260225 Attachment B - IL Cost Workbook .xlsx

XLSX spreadsheet 88 KB Posted

Attached to
Environmental Information Management System EIMS
Solicitation number
26-532EPA-FISCP-B-51295
Issued by
Illinois

About this file

This is a Cost Workbook template for a request for proposal (RFP) issued by the State of Illinois Environmental Protection Agency (IEPA) for the Environmental Information Management System (EIMS) project, identified as RFP 26-532EPA-FISCP-B-51295. The workbook is designed to standardize cost proposal submissions across all offerors by requiring the use of this template to calculate implementation deliverables, ongoing costs, and vendor role hourly rates. The project encompasses a ten-year contract term with deliverables organized across multiple service domains including Project Management, Requirements Analysis & Validation, Solution Design & Development/Configuration, Data Migration, Testing, User Training, Solution Hosting & Provisioning, Cutover/Deployment/Hypercare, Maintenance & Operations, Knowledge Transfer & Exit Transition, Multi-Vendor Integration, and Organizational Change Management. All functionalities selected in the Traceability Matrix must be included in the cost proposal and reflected in the workbook submission, with costs tied to either one-time deliverables or ongoing services aligned to the proposed work plan.

The Cost Workbook contains six primary worksheets that offerors must complete: the Total Cost Summary, which aggregates costs from all subsequent worksheets over the ten-year term; Deliverable Costs, capturing one-time implementation costs by service domain and contract year; Ongoing Costs, detailing annual expenses for solution services and maintenance operations; the Ad Hoc Rate Card, specifying hourly rates for sixteen vendor roles across three experience levels (senior, intermediate, junior) for five defined contract periods; Cost Assumptions, documenting all assumptions supporting the proposal with specific RFP references and cost impact analysis; and the BidBuy Entry worksheet, which auto-populates all costs and serves as the submission guide for formal entry into the state's procurement system. Offerors are responsible for ensuring formula accuracy prior to submission, and no cost assumptions or exceptions that conflict with the RFP terms and conditions will be subject to future negotiation once the proposal is submitted.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Introduction

State of Illinois Environmental Protection Agency
Environmental Information Management System (EIMS)
26-532EPA-FISCP-B-51295
Attachment B - Cost Workbook
Offeror:Enter Offeror Name Here
Introduction
Information & Instructions
This Cost Workbook contains multiple worksheets designed to provide an understanding of the cost model for this RFP. Offerors are to use this workbook to calculate the values of implementation deliverables, ongoing costs, and vendor role hourly rates which align with its offer. All costs associated with an offer to IEPA must be tied to either a Deliverable (worksheet 2) or Ongoing Cost (worksheet 3). Please refer to the RFP for all necessary details regarding scope, scale and complexity of this solicitation, and establish the cost proposal accordingly. All functionalities for which an Offeror has selected a Solution Method other than “Functionality Not Met” in column F of worksheet 2. Business Functionality and worksheet 3. Technical Functionality of Attachment A, Traceability Matrix, must be included in the offer and reflected in the cost proposal. In addition to these instructions, there are more information and instructions provided within subsequent worksheets of this workbook. Cells requiring Offeror data entry are in light-green highlight as shown for cell B8 above. It is the responsibility of the Offeror to ensure the accuracy of the Cost Workbook formulas prior to submission.

Note: It is important all Offerors understand that cost proposals must be developed using this workbook. Formal submission of the cost proposal will be entered into BidBuy as instructed in section C.1. and F.6. of the RFP. Utilization of this workbook ensures all Offerors are establishing cost Proposals in the same manner leading to a truer apples-to-apples comparison.

Worksheet Title
HyperlinkDescriptionInstructions
1. Total Cost SummaryThis worksheet calculates the total cost based on data entered in all subsequent worksheets.No data entry into this worksheet.
2. Deliverable CostsThis worksheet captures one-time costs for all anticipated deliverables for this RFP. Each deliverable is tied to a primary service domain. For additional detail on each deliverable, please refer to Attachment A - Traceability Matrix, worksheet 4. Services.• Enter the fixed one-time cost for each deliverable.

• Specify which year of the contract term the deliverable is anticipated to be completed and invoiced (as aligned to the proposed workplan).

3. Ongoing CostsThis worksheet is designed to elicit itemized, ongoing costs for the solution once in production (e.g., hosting/provisioning, maintenance and operations). The timing of these costs must align with the proposed workplan provided as part of the offer.• Enter fixed costs for each service requested.
4. Ad Hoc Rate CardThis worksheet is designed to collect the hourly rates for each implementation resource role.• Enter the hourly rate for each pre-populated resource role and experience level.
5. Cost AssumptionsThis worksheet shall be used by the Offeror to itemize all assumptions upon which its cost proposal is being determined/is dependent.• Provide details pertaining to any and all assumptions, expectations, and/or vendor performance parameters that have been used as the basis for the cost proposal.

• Each row should be a separate detailed assumption or expectation.

• The specific section, page, and paragraph of the Offer must be provided to support each assumption or expectation.

• If the Offeror's typical cost model does not normally charge for a specific deliverable/service provided within this workbook, please provide a statement in this worksheet regarding the Offeror's methodology (e.g., not applicable, no additional charge).

Note: Assumption that do not impact cost need not be entered here. No cost assumptions or exceptions shall be in conflict with the Terms and Conditions of this solicitation. There will be no future negotiation allowed for assumptions or exceptions not listed within this worksheet upon submission of the offer.

6. BidBuy Entry This worksheet auto-populates all costs as each subsequent worksheet is completed and provides space for capturing cost assumptions. • Verify the accuracy of the costs for each print sequence.

• Document all cost assumptions made relevant to each print sequence.

• Utilize this worksheet as your guide to entering the formal cost proposal into BidBuy.

1. Total Cost Summary

State of Illinois Environmental Protection Agency
Environmental Information Management System (EIMS)
26-532EPA-FISCP-B-51295
Attachment B - Cost Workbook
Enter Offeror Name Here
Total Cost Summary
Total Cost Summary: Ten-Year Contract TermTotal Cost by Contract Year
One Time CostsTotal Deliverable Costs12345678910
Project Management Deliverables$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Requirements Analysis & Validation Deliverables$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Solution Design & Development/Configuration Deliverables$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Data Migration Deliverables$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Testing Deliverables$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
User Training Deliverables$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Solution Hosting & Provisioning Deliverables$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Cutover/Deployment/Hypercare Deliverables$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Maintenance & Operations Deliverables$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Knowledge Transfer & Exit Transition Deliverables$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Multi-Vendor Integration Deliverables$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Organizational Change Management Deliverables$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
TOTAL Deliverable Costs$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Ongoing CostsTotal Ongoing Costs12345678910
Solution Ongoing Costs$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Maintenance and Operations Services$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
TOTAL Ongoing Costs$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
TOTAL YEARLY COST$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
TOTAL CONTRACT COST$0.00
S-126 As Needed Enhancement Plan
S-131 Exit Transition Plan
S-132 Final Acceptance Document
S-133 Knowledge Transfer Plan
S-139 Multi-Vendor Integration Plan
S-140 Organizational Change Management (OCM) Plan
S-141 Organizational Change Management Effectiveness Report
S-142 Organizational Change Readiness Assessment Report

X1A0T X1A0T X1A0T X1A0T

2. Deliverable Costs

State of Illinois Environmental Protection Agency
Environmental Information Management System (EIMS)
26-532EPA-FISCP-B-51295
Attachment B - Cost Workbook
Enter Offeror Name Here
Deliverable Costs
Information & Instructions
• Column A: Identifies the deliverables required for this RFP and resulting contract, as detailed in Attachment A - Traceability Matrix, worksheet 4. Services. The ID# assigned to each deliverable within Attachment A - Traceability Matrix is identified along with the Deliverable Name for easy cross-referencing.

• Column B: Offerors should use this column to enter the total one-time cost for each deliverable during the implementation.

• Column C: Offerors should use this column to enter the contract year the deliverable is expected to be completed and submitted for invoicing. The year entered here must align with the proposed work plan provided as part of the offer.

Note: Deliverables are required to be in a finalized state having all IEPA feedback and requested revisions applied and fully approved before an invoice can be raised.

Project Management Deliverables
Deliverable NameTotal One-time CostContract Year Completion12345678910
S-6 Project Management Plan$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
S-8 Baseline Project Schedule$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
S-11 Weekly Status Report$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
S-12 Monthly Executive Status Report$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Total Cost for Deliverable Group$ - 0$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Requirements Analysis & Validation Deliverables
Deliverable NameTotal One-time CostContract Year Completion
S-26 Requirements Validation Report$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Total Cost for Deliverable Group$ - 0$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Solution Design & Development/Configuration Deliverables
Deliverable NameTotal One-time CostContract Year Completion
S-34 Configuration Management Plan$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
S-35 Data Entry Protocol$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
S-36 Role Based Access Control (RBAC)$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
S-37 Solution Design Document$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
2-38 System Security Plan$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Total Cost for Deliverable Group$ - 0$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Data Migration Deliverables
Deliverable NameTotal One-time CostContract Year Completion
S-41 Data Transformation & Mapping Data Dictionary$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
S-42 Data Validation & Reconciliation Plan$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
S-43 Data Migration Plan$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
S-44 Data Migration Strategy$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Total Cost for Deliverable Group$ - 0$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Testing Deliverables
Deliverable NameTotal One-time CostContract Year Completion
S-45 Test Management Strategy$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
S-46 Test Plans$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
S-47 Test Results Reports$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
S-48 Test Scripts, Test Cases, Test Scenarios, and Test Data$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Total Cost for Deliverable Group$ - 0$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
User Training Deliverables
Deliverable NameTotal One-time CostContract Month Completion
S-54 User Training Plan$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
S-55 Training Curriculum & Materials$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
S-56 Training Report$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Total Cost for Deliverable Group$ - 0$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Solution Hosting & Provisioning Deliverables
Deliverable NameTotal One-time CostContract Year Completion
S-64 Downtime Processes & Protocols$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
S-65 Disaster Recovery Plan$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
S-66 Infrastructure & Solution Recovery Plan$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
S-67 Infrastructure Management Plan$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Total Cost for Deliverable Group$ - 0$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Cutover/Deployment/Hypercare Deliverables
Deliverable NameTotal One-time CostContract Year Completion
S-88 Cutover/Deployment Plan$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
S-89 Infrastructure Documentation$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
S-90 Post-Implementation Report$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
S-91 Successful Deployment Report$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Total Cost for Deliverable Group$ - 0$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Maintenance & Operations Deliverables
Deliverable NameTotal One-time CostContract Year Completion
S-96 Monthly Quality Assurance Report$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
S-97 Plan of Action & Milestones (POAM)$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
S-98 Production Support Plan$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
S-99 Release Management Plan$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
S-100 System & User Documentation$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
S-126 As Needed Enhancement Plan$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Total Cost for Deliverable Group$ - 0$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Knowledge Transfer & Exit Transition Deliverables
Deliverable NameTotal One-time CostContract Year Completion
S-131 Exit Transition Plan$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
S-132 Final Acceptance Document$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
S-133 Knowledge Transfer Plan$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Total Cost for Deliverable Group$ - 0$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Multi-Vendor Integration Deliverables
Deliverable NameTotal One-time CostContract Month Completion
S-139 Multi-Vendor Integration Plan8$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Total Cost for Deliverable Group$ - 0$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Organizational Change Management Deliverables
Deliverable NameTotal One-time CostContract Year Completion
S-140 Organizational Change Management (OCM) Plan10$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
S-141 Organizational Change Management Effectiveness Report$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
S-142 Organizational Change Readiness Assessment Report$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Total Cost for Deliverable Group$ - 0$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00

X2A0T X1A0T X1A0T X1A0T X1A0T

3. Ongoing Costs

State of Illinois Environmental Protection Agency
Environmental Information Management System (EIMS)Senior
26-532EPA-FISCP-B-51295
Attachment B - Cost Workbook
Enter Offeror Name Here
Ongoing Costs
Information & Instructions
This workbook is designed to capture the detailed pricing for Solution Services as well as Maintenance and Operations Services. Please carefully follow the instructions below to ensure accuracy and completeness in your submission.

• Column A: This column identifies the specific ongoing costs IEPA is requesting the Offeror to provide.

• Column B - K: The Offeror should use these columns to specify the annual cost per contract year as it aligns with the proposed work plan submitted as part of this offer.

Table 1 - Solution Services:

• Solution Hosting: Enter the costs related to hosting or subscription services required for the solution. Ensure these costs reflect the ongoing service fees.

• Solution Licensing: Enter the costs related to solution licensing reflective of initial set-up through full implementation and ongoing years. Ensure these costs reflect the ongoing service fees.

• Data Storage and Backup: Enter the costs related data storage and backup services from start-up through end of contract. Data storage/backup services should be implemented at start of project. Ensure these costs reflect the ongoing service fees.

• Development Environment: Enter the costs related to providing a development environment through-out the necessary project phases. Ensure these costs reflect the ongoing service fees.

• Testing Environment: Enter the costs related to providing a testing environment through-out the necessary project phases. Ensure these costs reflect the ongoing service fees.

• Training Environment: Enter the costs related to providing a training environment from start-up through end of contract. Ensure these costs reflect the ongoing service fees.

• Disaster Recovery Environment: Enter the costs related to maintaining a Disaster Recovery environment through-out the contract term. Ensure these costs reflect the ongoing service fees.

• Sub-Total Solution Costs: Verify that this field accurately sums the total costs from Solution Costs.

Table 2 - Maintenance and Operations Services:

• Maintenance and Operations Services: Provide the monthly cost associated with maintaining and operating the solution. This should include all necessary activities to ensure the solution remains functional and efficient.

• Monthly Status Report: Provide the costs associated with providing a monthly status report on performance and support of the solution.

• Sub-Total Maintenance and Operations Services Costs: Verify that this field accurately sums the total costs from Maintenance and Operations Services Costs.

Table 1 - Solution Services
ServiceAnnual Cost Year 1Annual Cost Year 2Annual Cost Year 3Annual Cost Year 4Annual Cost Year 5Annual Cost Year 6Annual Cost Year 7Annual Cost Year 8Annual Cost Year 9Annual Cost Year 10
Solution Hosting
Solution Licensing
Data Storage and Backup
Development Environment
Testing Environment
Training Environment
Disaster Recovery Environment
Sub-Total Solution Costs$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Table 2 - Maintenance and Operations Services
ServiceAnnual Cost Year 1Annual Cost Year 2Annual Cost Year 3Annual Cost Year 4Annual Cost Year 5Annual Cost Year 6Annual Cost Year 7Annual Cost Year 8Annual Cost Year 9Annual Cost Year 10
Maintenance and Operations Services
Monthly Status Report
Sub-Total Maintenance and Operations Services Costs$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
S-126 As Needed Enhancement Plan
S-131 Exit Transition Plan
S-132 Final Acceptance Document
S-133 Knowledge Transfer Plan
S-139 Multi-Vendor Integration Plan
S-140 Organizational Change Management (OCM) Plan
S-141 Organizational Change Management Effectiveness Report
S-142 Organizational Change Readiness Assessment Report

X3A0T X1A0T X1A0T X1A0T X1A0T

4. Ad Hoc Rate Card

State of Illinois Environmental Protection Agency
Environmental Information Management System (EIMS)
26-532EPA-FISCP-B-51295
Attachment B - Cost Workbook
Enter Offeror Name Here
Ad Hoc Rate Card
Information & Instructions
This worksheet pertains to specific vendor roles IEPA would like the Offeror to provide an hourly rate for. These rates are excluded from all of the services and deliverables listed throughout the other worksheets of this workbook. These rates will be utilized for any potential future enhances IEPA may request during the contract term. The Offeror should complete the below steps for each of the five (5) tables below for the identified contract term years (e.g., Table 1 is Years 1 - 3).

• Column A: Identifies the Vendor Role that may be requested during the contract term. Vendor Roles identified in section A.2.4. of the RFP have been prepopulated.

• Column B: Should be used by the Offeror to input the hourly rate for a senior level resource. (e.g., A resource who has a Bachelor's Degree with more than 5 years in the role, or more than 8 years in the role without a degree.)

• Column C: Should be used by the Offeror to input the hourly rate for a intermediate level resource. (e.g., A resource who has a Bachelor's Degree with 2-5 years in the role, or more than 5-8 years in the role without a degree.)

• Column D: Should be used by the Offeror to input the hourly rate for a junior level resource. (e.g., A resource who has a Bachelor's Degree with less than 2 years in the role, or more than 5 years in the role without a degree.)

Table 1
Years 1 - 3
Vendor RoleSenior Level ResourceIntermediate Level ResourceJunior Level Resource
Hourly RateHourly RateHourly Rate
Account Executive
Functional Lead
Project Manager
Security Engineer
Solution Architect
Technical Lead
Business Analyst
Data Architect
Database Administrator
Developer
Help Desk Level 2
Help Desk Level 3
Organizational Change Management (OCM) Leadadded 4 rows to the bottom of each table to hold all vendor roles identified in A.2. These need to be added to the bidbuy worksheet.
Quality & Testing Lead
Release Manager
Training Coordinator
Table 2
Years 4 - 5
Vendor RoleSenior Level ResourceIntermediate Level ResourceJunior Level Resource
Hourly RateHourly RateHourly Rate
Account Executive
Functional Lead
Project Manager
Security Engineer
Solution Architect
Technical Lead
Business Analyst
Data Architect
Database Administrator
Developer
Help Desk Level 2
Help Desk Level 3
Organizational Change Management (OCM) Lead
Quality & Testing Lead
Release Manager
Training Coordinator
Table 3
Years 6 - 7
Vendor RoleSenior Level ResourceIntermediate Level ResourceJunior Level Resource
Hourly RateHourly RateHourly Rate
Account Executive
Functional Lead
Project Manager
Security Engineer
Solution Architect
Technical Lead
Business Analyst
Data Architect
Database Administrator
Developer
Help Desk Level 2
Help Desk Level 3
Organizational Change Management (OCM) Lead
Quality & Testing Lead
Release Manager
Training Coordinator
Table 4
Years 8 - 9
Vendor RoleSenior Level ResourceIntermediate Level ResourceJunior Level Resource
Hourly RateHourly RateHourly Rate
Account Executive
Functional Lead
Project Manager
Security Engineer
Solution Architect
Technical Lead
Business Analyst
Data Architect
Database Administrator
Developer
Help Desk Level 2
Help Desk Level 3
Organizational Change Management (OCM) Lead
Quality & Testing Lead
Release Manager
Training Coordinator
Table 5
S-140 Organizational Change Management (OCM) Plan
S-141 Organizational Change Management Effectiveness ReportSenior Level ResourceIntermediate Level ResourceJunior Level Resource
Hourly RateHourly RateHourly Rate
Account Executive
Functional Lead
Project Manager
Security Engineer
Solution Architect
Technical Lead
Business Analyst
Data Architect
Database Administrator
Developer
Help Desk Level 2
Help Desk Level 3
Organizational Change Management (OCM) Lead
Quality & Testing Lead
Release Manager
Training Coordinator

X4A0T X1A0T X1A0T X1A0T X1A0T

5. Cost Assumptions

State of Illinois Environmental Protection Agency
Environmental Information Management System (EIMS)
26-532EPA-FISCP-B-51295
Attachment B - Cost Workbook
Enter Offeror Name Here
Cost Assumptions
Information & Instructions
The table below is designated for the Offeror to document any assumptions considered in the development of their cost proposal.

• Column A: Assigns a unique item number to each assumption or expectation.

• Column B: Specifies the section, page, and paragraph of the offer that supports each assumption or expectation.

• Column C: Details all assumptions, expectations, and/or Offeror performance parameters that form the basis of the cost proposal.

• Column D: Details the rationale for each separate assumption or expectation.

• Column E: Identifies the impact of the assumption or exception taken turns out to be invalid. If the Offeror's typical pricing model does not normally charge for a specific deliverable/service provided within this workbook, please provide a statement in this worksheet regarding the Offeror's methodology (e.g., not applicable, no additional charge).

Note: Assumptions that do not impact cost need not be entered here. No cost assumptions or exceptions shall be in conflict with the Terms and Conditions of this solicitation. There will be no future negotiation allowed for assumptions or exceptions not listed within this worksheet upon submission of the offer.

Offeror Assumptions
Item #Offer Section, Page, ParagraphDescriptionRationaleCost Impact if the Assumption Turns Out Not to be Valid
1
2
3
4
5
6
7
8
9
10
S-126 As Needed Enhancement Plan
S-131 Exit Transition Plan
S-132 Final Acceptance Document
S-133 Knowledge Transfer Plan
S-139 Multi-Vendor Integration Plan
S-140 Organizational Change Management (OCM) Plan
S-141 Organizational Change Management Effectiveness Report
S-142 Organizational Change Readiness Assessment Report

X1A0T X1A0T X1A0T X1A0T

6. BidBuy Entry

State of Illinois Environmental Protection Agency
Environmental Information Management System (EIMS)
26-532EPA-FISCP-B-51295
Attachment B - Cost Workbook
Enter Offeror Name Here
BidBuy Entry
Information & Instructions
• Please review the information below for accuracy.

• Use this information when entering your cost proposal into BidBuy, as noted in section C. of the main RFP document. The values from column F should be entered into the BidBuy as the unit cost in the same order shown below.

• Document any assumptions made when establishing the cost for each associated print sequence. These assumptions should be entered into BidBuy in alignment with each print sequence.

Note: It is important to note that all Offerors will ONLY be evaluated by the cost information on BidBuy and not this workbook.

Print SequenceYearDescriptionQuantityUOMUnit CostAssumption
10S-6 Project Management Plan1Deliverable$ - 0
20S-8 Baseline Project Schedule1Deliverable$ - 0
30S-11 Weekly Status Report1Deliverable$ - 0
40S-12 Monthly Executive Status Report1Deliverable$ - 0
50S-26 Requirements Validation Report1Deliverable$ - 0
60S-34 Configuration Management Plan1Deliverable$ - 0
70S-35 Data Entry Protocol1Deliverable$ - 0
80S-36 Role Based Access Control (RBAC)1Deliverable$ - 0
90S-37 Solution Design Document1Deliverable$ - 0
1002-38 System Security Plan1Deliverable$ - 0
110S-41 Data Transformation & Mapping Data Dictionary1Deliverable$ - 0
120S-42 Data Validation & Reconciliation Plan1Deliverable$ - 0
130S-43 Data Migration Plan1Deliverable$ - 0
140S-44 Data Migration Strategy1Deliverable$ - 0
150S-45 Test Management Strategy1Deliverable$ - 0
160S-46 Test Plans1Deliverable$ - 0
170S-47 Test Results Reports1Deliverable$ - 0
180S-48 Test Scripts, Test Cases, Test Scenarios, and Test Data1Deliverable$ - 0
190S-54 User Training Plan1Deliverable$ - 0
200S-55 Training Curriculum & Materials1Deliverable$ - 0
210S-56 Training Report1Deliverable$ - 0
220S-64 Downtime Processes & Protocols1Deliverable$ - 0
230S-65 Disaster Recovery Plan1Deliverable$ - 0
240S-66 Infrastructure & Solution Recovery Plan1Deliverable$ - 0
250S-67 Infrastructure Management Plan1Deliverable$ - 0
260S-88 Cutover/Deployment Plan1Deliverable$ - 0
270S-89 Infrastructure Documentation1Deliverable$ - 0
280S-90 Post-Implementation Report1Deliverable$ - 0
290S-91 Successful Deployment Report1Deliverable$ - 0
300S-96 Monthly Quality Assurance Report1Deliverable$ - 0
310S-97 Plan of Action & Milestones (POAM)1Deliverable$ - 0
320S-98 Production Support Plan1Deliverable$ - 0
330S-99 Release Management Plan1Deliverable$ - 0
340S-100 System & User Documentation1Deliverable$ - 0
350S-126 As Needed Enhancement Plan1Deliverable$ - 0
360S-131 Exit Transition Plan1Deliverable$ - 0
370S-132 Final Acceptance Document1Deliverable$ - 0
380S-133 Knowledge Transfer Plan1Deliverable$ - 0
398S-139 Multi-Vendor Integration Plan1Deliverable$ - 0
4010S-140 Organizational Change Management (OCM) Plan1Deliverable$ - 0
410S-141 Organizational Change Management Effectiveness Report1Deliverable$ - 0
420S-142 Organizational Change Readiness Assessment Report1Deliverable$ - 0
431Solution Hosting Annual Cost Year 11Year$0.00
441Solution Licensing Annual Cost Year 11Year$0.00
451Data Storage and Backup Annual Cost Year 11Year$0.00
461Development Environment Annual Cost Year 11Year$0.00
471Testing Environment Annual Cost Year 11Year$0.00
481Training Environment Annual Cost Year 11Year$0.00
491Disaster Recovery Environment Annual Cost Year 11Year$0.00
502Solution Hosting Annual Cost Year 21Year$0.00
512Solution Licensing Annual Cost Year 21Year$0.00
522Data Storage and Backup Annual Cost Year 21Year$0.00
532Development Environment Annual Cost Year 21Year$0.00
542Testing Environment Annual Cost Year 21Year$0.00
552Training Environment Annual Cost Year 21Year$0.00
562Disaster Recovery Environment Annual Cost Year 21Year$0.00
573Solution Hosting Annual Cost Year 31Year$0.00
583Solution Licensing Annual Cost Year 31Year$0.00
593Data Storage and Backup Annual Cost Year 31Year$0.00
603Development Environment Annual Cost Year 31Year$0.00
613Testing Environment Annual Cost Year 31Year$0.00
623Training Environment Annual Cost Year 31Year$0.00
633Disaster Recovery Environment Annual Cost Year 31Year$0.00
644Solution Hosting Annual Cost Year 41Year$0.00
654Solution Licensing Annual Cost Year 41Year$0.00
664Data Storage and Backup Annual Cost Year 41Year$0.00
674Development Environment Annual Cost Year 41Year$0.00
684Testing Environment Annual Cost Year 41Year$0.00
694Training Environment Annual Cost Year 41Year$0.00
704Disaster Recovery Environment Annual Cost Year 41Year$0.00
715Solution Hosting Annual Cost Year 51Year$0.00
725Solution Licensing Annual Cost Year 51Year$0.00
735Data Storage and Backup Annual Cost Year 51Year$0.00
745Development Environment Annual Cost Year 51Year$0.00
755Testing Environment Annual Cost Year 51Year$0.00
765Training Environment Annual Cost Year 51Year$0.00
775Disaster Recovery Environment Annual Cost Year 51Year$0.00
786Solution Hosting Annual Cost Year 61Year$0.00
796Solution Licensing Annual Cost Year 61Year$0.00
806Data Storage and Backup Annual Cost Year 61Year$0.00
816Development Environment Annual Cost Year 61Year$0.00
826Testing Environment Annual Cost Year 61Year$0.00
836Training Environment Annual Cost Year 61Year$0.00
846Disaster Recovery Environment Annual Cost Year 61Year$0.00
857Solution Hosting Annual Cost Year 71Year$0.00
867Solution Licensing Annual Cost Year 71Year$0.00
877Data Storage and Backup Annual Cost Year 71Year$0.00
887Development Environment Annual Cost Year 71Year$0.00
897Testing Environment Annual Cost Year 71Year$0.00
907Training Environment Annual Cost Year 71Year$0.00
917Disaster Recovery Environment Annual Cost Year 71Year$0.00
928Solution Hosting Annual Cost Year 81Year$0.00
938Solution Licensing Annual Cost Year 81Year$0.00
948Data Storage and Backup Annual Cost Year 81Year$0.00
958Development Environment Annual Cost Year 81Year$0.00
968Testing Environment Annual Cost Year 81Year$0.00
978Training Environment Annual Cost Year 81Year$0.00
988Disaster Recovery Environment Annual Cost Year 81Year$0.00
999Solution Hosting Annual Cost Year 91Year$0.00
1009Solution Licensing Annual Cost Year 91Year$0.00
1019Data Storage and Backup Annual Cost Year 91Year$0.00
1029Development Environment Annual Cost Year 91Year$0.00
1039Testing Environment Annual Cost Year 91Year$0.00
1049Training Environment Annual Cost Year 91Year$0.00
1059Disaster Recovery Environment Annual Cost Year 91Year$0.00
10610Solution Hosting Annual Cost Year 101Year$0.00
10710Solution Licensing Annual Cost Year 101Year$0.00
10810Data Storage and Backup Annual Cost Year 101Year$0.00
10910Development Environment Annual Cost Year 101Year$0.00
11010Testing Environment Annual Cost Year 101Year$0.00
11110Training Environment Annual Cost Year 101Year$0.00
11210Disaster Recovery Environment Annual Cost Year 101Year$0.00
1131Maintenance and Operations Services Annual Cost Year 11Year$0.00
1141Monthly Status Report Annual Cost Year 11Year$0.00
1152Maintenance and Operations Services Annual Cost Year 21Year$0.00
1162Monthly Status Report Annual Cost Year 21Year$0.00
1173Maintenance and Operations Services Annual Cost Year 31Year$0.00
1183Monthly Status Report Annual Cost Year 31Year$0.00
1194Maintenance and Operations Services Annual Cost Year 41Year$0.00
1204Monthly Status Report Annual Cost Year 41Year$0.00
1215Maintenance and Operations Services Annual Cost Year 51Year$0.00
1225Monthly Status Report Annual Cost Year 51Year$0.00
1236Maintenance and Operations Services Annual Cost Year 61Year$0.00
1246Monthly Status Report Annual Cost Year 61Year$0.00
1257Maintenance and Operations Services Annual Cost Year 71Year$0.00
1267Monthly Status Report Annual Cost Year 71Year$0.00
1278Maintenance and Operations Services Annual Cost Year 81Year$0.00
1288Monthly Status Report Annual Cost Year 81Year$0.00
1299Maintenance and Operations Services Annual Cost Year 91Year$0.00
1309Monthly Status Report Annual Cost Year 91Year$0.00
13110Maintenance and Operations Services Annual Cost Year 101Year$0.00
13210Monthly Status Report Annual Cost Year 101Year$0.00
1331-3Account Executive Senior Level Resource Hourly Rate1Hour$0.00
1341-3Functional Lead Senior Level Resource Hourly Rate1Hour$0.00
1351-3Project Manager Senior Level Resource Hourly Rate1Hour$0.00
1361-3Security Engineer Senior Level Resource Hourly Rate1Hour$0.00
1371-3Solution Architect Senior Level Resource Hourly Rate1Hour$0.00
1381-3Technical Lead Senior Level Resource Hourly Rate1Hour$0.00
1391-3Business Analyst Senior Level Resource Hourly Rate1Hour$0.00
1401-3Data Architect Senior Level Resource Hourly Rate1Hour$0.00
1411-3Database Administrator Senior Level Resource Hourly Rate1Hour$0.00
1421-3Developer Senior Level Resource Hourly Rate1Hour$0.00
1431-3Help Desk Level 2 Senior Level Resource Hourly Rate1Hour$0.00
1441-3Help Desk Level 3 Senior Level Resource Hourly Rate1Hour$0.00
1451-3Organizational Change Management (OCM) Lead Senior Level Resource Hourly Rate1Hour$0.00
1461-3Quality & Testing Lead Senior Level Resource Hourly Rate1Hour$0.00
1471-3Release Manager Senior Level Resource Hourly Rate1Hour$0.00
1481-3Training Coordinator Senior Level Resource Hourly Rate1Hour$0.00
1491-3Account Executive Intermediate Level Resource Hourly Rate1Hour$0.00
1501-3Functional Lead Intermediate Level Resource Hourly Rate1Hour$0.00
1511-3Project Manager Intermediate Level Resource Hourly Rate1Hour$0.00
1521-3Security Engineer Intermediate Level Resource Hourly Rate1Hour$0.00
1531-3Solution Architect Intermediate Level Resource Hourly Rate1Hour$0.00
1541-3Technical Lead Intermediate Level Resource Hourly Rate1Hour$0.00
1551-3Business Analyst Intermediate Level Resource Hourly Rate1Hour$0.00
1561-3Data Architect Intermediate Level Resource Hourly Rate1Hour$0.00
1571-3Database Administrator Intermediate Level Resource Hourly Rate1Hour$0.00
1581-3Developer Intermediate Level Resource Hourly Rate1Hour$0.00
1591-3Help Desk Level 2 Intermediate Level Resource Hourly Rate1Hour$0.00
1601-3Help Desk Level 3 Intermediate Level Resource Hourly Rate1Hour$0.00
1611-3Organizational Change Management (OCM) Lead Intermediate Level Resource Hourly Rate1Hour$0.00
1621-3Quality & Testing Lead Intermediate Level Resource Hourly Rate1Hour$0.00
1631-3Release Manager Intermediate Level Resource Hourly Rate1Hour$0.00
1641-3Training Coordinator Intermediate Level Resource Hourly Rate1Hour$0.00
1651-3Account Executive Junior Level Resource Hourly Rate1Hour$0.00
1661-3Functional Lead Junior Level Resource Hourly Rate1Hour$0.00
1671-3Project Manager Junior Level Resource Hourly Rate1Hour$0.00
1681-3Security Engineer Junior Level Resource Hourly Rate1Hour$0.00
1691-3Solution Architect Junior Level Resource Hourly Rate1Hour$0.00
1701-3Technical Lead Junior Level Resource Hourly Rate1Hour$0.00
1711-3Business Analyst Junior Level Resource Hourly Rate1Hour$0.00
1721-3Data Architect Junior Level Resource Hourly Rate1Hour$0.00
1731-3Database Administrator Junior Level Resource Hourly Rate1Hour$0.00
1741-3Developer Junior Level Resource Hourly Rate1Hour$0.00
1751-3Help Desk Level 2 Junior Level Resource Hourly Rate1Hour$0.00
1761-3Help Desk Level 3 Junior Level Resource Hourly Rate1Hour$0.00
1771-3Organizational Change Management (OCM) Lead Junior Level Resource Hourly Rate1Hour$0.00
1781-3Quality & Testing Lead Junior Level Resource Hourly Rate1Hour$0.00
1791-3Release Manager Junior Level Resource Hourly Rate1Hour$0.00
1801-3Training Coordinator Junior Level Resource Hourly Rate1Hour$0.00
1814-5Account Executive Senior Level Resource Hourly Rate1Hour$0.00
1824-5Functional Lead Senior Level Resource Hourly Rate1Hour$0.00
1834-5Project Manager Senior Level Resource Hourly Rate1Hour$0.00
1844-5Security Engineer Senior Level Resource Hourly Rate1Hour$0.00
1854-5Solution Architect Senior Level Resource Hourly Rate1Hour$0.00
1864-5Technical Lead Senior Level Resource Hourly Rate1Hour$0.00
1874-5Business Analyst Senior Level Resource Hourly Rate1Hour$0.00
1884-5Data Architect Senior Level Resource Hourly Rate1Hour$0.00
1894-5Database Administrator Senior Level Resource Hourly Rate1Hour$0.00
1904-5Developer Senior Level Resource Hourly Rate1Hour$0.00
1914-5Help Desk Level 2 Senior Level Resource Hourly Rate1Hour$0.00
1924-5Help Desk Level 3 Senior Level Resource Hourly Rate1Hour$0.00
1934-5Organizational Change Management (OCM) Lead Senior Level Resource Hourly Rate1Hour$0.00
1944-5Quality & Testing Lead Senior Level Resource Hourly Rate1Hour$0.00
1954-5Release Manager Senior Level Resource Hourly Rate1Hour$0.00
1964-5Training Coordinator Senior Level Resource Hourly Rate1Hour$0.00
1974-5Account Executive Intermediate Level Resource Hourly Rate1Hour$0.00
1984-5Functional Lead Intermediate Level Resource Hourly Rate1Hour$0.00
1994-5Project Manager Intermediate Level Resource Hourly Rate1Hour$0.00
2004-5Security Engineer Intermediate Level Resource Hourly Rate1Hour$0.00
2014-5Solution Architect Intermediate Level Resource Hourly Rate1Hour$0.00
2024-5Technical Lead Intermediate Level Resource Hourly Rate1Hour$0.00
2034-5Business Analyst Intermediate Level Resource Hourly Rate1Hour$0.00
2044-5Data Architect Intermediate Level Resource Hourly Rate1Hour$0.00
2054-5Database Administrator Intermediate Level Resource Hourly Rate1Hour$0.00
2064-5Developer Intermediate Level Resource Hourly Rate1Hour$0.00
2074-5Help Desk Level 2 Intermediate Level Resource Hourly Rate1Hour$0.00
2084-5Help Desk Level 3 Intermediate Level Resource Hourly Rate1Hour$0.00
2094-5Organizational Change Management (OCM) Lead Intermediate Level Resource Hourly Rate1Hour$0.00
2104-5Quality & Testing Lead Intermediate Level Resource Hourly Rate1Hour$0.00
2114-5Release Manager Intermediate Level Resource Hourly Rate1Hour$0.00
2124-5Training Coordinator Intermediate Level Resource Hourly Rate1Hour$0.00
2134-5Account Executive Junior Level Resource Hourly Rate1Hour$0.00
2144-5Functional Lead Junior Level Resource Hourly Rate1Hour$0.00
2154-5Project Manager Junior Level Resource Hourly Rate1Hour$0.00
2164-5Security Engineer Junior Level Resource Hourly Rate1Hour$0.00
2174-5Solution Architect Junior Level Resource Hourly Rate1Hour$0.00
2184-5Technical Lead Junior Level Resource Hourly Rate1Hour$0.00
2194-5Business Analyst Junior Level Resource Hourly Rate1Hour$0.00
2204-5Data Architect Junior Level Resource Hourly Rate1Hour$0.00
2214-5Database Administrator Junior Level Resource Hourly Rate1Hour$0.00
2224-5Developer Junior Level Resource Hourly Rate1Hour$0.00
2234-5Help Desk Level 2 Junior Level Resource Hourly Rate1Hour$0.00
2244-5Help Desk Level 3 Junior Level Resource Hourly Rate1Hour$0.00
2254-5Organizational Change Management (OCM) Lead Junior Level Resource Hourly Rate1Hour$0.00
2264-5Quality & Testing Lead Junior Level Resource Hourly Rate1Hour$0.00
2274-5Release Manager Junior Level Resource Hourly Rate1Hour$0.00
2284-5Training Coordinator Junior Level Resource Hourly Rate1Hour$0.00
2296-7Account Executive Senior Level Resource Hourly Rate1Hour$0.00
2306-7Functional Lead Senior Level Resource Hourly Rate1Hour$0.00
2316-7Project Manager Senior Level Resource Hourly Rate1Hour$0.00
2326-7Security Engineer Senior Level Resource Hourly Rate1Hour$0.00
2336-7Solution Architect Senior Level Resource Hourly Rate1Hour$0.00
2346-7Technical Lead Senior Level Resource Hourly Rate1Hour$0.00
2356-7Business Analyst Senior Level Resource Hourly Rate1Hour$0.00
2366-7Data Architect Senior Level Resource Hourly Rate1Hour$0.00
2376-7Database Administrator Senior Level Resource Hourly Rate1Hour$0.00
2386-7Developer Senior Level Resource Hourly Rate1Hour$0.00
2396-7Help Desk Level 2 Senior Level Resource Hourly Rate1Hour$0.00
2406-7Help Desk Level 3 Senior Level Resource Hourly Rate1Hour$0.00
2416-7Organizational Change Management (OCM) Lead Senior Level Resource Hourly Rate1Hour$0.00
2426-7Quality & Testing Lead Senior Level Resource Hourly Rate1Hour$0.00
2436-7Release Manager Senior Level Resource Hourly Rate1Hour$0.00
2446-7Training Coordinator Senior Level Resource Hourly Rate1Hour$0.00
2456-7Account Executive Intermediate Level Resource Hourly Rate1Hour$0.00
2466-7Functional Lead Intermediate Level Resource Hourly Rate1Hour$0.00
2476-7Project Manager Intermediate Level Resource Hourly Rate1Hour$0.00
2486-7Security Engineer Intermediate Level Resource Hourly Rate1Hour$0.00
2496-7Solution Architect Intermediate Level Resource Hourly Rate1Hour$0.00
2506-7Technical Lead Intermediate Level Resource Hourly Rate1Hour$0.00
2516-7Business Analyst Intermediate Level Resource Hourly Rate1Hour$0.00
2526-7Data Architect Intermediate Level Resource Hourly Rate1Hour$0.00
2536-7Database Administrator Intermediate Level Resource Hourly Rate1Hour$0.00
2546-7Developer Intermediate Level Resource Hourly Rate1Hour$0.00
2556-7Help Desk Level 2 Intermediate Level Resource Hourly Rate1Hour$0.00
2566-7Help Desk Level 3 Intermediate Level Resource Hourly Rate1Hour$0.00
2576-7Organizational Change Management (OCM) Lead Intermediate Level Resource Hourly Rate1Hour$0.00
2586-7Quality & Testing Lead Intermediate Level Resource Hourly Rate1Hour$0.00
2596-7Release Manager Intermediate Level Resource Hourly Rate1Hour$0.00
2606-7Training Coordinator Intermediate Level Resource Hourly Rate1Hour$0.00
2616-7Account Executive Junior Level Resource Hourly Rate1Hour$0.00
2626-7Functional Lead Junior Level Resource Hourly Rate1Hour$0.00
2636-7Project Manager Junior Level Resource Hourly Rate1Hour$0.00
2646-7Security Engineer Junior Level Resource Hourly Rate1Hour$0.00
2656-7Solution Architect Junior Level Resource Hourly Rate1Hour$0.00
2666-7Technical Lead Junior Level Resource Hourly Rate1Hour$0.00
2676-7Business Analyst Junior Level Resource Hourly Rate1Hour$0.00
2686-7Data Architect Junior Level Resource Hourly Rate1Hour$0.00
2696-7Database Administrator Junior Level Resource Hourly Rate1Hour$0.00
2706-7Developer Junior Level Resource Hourly Rate1Hour$0.00
2716-7Help Desk Level 2 Junior Level Resource Hourly Rate1Hour$0.00
2726-7Help Desk Level 3 Junior Level Resource Hourly Rate1Hour$0.00
2736-7Organizational Change Management (OCM) Lead Junior Level Resource Hourly Rate1Hour$0.00
2746-7Quality & Testing Lead Junior Level Resource Hourly Rate1Hour$0.00
2756-7Release Manager Junior Level Resource Hourly Rate1Hour$0.00
2766-7Training Coordinator Junior Level Resource Hourly Rate1Hour$0.00
2778-9Account Executive Senior Level Resource Hourly Rate1Hour$0.00
2788-9Functional Lead Senior Level Resource Hourly Rate1Hour$0.00
2798-9Project Manager Senior Level Resource Hourly Rate1Hour$0.00
2808-9Security Engineer Senior Level Resource Hourly Rate1Hour$0.00
2818-9Solution Architect Senior Level Resource Hourly Rate1Hour$0.00
2828-9Technical Lead Senior Level Resource Hourly Rate1Hour$0.00
2838-9Business Analyst Senior Level Resource Hourly Rate1Hour$0.00
2848-9Data Architect Senior Level Resource Hourly Rate1Hour$0.00
2858-9Database Administrator Senior Level Resource Hourly Rate1Hour$0.00
2868-9Developer Senior Level Resource Hourly Rate1Hour$0.00
2878-9Help Desk Level 2 Senior Level Resource Hourly Rate1Hour$0.00
2888-9Help Desk Level 3 Senior Level Resource Hourly Rate1Hour$0.00
2898-9Organizational Change Management (OCM) Lead Senior Level Resource Hourly Rate1Hour$0.00
2908-9Quality & Testing Lead Senior Level Resource Hourly Rate1Hour$0.00
2918-9Release Manager Senior Level Resource Hourly Rate1Hour$0.00
2928-9Training Coordinator Senior Level Resource Hourly Rate1Hour$0.00
2938-9Account Executive Intermediate Level Resource Hourly Rate1Hour$0.00
2948-9Functional Lead Intermediate Level Resource Hourly Rate1Hour$0.00
2958-9Project Manager Intermediate Level Resource Hourly Rate1Hour$0.00
2968-9Security Engineer Intermediate Level Resource Hourly Rate1Hour$0.00
2978-9Solution Architect Intermediate Level Resource Hourly Rate1Hour$0.00
2988-9Technical Lead Intermediate Level Resource Hourly Rate1Hour$0.00
2998-9Business Analyst Intermediate Level Resource Hourly Rate1Hour$0.00
3008-9Data Architect Intermediate Level Resource Hourly Rate1Hour$0.00
3018-9Database Administrator Intermediate Level Resource Hourly Rate1Hour$0.00
3028-9Developer Intermediate Level Resource Hourly Rate1Hour$0.00
3038-9Help Desk Level 2 Intermediate Level Resource Hourly Rate1Hour$0.00
3048-9Help Desk Level 3 Intermediate Level Resource Hourly Rate1Hour$0.00
3058-9Organizational Change Management (OCM) Lead Intermediate Level Resource Hourly Rate1Hour$0.00
3068-9Quality & Testing Lead Intermediate Level Resource Hourly Rate1Hour$0.00
3078-9Release Manager Intermediate Level Resource Hourly Rate1Hour$0.00
3088-9Training Coordinator Intermediate Level Resource Hourly Rate1Hour$0.00
3098-9Account Executive Junior Level Resource Hourly Rate1Hour$0.00
3108-9Functional Lead Junior Level Resource Hourly Rate1Hour$0.00
3118-9Project Manager Junior Level Resource Hourly Rate1Hour$0.00
3128-9Security Engineer Junior Level Resource Hourly Rate1Hour$0.00
3138-9Solution Architect Junior Level Resource Hourly Rate1Hour$0.00
3148-9Technical Lead Junior Level Resource Hourly Rate1Hour$0.00
3158-9Business Analyst Junior Level Resource Hourly Rate1Hour$0.00
3168-9Data Architect Junior Level Resource Hourly Rate1Hour$0.00
3178-9Database Administrator Junior Level Resource Hourly Rate1Hour$0.00
3188-9Developer Junior Level Resource Hourly Rate1Hour$0.00
3198-9Help Desk Level 2 Junior Level Resource Hourly Rate1Hour$0.00
3208-9Help Desk Level 3 Junior Level Resource Hourly Rate1Hour$0.00
3218-9Organizational Change Management (OCM) Lead Junior Level Resource Hourly Rate1Hour$0.00
3228-9Quality & Testing Lead Junior Level Resource Hourly Rate1Hour$0.00
3238-9Release Manager Junior Level Resource Hourly Rate1Hour$0.00
3248-9Training Coordinator Junior Level Resource Hourly Rate1Hour$0.00
32510Account Executive Senior Level Resource Hourly Rate1Hour$0.00
32610Functional Lead Senior Level Resource Hourly Rate1Hour$0.00
32710Project Manager Senior Level Resource Hourly Rate1Hour$0.00
32810Security Engineer Senior Level Resource Hourly Rate1Hour$0.00
32910Solution Architect Senior Level Resource Hourly Rate1Hour$0.00
33010Technical Lead Senior Level Resource Hourly Rate1Hour$0.00
33110Business Analyst Senior Level Resource Hourly Rate1Hour$0.00
33210Data Architect Senior Level Resource Hourly Rate1Hour$0.00
33310Database Administrator Senior Level Resource Hourly Rate1Hour$0.00
33410Developer Senior Level Resource Hourly Rate1Hour$0.00
33510Help Desk Level 2 Senior Level Resource Hourly Rate1Hour$0.00
33610Help Desk Level 3 Senior Level Resource Hourly Rate1Hour$0.00
33710Organizational Change Management (OCM) Lead Senior Level Resource Hourly Rate1Hour$0.00
33810Quality & Testing Lead Senior Level Resource Hourly Rate1Hour$0.00
33910Release Manager Senior Level Resource Hourly Rate1Hour$0.00
34010Training Coordinator Senior Level Resource Hourly Rate1Hour$0.00
34110Account Executive Intermediate Level Resource Hourly Rate1Hour$0.00
34210Functional Lead Intermediate Level Resource Hourly Rate1Hour$0.00
34310Project Manager Intermediate Level Resource Hourly Rate1Hour$0.00