Bureau of Air Operating and Construction Permit Fee Tables - Attachment C.docx
DOCX document 16 KB Posted
- Attached to
- Environmental Information Management System EIMS
- Solicitation number
- 26-532EPA-FISCP-B-51295
- Issued by
- Illinois
About this file
This is an Operating Permit Fees attachment document from a state Bureau of Air, establishing fee structures for air quality permits and emissions compliance. The document presents a tiered fee schedule for Title V (CAAPP) operating permits based on annual emissions thresholds. Facilities with emissions at or below 100 tons per year (TPY) are assessed a minimum annual fee of $2,150. Facilities with emissions exceeding 100 TPY but not exceeding 13,674 TPY are charged $21.50 per ton of emissions annually. Facilities with emissions exceeding 13,674 TPY face a maximum annual fee of $294,000, with the document noting additional FESOP (Federally Enforceable State Operating Permit) fees apply.
The fee structure represents the current operating permit pricing model implemented by the state air quality regulatory authority. This tiered approach incentivizes emissions reductions by capping fees at the highest emission level, while ensuring smaller operations pay proportionally lower costs. The fees fund the state's air permitting and compliance monitoring programs and reflect the administrative and enforcement costs associated with Title V operating permits required under federal Clean Air Act regulations.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| c2d-vendor-guidance.pdf | ||
| vendor-disclosure-formerly-forms-a-v26-1-6-25-2025~1.docx | DOCX document | |
| 260410 EIMS Rebid RFP~1.docx | DOCX document | |
| EIMS Pre-Submission Conference Sign-In Sheet 2 of 2.pdf | ||
| BEP U-Plan.pdf | ||
| ipg-active-registered-vendor-disclosure-formerly-forms-b-v.23.1~8.docx | DOCX document | |
| information-and-technology-request-for-proposal-offer-to-the-state-of-illinois.pdf | ||
| 260225 Attachment B - IL Cost Workbook .xlsx | XLSX spreadsheet | |
| 260227 EIMS Rebid RFP.docx | DOCX document | |
| 2600415 IEPA EIMS Rebid Q and A.docx | DOCX document | |
| state-of-illinois-standard-it-terms-and-conditions-v26-1.pdf | ||
| c2d-vendor-answer-sheet-v.24.4 ~3.docx | DOCX document | |
| 260225 Revised Attachment A - Traceability Matrix.xlsx | XLSX spreadsheet | |
| EIMS Pre-Submission Conference Sign-In Sheet 1 of 2.pdf |
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Operating Permit Fees Current Fees
Title V (CAAPP) Fees
| ≤100 TPY Minimum Emission Fee |
| $2,150/yr |
| >100 ≤13,674 TPY Emission Fee |
| $21.50/ton |
| >13,674 TPY Emission Fee |
| $294,000/yr Max |
FESOP Fees
| <25 TPY Emissions |
| $235/yr |
| ≥25 <100 TPY Emissions |
| $2,150/yr |
| ≥100 ≤191 TPY Emissions |
| $21.50/ton |
| >191 TPY Emissions |
| $4,112/yr Max |
State/LOP Fees
| <25 TPY Emissions |
| $235/yr |
| ≥25 <100 TPY Emissions |
| $2,150/yr |
| ≥100 ≤191 TPY Emissions |
| $21.50/ton |
| >191 TPY Emissions |
| $4,112/yr Max |
ROSS Fee
| Registration Fee |
| $235/yr |
Other Fees
| Avoided Operating Permit Fees |
| Double amount owed had a permit been timely obtained |
| Expedited Permit Fee |
| 4 times the standard fee, Max $100,000 |
| Construction Permit Application Fees |
| Current Fees |
CAAPP/FESOP Sources
| Base Fee – New Emission Unit |
| $4,000 1st new emission unit, |
$1,000/additional new or modified emission unit, Max $10,000
| Base Fee – Modified Emission Unit |
| $2,000 1st modified emission unit, |
$1,000/additional modified emission unit, Max $5,000
| Supplemental Fees – CAAPP/FESOP Entry Fee |
| $5,000 |
| Supplemental Fees –Complex Sources |
| $25,000 |
| Supplemental Fees – Netting/Contemporaneous Decrease |
| $3,000/pollutant |
| Supplemental Fees – New Major PSD Source Fee |
| $12,000 |
| Supplemental Fees – New Major NANSR Source Fee |
| $20,000 |
| Supplemental Fees – Major PSD Modification Fee |
| $6,000 |
| Supplemental Fees – Major NANSR Modification Fee |
| $12,000 |
| Supplemental Fees – MACT Determination Fee |
| $5,000/unit |
| Supplemental Fees – Public Hearing Administrative Fee |
| $10,000 |
| Supplemental Fees - No Other Applicable Fee Filing Fee |
| $500 |
Source Not Subject to CAAPP/FESOP
| Base Fee – New Emission Unit |
| $500 single new emission unit |
| Base Fee – New Emission Unit |
| $1,000 more than one new emission unit |
| Base Fee – Modified Emission Unit |
| $500 no more than 2 modified emission units |
| Base Fee – Modified Emission Unit |
| $1,000 more than 2 modified emission units |
| Supplemental Fees – New Source (unpermitted) Entry Fee |
| $500 |
| Supplemental Fees – Complex Sources |
| $15,000 |
| Supplemental Fees – Public Hearing Administrative Fee |
| $10,000 |
| Supplemental Fees - No Other Applicable Fee Filing Fee |
| $500 |
Permit By Rule (PBR)
| Base Fee – CAAPP New Boiler |
| $4,000/boiler |
| Base Fee – CAAPP Modified Boiler |
| $2,000/boiler |
Other Fees
| Expedited Permit Fee |
| 4 times the standard fee, Max $100,000 |
| Asbestos Fee |
| $150/10-day notice |