Contract_-_Attachment_F.pdf PDF
Honeywell_Glycol_Points_Panel_-_Attachment_A.pdf PDF
CVG_IT_Standard_Equip_List_for_Industrial_Networking_Deployments_-_Attachment_B.pdf PDF
SCADA_Upgrade_Maintenance_Plan_-_Attachment_C.pdf PDF
CVG_IT_Standard_Equipment_List_for_Industrial_Networking_Deployments.pdf PDF
SCADA_IT_System_Requirements_-_Attachment_x.xlsx XLSX spreadsheet
Honeywell_Glycol_Points_Panel.xlsx XLSX spreadsheet
SCADA_Upgrade_Maint_Plan.docx DOCX document
Show all 19

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Master Plan Alignment

Strategic Plan Alignment

Sustainability Benefits

$270,000.00

$2,100,000.00

$237,000.00

$78,210.00

$1,000.00

$2,686,210.00

Recurring O&M yearly costs: $15,000.00

Force Labor:

Miscellaneous:

Total Appropriations Request:

Certainty of Cost Estimates

100% - received quote from vendor

Cost

Project Value/ROI: A more reliable overall SCADA system due to modern equipment (PLCs). Reduced downtime as modern equipment is more readily available.

Lower total project costs and long-term savings due to elimination of tag license requirements.

Organizational Impact

Project Approach

Engineer a control system based on current industry standards, CVGAA standards, and best practices. Remove Honeywell control system. Install and commission a new system, including full wiring, configuration, and functional validation. Install new SCADA interface.

Alternatives

Vendor Contingency:

Continue to use the Honeywell Control system with outdated boards and run the risk of failure. Failure of these boards would result in losing the ability to control and monitor the glycol conveyance assets (Diversion valves for deice pads, glycol pump stations, and remotely operating gates at the detention basins) until outdated parts can procured. We buy additional tags with existing SCADA program for DHL expansion, which will be temporary until a new system is installed or we use a new

SCADA program as test run to determine effectiveness.

Related Projects

This should be in place before the DHL Ramp Expansion is complete

Design:

Equipment:

Supervisory Control and Data Acquisition (SCADA) Upgrades for Spent Aircraft Deicing Fluid Recovery PMWeb #

Current Situation/Background Information

The stormwater management system uses two Supervisory Control and Data Acquisition (SCADA) systems to control and monitor various valves, pumpstations, tank levels, and the stormwater treatment plant. The glycol conveyance system SCADA utilizes Honeywell Enterprise Buildings Integrator and the stormwater conveyance system uses VTSCADA as the SCADA software platforms. These assets are responsible for capturing, conveying, storing and treating spent aircraft deicing fluid (SADF).

The Honeywell Enterprise Buildings Integrator system is outdated and better suited for building management. DHL is currently expanding their ramp. Their expansion includes additional pumpstations and a deice pads. These assets will require SCADA integration for controlling and monitoring these assets. The existing VTSCADA software system is at tag licensing capacity.

Project Definition

Project Scope:

(1) Replace the existing legacy Honeywell control system for the glycol conveyance system to Programmable Logix Controllers (PLC) platform to match the existing stormwater conveyance SCADA system.

(2) Integrate the new control system for SADF conveyance from DHL ramp expansion.

(3) Replace the stormwater treatment plant existing SCADA software platform to address licensing limitations. Integrate the new PLCs, the new control system for the expansion of DHL ramp, and the existing stormwater conveyance system into one SCADA Software platform. The existing stormwater conveyance SCADA system will remain unchanged as it was upgraded in 2018.

Organizational Impact Justification

Fuel Performance via Operational Excellence - Ensure the safety and health of passengers and employees

Business Objectives: Improves reliability, strengthens cybersecurity, more efficient, ensures regulatory compliance, and is expandable for future growth. Ensures the storm management system operates under one seamless SCADA system.

Risk if Not Funded: If existing Honeywell panels need to be replaced, the cost and lead time for delivery of replacements could be significant due to the age of the system. Failure of these boards would result in losing the ability to control and monitor the glycol conveyance assets (Diversion valves for deice pads, glycol pump stations, and remotely operating gates at the detention basins). As the DHL ramp expansion progresses, the related assets would not be added to the current system, resulting in improper monitoring and processing of spent aircraft deicing fluid (SADF).

1/28/2026

4/30/2026

5/18/2026

5/26/2026

6/1/2026

11/1/2026

ARFF Human Resources

Business Administration Information Technology

Capital Accounting Innovation

Commercial Management Operations

Customer Experience Planning & Development

Environmental, Social & Governance (ESG) Police Department

Facilities Procurement

Field Safety

Finance Terminal Modernization Program

Fleet Other __Environmental Operations______________

Approvals:

Software Implementation/Equipment Installation Complete

Known Risks & Limitations

None

Recommendation

Remove the Honeywell control panels related to the glycol control system. Install PLC panels to replace Honeywell panels. Install one SCADA program, either new

SCADA program that is specifically designed for water treatment processes or continue to use existing SCADA program in accordance with current industry and

CVGAA standards.

Visuals

Larry Krauter

Chief Executive Officer

Dil Gruffydd

Chief Financial Officer

Executive Sponsor

Shannon Oldfield

Chief Operations Officer

Concurrence Leader

Brian Cobb

Chief Innovation Officer

Business Unit Leader

Tim Haizlip

Vice President, Maintenance & Asset Management

Sponsor/Originator

Scott Thacker

Senior Manager Environmental Operations

Procurement (Bid/Solicitation) Completion

Contract Negotiation Finalized

Board Meeting

Software/Equipment Purchase (after contract is signed)

Project Funding

CAPEX

Project Schedule

Appropriations Approval

Stakeholders