BP-00048_PROJECT_STARTUP_REV_0_-_12.09.24_Signed.pdf

PDF 793 KB Posted

Attached to
Orlando Executive Airport (ORL) East Ramp Rehabilitation - Phase 1 (BP-00048)
Solicitation number
25-598-IFB
Issued by
Orange County, Orlando City, Florida

About this file

This Project Start-Up Package (PAF) for the Greater Orlando Aviation Authority details the BP-00048-ORL project for the Orlando Executive Airport East Ramp Rehabilitation - Phase 1. The project involves rehabilitating a portion of the existing asphalt pavement at the East Ramp, including airplane tie-downs, drainage systems, markings, and lighting. The project is scheduled to be advertised on 04/01/25, with a pre-bid meeting on 04/09/25 and bid opening on 05/06/25. The anticipated construction Notice to Proceed (NTP) is 11/21/25, with substantial completion expected by 03/20/26 (120 calendar days) and final completion by 05/19/26 (60 calendar days after substantial completion).

The project has a total control budget of $264,872.50, with funding sources including FDOT and ORL Revenue Fund. The proposed delivery method is Traditional Design/Bid/Award, with Mead & Hunt, Inc. as the A/E (Architect/Engineer) and Loyal Wingman, LLC as the OAR (Owner's Authorized Representative) for both design and construction phases. The project is classified as high priority with a 20-year life expectancy. No Dispute Review Board (DRB) requirement is anticipated, and no specific permits are currently identified. The project will be managed through the Facilities Improvements Projects (FIP) program for the Orlando Executive Airport.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROJECT ASSESSMENT FORM (PAF) Coding by Construction Finance :

DATE:

TO:

FROM:

SUBJECT:

Short Name:

Template:

Campus:

Cost Center:

Organization:

Program:

Subprogram:

December 9, 2024

Kevin J. Thibault, P.E, Chief Executive Officer

Tuan N. Nguyen, Assistant Vice President, Engineering

Project Start-Up

BP-00048-ORL ORL EAST RAMP REHABILITATION - PHASE 1

Orlando Executive Airport

PROGRAM: Facilities Improvements Projects / Orlando Executive Airport Projects (FIP)

DESCRIPTION OF PROJECT: SPONSOR: Orlando Executive Airport

This project rehabilitates a portion of the existing asphalt pavement at the East Ramp of the Orlando Executive Airport, as identified in the FDOT Airfield Pavement Management Program Report. It also includes rehabilitating airplane tie-downs, drainage systems, markings, and lighting as called for within the immediate or surrounding area.

LIFE EXPECTANCY OF PROJECT: 20 Years

FUNDING: FDOT,ORL Revenue Fund

PROPOSED DELIVERY METHOD: (Proposed)

A/E: Mead & Hunt, Inc.

Traditional Design / Bid / Award

Loyal Wingman, LLC

Loyal Wingman, LLCOAR Constr. Phase:

OAR Design Phase:

Construction:

SCHEDULE: (See Details under "CURRENT STATUS" Below)

Advertise:

Pre-Bid Conference:

Bid Opening:

Ant. Notice to Proceed:

Ant. Subst. Completion:

Ant. Final Completion:

11/21/2025

03/20/2026

05/19/2026

120 Calendar Days

60 Calendar DaysPROJECT PRIORITY: High Priority

FAA/AIP

FDOT

PFCs

Authority Funds

Other Funds

TOTAL

Comments by Construction Finance

$ Amount $ FUNDED $ UNFUNDED Comments $19,804.00

$0.00

$0.00 $12,500.00

$0.00 $0.00

CONTROL BUDGET:

Task A/E Consultant Fees - Bid & Award A/E Consultant Fees - Construction Phase (Base) Construction OAR Fees - Bid & Award OAR Fees - Construction Phase Miscellaneous Contingency $232,568.50

BY CONSTRUCTION FINANCE:

TOTAL $264,872.50

CC: Fully executed copy will be posted to \GROUPS\CONST_ENG\PDF- Start-Up Packages\

Greater Orlando Aviation Authority - Engineering & Construction (Project Start-Up Package) BP-00048-ORL Page 1 of 3

PROJECT START-UP PACKAGE FOR BP-00048-ORL

DRB (DISPUTE REVIEW BOARD):

DRB requirement IS NOT anticipated.

SYSTEMS / AREAS AFFECTED:

ANTICIPATED PERMITS:

Agency : Type Of Permit: Permit No: Issued: Expires: Final: Comments: Address:

PERMITS

NONE

CURRENT STATUS:

FUNDING: FDOT, OEA Revenue Fund

TENTATIVE SCHEDULE:

01/07/25 C.C. Recommendation of A/E Negotiated Fee

02/19/25 Receive approval A/E Negotiated Fees from Board (If>$250k)

03/04/25 Contract Execution & Design NTP

03/28/25 Receive approval to bid

04/01/25 Advertise for bids

04/09/25 Pre-bid meeting

05/06/25 Bid opening

05/27/25 Receive Recommendation to award from CC

10/24/25 Receive Approval to award from Board (If > $250k)

11/07/25 Complete contract execution

11/21/25 Issue Construction NTP (effective date)

03/20/26 Substantial Completion (120 cal. days from NTP)

05/19/26 Final Completion (60 cal. days from Subst.)

CC: Fully executed copy will be posted to \GROUPS\CONST_ENG\PDF- Start-Up Packages\

Greater Orlando Aviation Authority - Engineering & Construction (Project Start-Up Package) BP-00048-ORL Page 2 of 3

REVIEWED BY:

ENGINEERING & CONSTRUCTION SENIOR STAFF:

Scott Shedek, Vice President, Construction

Max E. Marble, Senior Vice President, Capital Programs

Date:

Date:

Date:

If signing as a Temporary Designee, attach a copy of authorization memo (or e-mail)

Tuan N. Nguyen, Assistant Vice President, Engineering

Date:

SPONSORING DEPARTMENT (CONSTRUCTION)

Robert Furr, Vice President, Engineering and Architecture

CC: Fully executed copy will be posted to \GROUPS\CONST_ENG\PDF- Start-Up Packages\

Greater Orlando Aviation Authority - Engineering & Construction (Project Start-Up Package) BP-00048-ORL Page 3 of 3

File details come from the government source that posted it. Updated .