This is an Insurance Requirements document establishing builder's risk insurance mandates for Santa Rosa County, Florida construction projects. The Contractor must obtain and maintain an "all-risk" or "special form" Builder's Risk Insurance policy for the entire duration of construction at the Contractor's expense. Coverage must equal or exceed the total construction contract amount, including any approved change orders, and must protect against loss or damage to work, materials, equipment, and supplies whether located on-site, off-site, or in transit. Santa Rosa County, its officers, employees, and agents must be named as additional insureds and loss payees, with the policy including a waiver of subrogation in favor of the County. The Contractor must provide a Certificate of Insurance and a copy of the Builder's Risk policy endorsement prior to the Notice to Proceed or commencement of any work, with documentation subject to County review and approval before work begins. Coverage must remain in effect until Santa Rosa County issues written notice of final acceptance or project completion, and the policy cannot be canceled, reduced, or allowed to lapse without thirty days' prior written notice to Santa Rosa County.

The Contractor assumes sole responsibility for all deductibles and must promptly process any claims arising under the Builder's Risk policy. All insurance proceeds must be made payable jointly to the Contractor and Santa Rosa County and applied toward repair or replacement of damaged work. These requirements apply to the Housing Reconstruction project at 8616 Baxter Road, Milton, FL 32583, with a mandatory pre-bid meeting scheduled for November 18, 2025, at 9:30 a.m., bid submissions due December 8, 2025, at 10:00 a.m. through the Santa Rosa County Procurement Portal, and a contract term of 120 consecutive calendar days after the Notice to Proceed.

View the file

Other files

Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ARTICLE VII – INSURANCE REQUIREMENTS

Section 7.1 – Builder’s Risk Insurance

a. Coverage.

The Contractor shall obtain and maintain, at its own expense, a Builder’s Risk Insurance policy for the duration of construction. The policy shall provide “all-risk” or “special form” coverage protecting against loss or damage to the work, materials, equipment, and supplies used in or incidental to the project, whether located on-site, off-site, or in transit.

b. Amount.

Coverage shall be written for no less than the total construction contract amount, including any approved change orders.

c. Named Insureds.

The policy shall name Santa Rosa County, its officers, employees, and agents as additional insureds and loss payees as their interests may appear. The policy shall include a waiver of subrogation in favor of Santa Rosa County.

d. Proof of Coverage.

Prior to issuance of the Notice to Proceed or commencement of any work, the Contractor shall furnish Santa Rosa County with a Certificate of Insurance and a copy of the Builder’s Risk policy endorsement. Work shall not commence until such documentation has been reviewed and approved by the County.

e. Deductibles and Claims.

The Contractor shall be solely responsible for any and all deductibles and shall promptly process any claims arising under the Builder’s Risk policy. Any insurance proceeds shall be made payable jointly to the Contractor and Santa Rosa County and applied toward repair or replacement of the damaged work.

f. Duration and Cancellation.

Coverage shall remain in effect until Santa Rosa County issues written notice of final acceptance or completion of the project. The policy shall not be canceled, reduced, or allowed to lapse without thirty (30) days’ prior written notice to Santa Rosa County.