Brand Name Justifcation - Miami EHRM Construction_Redacted.pdf

PDF 150 KB Posted

Attached to
EHRM Infrastructure Upgrades Construction - Miami - Project 546-20-120 Federal contract opportunity
Solicitation number
36C77624B0027
Issued by
Department of Veterans Affairs Technology Acquisition Center Austin

About this file

This document is a Justification and Approval (J&A) for Other Than Full and Open Competition (OFOC) for the EHRM Infrastructure Upgrades Construction project at the Bruce W. Carter VA Medical Center in Miami, Florida.

The procurement is for a firm-fixed price contract to complete the EHRM infrastructure upgrades, which includes the installation and programming of a physical security access control system using the Lenel system and a direct-digital control system for the HVAC using Siemens Desigo components. These brand name items are required to ensure compatibility and proper operation with the existing systems at the facility. The overall construction project is estimated to be between $20 million and $50 million and will be competed as a Service-Disabled Veteran-Owned Small Business (SDVOSB) set-aside. The Contracting Officer will determine the pricing to be fair and reasonable based on the competitive proposals received.

View the file

Other files for this federal contract opportunity

Other files attached to EHRM Infrastructure Upgrades Construction - Miami - Project 546-20-120, newest first.
File Type Posted
Wage Determination - Miami-Dade County 11-1-24.pdf PDF
36C77624B0027 0006.pdf PDF
36C77624B0027 0005.pdf PDF
Additional RFI responses - SOLICITATION 36C77624B0027 - Miami Project 546-20-120.pdf PDF
Online Bid Opening Meeting Info.docx DOCX document
36C77624B0027 0004.pdf PDF
36C77624B0027 0003.pdf PDF
52.222-33 NOTICE OF REQUIREMENT FOR PROJECT LABOR AGREEMENT.pdf PDF
RFI Responses - SOLICITATION 36C77624B0027 - Miami Project 546-20-120.pdf PDF
Q73 - Annual - Utility Building - 2023-09-25.pdf PDF
Data Racks By TR.pdf PDF
Q73 - Annual - Building 10 - 2023-09-26.pdf PDF
36C77624B0027 0002.pdf PDF
52.222-34 PROJECT LABOR AGREEMENT ALTERNATE I.pdf PDF
Q73 - Annual - Building 1 - 2023-09-29.pdf PDF
Q73 - Annual - Building 7 and 40 - 2023-09-26.pdf PDF
Q73 - Quarterly - Fisher House - 2023-12-05.pdf PDF
Wage Determination - Miami-Dade County 10-4-24.pdf PDF
Q73 - Annual - Shop Building - 2023-09-26.pdf PDF
EHRM Site Visit Sign-in Sheet.pdf PDF
Amendment 0001 9-18-2024 - 36C77624B0027 0001.pdf PDF
Miami RFI SUBMISSION SHEET - SOLICITATION 36C77624B0027.xlsx XLSX spreadsheet
21-147 100 Percent CD Dwgs.pdf PDF
Terracon Asbestos Report.pdf PDF
VHA PCRA 546-20-120 Signed.pdf PDF
Site Visit Instructions - Miami.pdf PDF
IFB 36C77624B0027.pdf PDF
Wage Determination - Miami-Dade County 8-9-24.pdf PDF
21-147 100 Percent CD Specs.pdf PDF
VAAR 852.219-75 Limitations on Subcontracting.docx DOCX document
Show all 30

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project No. 546-20-120 Project Title: EHRM Infrastructure Upgrades Construction - Miami

VHAPG Part 806.3 OFOC Page 1 of 4 Revision: 02 Effective Date: 11/15/23 Acquisition ID#: 36C776-24-AP-0335

DEPARTMENT OF VETERANS AFFAIRS

Justification and Approval (J&A) for Other Than Full and Open Competition

Acquisition Plan Action ID: 36C776-24-AP-1618

1. Contracting Activity:

Veterans Health Administration (VHA), Program Contracting Activity Central (PCAC) The proposed procurement, Invitation for Bid (IFB) 36C77624B0027, is for the EHRM Infrastructure Upgrades Construction project at the Bruce W. Carter, VA Medical Center

(VAMC), 1201 NW 16TH ST., MIAMI, FL 33125-1624

2. Nature and/or Description of the Action Being Processed:

This justification is to support the EHRM Infrastructure Upgrades Construction project at the Bruce W. Carter VAMC, that will be awarded as a firm-fixed price contract. This justification is for other than full and open competition for the procurement of certain construction materials. The use of a particular brand name for the items listed below accommodate standardization of these items throughout the facility.

a. Physical security access control system

i. Lenel Access Control System

b. Direct-digital control system for HVAC.

i. Siemens (Siemens Desigo)

3. Description of Supplies/Services Required to Meet the Agency’s Needs:

This procurement is for the EHRM Infrastructure Upgrades Construction project at the Bruce W. Carter VAMC. The scope includes everything necessary to complete the EHRM Infrastructure Upgrades Construction project that meets the requirements of the Department of Veterans Affairs. There are two (2) brand name items listed for which the VA is not able to accept equal or alternate items. The value of the items are listed below. The VAAR Construction magnitude for the entire project is between $20,000,000 and $50,000,000.

a .Physical security access control system

i. Lenel Access Control System

ii. Value:

iii. Description: Complete installation and programming of card readers and communication components matching existing to ensure and maintain proper operation of the existing physical access control system (PACS).

Safeguarding access to all areas of the medical center to only authorized personnel only.

b. Direct-digital control system for HVAC

i. Siemens Desigo

ii. Value:

iii. Description: Complete installation and programming of direct-digital control system initiating and notification appliances matching existing to ensure and maintain proper operation of the existing direct-digital control system of the HVAC system.

VHAPG Part 806.3 OFOC Page 2 of 4 Revision: 02 Effective Date: 11/15/23 Acquisition ID#: 36C776-24-AP-0335

4. Statutory Authority Permitting Other than Full and Open Competition:

(X) Only One Responsible Source and No Other Supplies or Services Will Satisfy Agency Requirements per 41 USC §3304(a)(1) as implemented by FAR 6.302-1;

( ) Unusual and Compelling Urgency per 41 USC §3304(a)(2) as implemented by FAR 6.302-2;

( ) Industrial Mobilization, Engineering, Developmental or Research Capability or Expert Services per 41 USC §3304(a)(3) as implemented by FAR 6.302-3;

( ) International Agreement per 41 USC §3304(a)(4) as implemented by FAR 6.302-4

( ) Authorized or Required by Statute per 41 USC §3304(a)(5) as implemented by FAR 6.302-5;

( ) National Security per 41 USC §3304(a)(6) as implemented by FAR 6.302-6;

( ) Public Interest per 41 USC §3304(a)(7) as implemented by FAR 6.302-7;

5. Demonstration that the Contractor’s Unique Qualifications or Nature of the

Acquisition Requires the Use of the Authority Cited Above (applicability of authority):

These items have been standardized throughout the Bruce W. Carter VAMC. Installing a different manufacturers’ systems will create significant duplication in costs for the facility, and in most cases the equipment will not function properly. The specific impact for not using the brand name items is listed below:

b. Physical security access control system

i. Tyco iSTAR

ii. Impact: Any other devices and equipment not of the existing manufacturer may not provide correct interface and operability with existing PACS. The PACS is vital for authorized personnel to access key areas to provide direct patient care and safeguard critical operations of the facility. Modifications of the existing without the correct OEM components and service can compromise the integrity of the entire system. Factory trained and authorized service must be located and supported by OEM within a limited travel time to provide emergency service support.

c. Fire alarm system

i. Siemens Desigo

ii. Impact: Any other devices and equipment not of the existing manufacturer may not provide correct interface and operability with the existing direct-digital control system. Modifications of the existing without the correct OEM components and service can compromise the integrity of the entire system.

Complete installation and programming of direct-digital control system initiating and notification appliances matching existing to ensure and maintain proper operation of the existing direct-digital control system of the HVAC system.

6. Description of Efforts Made to ensure that offers are solicited from as many potential sources as deemed practicable:

In accordance with the Competition in Contracting Act (CICA), the components listed above are identified as brand name; however, the overall procurement will be competed as a Service-Disabled Veteran-Owned Small-Business (SDVOSB) set-aside. This Justification for Other Than Full and Open Competition will be posted to Contract Opportunities with the solicitation.

VHAPG Part 806.3 OFOC Page 3 of 4 Revision: 02 Effective Date: 11/15/23 Acquisition ID#: 36C776-24-AP-0335

7. Determination by the CO that the Anticipated Cost to the Government will be Fair and Reasonable:

The Government estimate was prepared by the VA team and confirmed by the Contracting Officer’s Representative (COR). The anticipated price to the Government for the items requested to be brand name is approximately .

The items for which brand name approval is being requested are subsequent components to the overall construction project. This procurement will be competed and based on competition; the CO will make a determination of fair and reasonable pricing prior to award.

8. Description of the Market Research Conducted and the Results, or a Statement of the Reasons Market Research Was Not Conducted:

The market research for the equipment was conducted and prepared by the COR and shared with the CO for further review. The CO was in concurrence with information provided in the estimate that supported the brand name items. Approval of the items as brand name only is critical for the overall efficiency of the completed project and the entire Bruce W.

Carter VAMC.

9. Any Other Facts Supporting the Use of Other than Full and Open Competition:

The new components (software and servers) must be able to tie into the existing and operational systems including the use of existing hardware. At this time, there are no competing vendors who have the programming rights to the systems, and products must be fully compatible with the existing systems being used at the Bruce W. Carter VAMC.

10. Listing of Sources that Expressed, in Writing, an Interest in the Acquisition:

Not applicable. It is the responsibility of the offerors and the general contractor awarded the project to locate suppliers and obtain pricing for all materials and components, including the items listed in this justification.

11. A Statement of the Actions, if any, the Agency May Take to Remove or Overcome any

Barriers to Competition before Making subsequent acquisitions for the supplies or services required:

There will be competition for the overall procurement. It will be the responsibility of the offerors to obtain pricing from the suppliers of the items and to submit a competitive proposal for the project.

12. Requirements Certification: I certify that the requirement outlined in this justification is a Bona Fide Need of the Department of Veterans Affairs and that the supporting data under my cognizance, which are included in the justification, are accurate and complete to the best of my knowledge and belief.

NAME: Jose Gonzalez Date TITLE: Healthcare Engineer FACILITY: Bruce W. Carter VAMC

VHAPG Part 806.3 OFOC Page 4 of 4 Revision: 02 Effective Date: 11/15/23 Acquisition ID#: 36C776-24-AP-0335

13. Approvals in accordance with the VHAPM Part 806.3 OFOC SOP:

a. Contracting Officer Certification (required): I certify that the foregoing justification is accurate and complete to the best of my knowledge and belief.

Bridget May Date Contracting Officer Program Contracting Activity Central

b. One Level Above the Contracting Officer (Required over SAT but not exceeding

$750K): I certify the justification meets requirements for other than full and open competition.

Donald A. Marsh III Date

Supervisory Contracting Officer Program Contracting Activity Central

BRIDGET MAY Digitally signed by BRIDGET MAY Date: 2024.08.19 12:47:54 -04'00'

DONALD MARSH Digitally signed by DONALD MARSH Date: 2024.08.19 13:32:49 -04'00'

File details come from the government source that posted it. Updated .