This is an acquisition timeline document for a Business and Logistics Management Support Services (BL/MSS) procurement, structured as a 100% Small Business Set-Aside using GSA Multiple Award Schedule (MAS) SIN 541611. The procurement will follow competitive procedures under FAR 8.405-3 and 8.405-5.

The timeline outlines key dates from solicitation release on April 11, 2025, through contract award on October 22, 2025. The procurement follows a two-phase approach, with Phase 1 proposals due May 12, 2025, and Phase 2 proposals due 15 days after issuance of advisory notification on June 25, 2025. Evaluation completions are scheduled for June 6, 2025 (Phase 1) and August 11, 2025 (Phase 2). The approval process includes multiple review stages totaling approximately 60 days, including Contracting Officer, Office of General Counsel, COCO Review, and HCA review. The procurement requires Department of Labor Equal Employment Opportunity Clearance (for actions over $10M) by September 2, 2025, and DHS Congressional Notification (for actions over $4M) by October 21, 2025. Debriefings will be completed between October 27-31, 2025.

View the file

Other files for this federal contract opportunity

Show all 15

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT 2

ACQUISITION TIMELINE

BUSINESS AND LOGISTICS MANAGEMENT SUPPORT SERVICES

(BL/MSS)

DRAFT ACQUISITION STRATEGY: 100% Small Business Set-Aside to Capable Small Business Contract Holders utilizing GSA Multiple Award Schedule (MAS)

Special Item Number (SIN) 541611 in accordance with the competitive procedure’s requirements of FAR Subparts 8.405-3 and 8.405-5.

Solicitation Released April 11, 2025

Proposals/Quotes Received

Phase One 1:

May 12, 2025

Phase 2: Due 15 Days After Issuance Advisory Notification June 25, 2025

Evaluation of Proposals/Quotes Complete

Phase 1:

June 6, 2025

Phase 2: 30 – 45 Days after quotes received

August 11, 2025

Acquisition Reviews & Approvals: Contracting Officer (3 days), Office of General Counsel (10 days), Level Above Review (5 days), COCO Review (5 days), CG 913 (3 days), HCA (10 days)

60 Days approximately October 13, 2025

Department of Labor Equal Employment Opportunity Clearance Complete ($10M and above), if applicable

September 2, 2025

DHS Unique Congressional Notification of Award in Accordance with HSAM 3005.303-70 (5-Day Advance Notice/Actions > $4M)

October 21, 2025

Contract Award October 22, 2025

Notification of Unsuccessful Offerors October 22, 2025

Notification of Award October 22, 2025

Debriefing Complete October 27 – 31, 2025